Find

  • All tenders
Germany: Tenders/AquaDuctus Pipeline GmbH/AquaDuctus Geotechnical and Geophysical Surveys

AquaDuctus Geotechnical and Geophysical Surveys

Published deadline passed

The published deadline has passed. For multi-stage competitions a later tender deadline may still apply — check the notice or portal for the current phase.

Qualification deadline
Nov 13, 2025Expired
Procedure
With negotiationTwo stages
Agreement
Buying services

Brief

AquaDuctus Project: Geotechnical & geophysical surveys To address Europe's future energy demand, significant investments into hydrogen infrastructure are essential. One of the core components of this initiative is the development of a pan-European hydrogen pipeline network in the North Sea, designed to connect major hydrogen producers with key consumers across the continent.?AquaDuctus is Part of this future pipeline network. AquaDuctus project consists of an offshore part (Exclusive Economic Zone (EEZ) and territorial waters of the German North Sea and a receiving terminal at the coastline of Lower Saxony) and an onshore part to make connection with the onshore grid. AquaDuctus is planned as a large diameter pipeline (48 inch) with a transport capacity of 20 GWH2 and a design pressure of 120 bara. The conceptual design of the pipeline enables the connection of neighbouring European hydrogen infrastructures and the planned production facilities in the German EEZ (SEN-1 Area). The procurement item consists of four lots. On the offshore part of the project (Lot 1 and Lot 2) the pipeline is expected to be mostly buried in the seabed and the crossing of the shore will be done via tunnelling. For the offshore part there are two sections to be considered. Section I extends from shore to the area of SEN-1. Section II extends from SEN-1 to the end of the German EEZ. Section II is an option in this procurement procedure and may only be awarded together with Section I. For the purposes of the offer evaluation, the contents of Section I and II will be considered. The evaluation of Sections I and II for the respective services (Scope of Work packages A and B) is based on an equal weighting of 50% each. Due to administrative requirements, separate approval is necessary for Section II, therefore it is designated as an optional position. Lot 3 covers the geophysical and geotechnical surveys needed for the project section in shallow waters. Lot 4 covers the geotechnical surveys needed for the tunnel section of AquaDuctus pipeline. Owner of the Project (Client) is the AquaDuctus Pipeline GmbH. GASCADE Gastransport GmbH is acting as General Service Provider for the AquaDuctus Pipeline GmbH and will be responsible for the surveys.

Miljøovervåking og naturvitenskapelige tjenester

Register interest

Previous winners

  • Who are you up against?

    The suppliers who have won similar contracts at AquaDuctus Pipeline GmbH

Will you bid?

The agent sets up the bid and writes the first draft. Free for 14 days.

Qualification requirements

  • Description

    Proof of registration in the professional or commercial register must be attached in accordance with the legal provisions of the country in which the tenderer is based, provided that the tenderer is registered in the professional or commercial register. In case of non-registration: The submission of a business registration (for foreign tenderers: or equivalent). The proof must identify at least the persons authorized to represent the company.

    Documentation Requirement

    The proof may be submitted in (non-certified) photocopy/photocopy (PDF) but must be clearly legible and formulated in German or English (if necessary, translated). The proof must not be older than 12 months at the time of publication of this announcement. Refer to Attachment A.1 Forms and Proofs (Eligibility), Proof 1.

    Source

    No source found in the documents. Check the requirement against the tender documents.

  • Description

    Declaration of the absence of Exclusion Grounds according to §§ 123, 124 GWB. The proof of self-cleaning measures according to § 125 GWB is possible.

    Documentation Requirement

    See Attachment A.1 Forms and Certificates (Eligibility), Form 3.1 (or Form 3.2).

    Source

    No source found in the documents. Check the requirement against the tender documents.

  • Description

    Self-declaration (Sanctions against Russia).

    Documentation Requirement

    See Attachment A.1 Forms and Proofs (Eligibility), Form 8.

    Source

    No source found in the documents. Check the requirement against the tender documents.

  • Description

    Self-declaration of the company's annual turnover of the last 3 (three) completed financial years relating to services comparable to the services to be awarded. If a company was established within the last three years and therefore does not yet have three completed financial years, it shall submit a business plan indicating the expected annual turnover. Minimum requirement (failure to meet will result in exclusion): The average turnover over the last three (3) completed financial years must amount in EUR (net) at least: For lot 1: At least EUR 4 million (net) For lot 2: At least EUR 4 million (net) For lot 3: At least EUR 4 million (net) For lot 4: At least EUR 4 million (net)

    Documentation Requirement

    See Attachment A.1 (Forms and Proofs (Eligibility), Form 6).

    Source

    No source found in the documents. Check the requirement against the tender documents.

  • Description

    Proof of experience in the field of services to be awarded per lot is required by providing at least three (3) reference contracts within the last maximum ten (10) years that are comparable in type, scope, and complexity to the service being tendered. The references must relate to: Lot 1: Offshore geophysical survey in water depths varying between 15 and 41 metres. The applicant must provide that the surveys stated under the references directly correspond to and fulfill the requirements stated in the Attachment B.1.1 Scope of Work Package A (Lot 1). The references demonstrate the applicant's knowledge of marine environmental actors and associated logistical considerations. Cable or pipeline route survey of similar size (~50km route length). Lot 2: Offshore geotechnical survey in water depths varying between 15 and 41 metres. The applicant must provide evidence that the surveys stated under the references directly correspond to and fulfill the requirements stated in the Attachment B.1.2 Scope of Work Package B (Lot 2). The references demonstrate the applicant's knowledge of marine environmental actors and associated logistical considerations. Cable or pipeline route survey of similar size (~50km route length). Lot 3: Shallow water geophysical and geotechnical survey in water depths varying from 15 meters to shore (top of beach line). The applicant must provide that the surveys stated under the references directly correspond to and fulfill the requirements stated in the Attachment B.1.3 Scope of Work Package C (Lot 3). The references demonstrate the applicant's knowledge of marine environmental actors and associated logistical considerations. Cable or pipeline route survey of similar size (~20km route length). The reference shows that the applicant is familiar with conducting surveys in military or otherwise restricted zones. Lot 4: Geotechnical survey with a survey area including two dry sections, the foreland areas and the intertidal mud flats. The applicant must provide that the surveys stated under the references directly correspond to and fulfill the requirements stated in the Attachment B.1.4 Scope of Work Package D (Lot 4). The references demonstrate the applicant's knowledge of environmental factors of the intertidal mud flat and dry sections and associated logistical considerations. The references show that the applicant is familiar with conducting surveys in the national park - Wadden Sea. Minimum requirement (failure to meet will result in exclusion): For Lot 1, at least 3 particularly relevant (comparable) references must be submitted. For Lot 2, at least 3 particularly relevant (comparable) references must be submitted. For Lot 3, at least 3 particularly relevant (comparable) references must be submitted. For Lot 4, at least 3 particularly relevant (comparable) references must be submitted. If one reference is comparable with several lots, the reference can be submitted for multiple lots.

    Documentation Requirement

    The references must include at least the following information to demonstrate comparability: Reference title Client (contracting authority) (If the client may not be named for data protection reasons, it is sufficient to categorize the client (research, industry, other sectors of the contracting entity)). Contact person incl. contact details (e.g., email, phone number) (If the contact person may not be named for data protection reasons, it is sufficient to categorize the client (research, industry, other sectors client)). A brief description of the services performed including confirmation that the reference is comparable to the services tendered. Contract value in EUR (net) Execution period. See Attachment A.1 (Forms and Proofs (Eligibility), Form 7).

    Source

    No source found in the documents. Check the requirement against the tender documents.

  • Description

    The applicant will receive extra points for each reference that fulfils the requirements of Lot 1 mentioned in Attachment A.5.

    Documentation Requirement

    Note: The below mentioned Weighting of 250 points is a placeholder. Please refer to Attachment A.5.

    Source

    No source found in the documents. Check the requirement against the tender documents.

From the notice

  • AquaDuctus Project: Geotechnical & geophysical surveys To address Europe's future energy demand, significant investments into hydrogen infrastructure are essential. One of the core components of this initiative is the development of a pan-European hydrogen pipeline network in the North Sea, designed to connect major hydrogen producers with key consumers across the continent.?AquaDuctus is Part of this future pipeline network. AquaDuctus project consists of an offshore part (Exclusive Economic Zone (EEZ) and territorial waters of the German North Sea and a receiving terminal at the coastline of Lower Saxony) and an onshore part to make connection with the onshore grid. AquaDuctus is planned as a large diameter pipeline (48 inch) with a transport capacity of 20 GWH2 and a design pressure of 120 bara. The conceptual design of the pipeline enables the connection of neighbouring European hydrogen infrastructures and the planned production facilities in the German EEZ (SEN-1 Area). The procurement item consists of four lots. On the offshore part of the project (Lot 1 and Lot 2) the pipeline is expected to be mostly buried in the seabed and the crossing of the shore will be done via tunnelling. For the offshore part there are two sections to be considered. Section I extends from shore to the area of SEN-1. Section II extends from SEN-1 to the end of the German EEZ. Section II is an option in this procurement procedure and may only be awarded together with Section I. For the purposes of the offer evaluation, the contents of Section I and II will be considered. The evaluation of Sections I and II for the respective services (Scope of Work packages A and B) is based on an equal weighting of 50% each. Due to administrative requirements, separate approval is necessary for Section II, therefore it is designated as an optional position. Lot 3 covers the geophysical and geotechnical surveys needed for the project section in shallow waters. Lot 4 covers the geotechnical surveys needed for the tunnel section of AquaDuctus pipeline. Owner of the Project (Client) is the AquaDuctus Pipeline GmbH. GASCADE Gastransport GmbH is acting as General Service Provider for the AquaDuctus Pipeline GmbH and will be responsible for the surveys.

  • Contact

    vergabe@gascade.de
  • Type
    Competition · Prequalification
  • Main code
    Geotechnical engineering services
    71332000

Similar active competitions

  • AquaDuctus Pipeline GmbH

    Avfallshåndtering

    TP4 - Benthic (Benthos) Survey (TW and EEZ)

    AquaDuctus Pipeline GmbH needs benthic (benthos) survey services in territorial waters and the exclusive economic zone. The supplier must be able to undertake environmental surveys and demonstrate experience with environmental impact assessment and permitting for linear infrastructure projects in Germany, including familiarity with German approval planning, permitting requirements and coordination with German authorities. Applicants must document at least 10 relevant permanent employees at the executing office, an average annual turnover of at least €1.5 million in each of the last three completed financial years, and at least three comparable EIA reference contracts from the last 15 years, each worth at least €100,000.

    Competition with qualification
    Dec 14, 2026(19 days)
  • AquaDuctus Pipeline GmbH

    Miljøovervåking og naturvitenskapelige tjenester

    Bodenuntersuchungsbohrungen sowie die Durchführung von Konusdrucksondierungen mit Porenwasserdruckmessung (PCPT) und die damit verbundenen geotechnischen Laboruntersuchungen. Es sind zwei geotechnische Bohrungen bis zu einer Tiefe von ca. 30 m unterhalb der Schlammlinie/des Meeresbodens durchzuführen. Die Standorte der Bohrungen befinden sich nördlich der Insel Norderney.

    Die AquaDuctus Pipeline GmbH plant die Beschaffung von geotechnischen Ingenieurdienstleistungen, die Bodenuntersuchungsbohrungen, Konusdrucksondierungen mit Porenwasserdruckmessung (PCPT) und geotechnische Laboruntersuchungen umfassen, um Bodenschichten und geotechnische Parameter für die Tunnelplanung zu identifizieren. Lieferanten können Feedback geben, indem sie per E-Mail an vergabe@gascade.de mitteilen, ob eine Durchführung grundsätzlich möglich ist und zu welchem frühestmöglichen Termin diese erfolgen könnte.

    Planning
  • TenneT Offshore GmbH

    Geotekniske undersøkelser

    Qualification System Marine Surveys

    This qualification system shall cover the provision of marine geophysical, geotechnical and UXO surveys as well as IRM in the German North Sea and Wadden Sea (German EEZ and German territorial waters): • Lot 1 – Marine Geophysical Surveys Offshore • Lot 2 – Marine Geophysical Surveys Nearshore • Lot 3 – Marine Geotechnical Surveys Offshore • Lot 4 – Marine Geotechnical Surveys Nearshore • Lot 5 – General Engineering Survey – integrated geophysical and geotechnical survey and cable tracking Offshore • Lot 6 – General Engineering Survey – integrated geophysical and geotechnical survey and cable tracking Nearshore • Lot 7 – IRM Structural Inspections • Lot 8 – UXO Survey and ID&C Offshore • Lot 9 – UXO Survey an ID&C Nearshore • Lot 10 – UXO Survey Offshore • Lot 11 – UXO Survey Nearshore • Lot 12 – UXO ID&C Offshore • Lot 13 – UXO ID&C Nearshore Applicants have to answer the questionnaire in Mercell https://s2c.mercell.com/today/77318. The questionnaires give you an overview of the information and documents we need for the first part of the application process. Questions 1. “General Questions” and 2. “Health, Safety & Environment” are mandatory for all applicants. It is not necessary to apply for all lots. With regard to the individual lots, you only need to answer the questionnaires from 3. to 15. that apply to you. Even if you leave questions from 3.-15. unanswered, you can continue through the application process and submit your application. *** TenneT reserves the right to extend this scope of work to cover its in operation assets in Dutch, British, Norwegian and Danish waters in the future for cables which fall in the major responsibility of TenneT. For each requirement of survey services of offshore or nearshore power cables or offshore platform the client will issue an invitation to tender/request for quotation (ITT) based on the general survey conditions which are published with this Qualification System. The technical requirements can vary in its nature, depending on the region, permit requirements, soil conditions, etc. A non-disclosure agreement (NDA) is to be concluded to protect the confidentiality of the client's information. Please download the attached NDA and send the completed, stamped and signed document to the following email address: Jana.Gerlach@tennet.eu Once the NDA has been received and considered complete, you shall be added as participant to the prequalification system and granted access to all questions and documents accordingly. As a participant you have to pass the prequalification requirements to qualify as a bidder for upcoming ITTs. Please note that there is no schedule and no deadline for the participation in this qualification system. In the event of a requirement for survey services we are going to issue individual invitations to tender (ITT) to prequalified companies only. Please carefully read the Scope of Services and Procedural Guide once you have been added as a participant to the qualification system. The questionnaires will guide you through our requirements with regards to information and documents to complete the first part of the application process. *** The application for participation must be submitted electronically (in a standardized data format, such as PDF and MS Office format) via the Mercell e-Tendering Platform, including all required information and supporting documents. *** All attachments have to be submitted exclusively via Mercell Source-to-Contract (T77318) only. Please use the templates made available. *** Authorized to call for this qualification system are also companies affiliated with the client within the meaning of §§ 15 ff. AktG. *** TenneT will only place orders with respect to these general terms and conditions as soon and as long TenneT is in the full responsibility to purchase those demands. In cases of joined projects for which TenneT is not in full charge of provision of survey services, the contractor is not entitled to claim for providing such services to TenneT. *** Technical questions regarding the use of Mercell Source-to-Contract can be asked directly to the Mercell ServiceDesk: E-Mail: support-nl@mercell.com Phone: +31 (0)85-001 4593

    Qualification system
    Oct 10, 2027(100+ days)