Find

  • All tenders
Germany: Tenders/Trianel Windkraftwerk Borkum II GmbH & Co. KG/20251127

20251127

Published deadline passed

The published deadline has passed. For multi-stage competitions a later tender deadline may still apply — check the notice or portal for the current phase.

Qualification deadline
Jan 16,Expired
Award
Quality Award Criteria, weight 30
Procedure
With negotiationTwo stages
Agreement
Buying servicesover 2 years

Brief

The tender covers the replacement and disposal of hydraulic hoses on 32 offshore crane systems (16 units per year), as well as optional services related to oil maintenance/replacement and the procurement of materials required for these activities. In addition, and optionally the assessment, planning, and execution of local repair activities for selected components on offshore crane and transition piece structures, in connection with the scope of work defined in SOW1, is planned. Furthermore, a technical evaluation and the development of potential repair methods and long-term maintenance concept is included.

Register interest

Previous winners

  • Who are you up against?

    The suppliers who have won similar contracts at Trianel Windkraftwerk Borkum II GmbH & Co. KG

Will you bid?

The agent sets up the bid and writes the first draft. Free for 14 days.

Qualification requirements

  • Description

    Leverandøren skal ha tiltak for å sikre kvalitet.

    Documentation Requirement

    Se konkurransedokumentene (søknadsdokumentet).

    Source

    No source found in the documents. Check the requirement against the tender documents.

Award Criteria

  • Description

    see tender documents

    Source

    No source found in the documents. Check the weight against the tender documents.

  • Description

    see tender documents

    Source

    No source found in the documents. Check the weight against the tender documents.

From the notice

  • The tender covers the replacement and disposal of hydraulic hoses on 32 offshore crane systems (16 units per year), as well as optional services related to oil maintenance/replacement and the procurement of materials required for these activities. In addition, and optionally the assessment, planning, and execution of local repair activities for selected components on offshore crane and transition piece structures, in connection with the scope of work defined in SOW1, is planned. Furthermore, a technical evaluation and the development of potential repair methods and long-term maintenance concept is included.

  • Contact

    m.gosse@trianel.com
  • Type
    Competition · Prequalification
  • Main code
    Offshore installation services
    76521000

Similar active competitions

  • Infrastruktur Windkraftwerk Borkum GmbH & Co. KG

    Air Conditioning Units Exchange

    Infrastruktur Windkraftwerk Borkum GmbH & Co. KG needs air conditioning units procured and installed on an offshore platform at the Trianel Windpark Borkum in Germany. Bidders must hold valid ISO 9001, ISO 14001 and ISO 45001 certifications; have at least three employees with valid ChemKlimaschutzV and EU F-gas competence certificates, or equivalents; and be qualified and authorized to install air-conditioning units in explosion-protected areas. They must also demonstrate work on at least five offshore projects in the past three years. Offers will be evaluated on price (70%) and quality (30%).

    Competition with qualification
    Dec 21, 2026(29 days)
  • TenneT Offshore GmbH

    Elektrisk infrastruktur og veibelysning

    Betriebunterstützungsvereinbarung Offshore (BUV)

    TenneT Offshore GmbH sucht im Rahmen einer Dienstleistungs-Rahmenvereinbarung Betriebsunterstützung für Offshore-Netzanlagen und Netzanbindungssysteme; der maximale Gesamtwert beträgt 47 Millionen Euro, die Vertragslaufzeit ist nicht angegeben. Der Auftrag umfasst drei Segmente: Offshore-Logistikmanagement für Material- und Entsorgungsflüsse, Projektmanagement für Instandhaltungs- und Optimierungsprojekte an Bestandsanlagen sowie Dokumentenmanagement zur Sicherstellung vollständiger und qualitätsgesicherter Anlagendokumentation. Die Leistungen sind für den Standortbereich Region Hannover vorgesehen. Erforderlich sind mindestens zwei vergleichbare Referenzprojekte je Segment aus den letzten zehn Jahren: für Logistikprojekte jeweils mindestens 1 Million Euro Auftragswert, sechs Vollzeitkräfte und zwei Jahre Laufzeit; für Projektmanagement technische Offshore- oder Energieinfrastrukturprojekte an Bestandsanlagen mit mindestens 1 Million Euro Projektvolumen und zwölf Monaten Laufzeit; für Dokumentenmanagement jeweils mindestens 250.000 Euro Auftragswert, zwei Vollzeitkräfte und zwei Jahre Laufzeit. Zusätzlich ist ein Jahresumsatz von mindestens 8 Millionen Euro durch Geschäftsberichte der letzten drei Jahre nachzuweisen. Bewertet werden Preis (50 %), technisches Konzept (30 %) sowie Vertragsbedingungen und Verteilung der Vertragsrisiken (20 %).

    Framework agreement with qualification
    Dec 1, 2026(9 days)
    €47,000,000
  • Havenbedrijf Rotterdam

    Fartøyvedlikehold og verftstjenester

    Overeenkomst Onderhoud Hydraulische Installaties

    Havenbedrijf Rotterdam heeft behoefte aan onderhoudsdiensten voor hydraulische installaties aan boord van hun vaartuigen, middels een raamovereenkomst met een looptijd van 8 jaar en een maximale totale waarde van 1 EUR. De opdracht omvat preventief en correctief onderhoud, inspecties, keuringen, ondersteuning bij certificering, en onderhoudsgerelateerde dienstverlening zoals analyse, advisering en rapportage, met als doel bij te dragen aan levensduurverlenging en optimalisatie van de installaties.

    Framework agreement
    Jan 1, 2027(40 days)
    €1