A-21/25; Izdelava DGD in PZI izvennivojskega križanja deviacije regionalne ceste R3-679/3909 čez glavno železniško progo št. 10 državna meja Dobova–Ljubljana
Awarded
The competition has ended and a winner has been selected.
- Award
- Kakovost, weight 40
- Agreement
- Buying servicesover 300 days
Brief
MINISTRSTVO ZA INFRASTRUKTURO, DIREKCIJA REPUBLIKE SLOVENIJE ZA INFRASTRUKTURO je sklenilo pogodbo s PNZ svetovanje projektiranje d.o.o. za storitve izdelave DGD in PZI izvennivojskega križanja deviacije regionalne ceste R3-679/3909 čez glavno železniško progo št. 10 državna meja Dobova–Ljubljana. Projekt se bo izvajal v regiji Posavska in bo trajal 300 dni, s končno vrednostjo pogodbe 339.975 EUR. Pri izbiri ponudnika sta bila upoštevana cena (60 %) in kakovost (40 %). Na razpis je prispelo 6 ponudb.
Consulting engineers RWA (Road, Water, Wastewater)
Result
- PNZ svetovanje projektiranje d.o.o.Winner
- 0Number of tenders received
- €339,975Contract value
Previous winners
Who are you up against?
The suppliers who have won similar contracts at MINISTRSTVO ZA INFRASTRUKTURO, DIREKCIJA REPUBLIKE SLOVENIJE ZA INFRASTRUKTURO
Will you bid?
The agent sets up the bid and writes the first draft. Free for 14 days.
Award Criteria
Description
Kot je navedeno v razpisni dokumentaciji
Source
No source found in the documents. Check the weight against the tender documents.
Description
Kot je navedeno v razpisni dokumentaciji
Source
No source found in the documents. Check the weight against the tender documents.
From the notice
Izdelava DGD in PZI izvennivojskega križanja deviacije regionalne ceste R3-679/3909 čez glavno železniško progo št. 10 državna meja Dobova–Ljubljana
Contact
jn.drsi@gov.si- ResultType
- PosavskaLocation
- 71000000Main codeArchitectural, construction, engineering and inspection services
- 71242000Project and design preparation, estimation of costs71322000Engineering design services for the construction of civil engineering works71322500Engineering-design services for traffic installations