Aalborg Universitet har inngått en avtale med Felix Technology Inc. om levering av batterimoduler til et nytt hybrid energilagringsanlegg (HES) i Nordjylland, med en total verdi på 234 859 €. Anlegget, som opererer på et 750-kW kapasitetsnivå, skal stabilisere strømbehovsfluktuasjoner fra fornybare energikilder, muliggjøre både nettilkoblede og øy-driftsmoduser, og støtte energitjenester og kraftsystemapplikasjoner. Det ble mottatt 3 tilbud.
Batterisystemer og energilagring
Result
- Felix Technology Inc.Winner
- 3Number of tenders received
- €234,859Contract value
Previous winners
Who are you up against?
The suppliers who have won similar contracts at Aalborg Universitet
Will you bid?
The agent sets up the bid and writes the first draft. Free for 14 days.
Award Criteria
Description
The sub-criterion "Price" is assessed relatively. The offers are thus assessed in relation to the other offers received. In connection with the final evaluation, a scoring model will be used, where prices are converted into points, which can then be weighted against points for qualitative criteria in an overall assessment.
Source
No source found in the documents. Check the weight against the tender documents.
Description
The tenders received will be assessed according to the detailed answers in the requirement specification. The qualitative sub-criterion 'quality' will be evaluated according to an absolute evaluation model. The offers are thus assessed independently of the other offers received. Points are awarded on the basis of how well the tenders meet the requirements linked to the individual sub-criteria. Several offers can thus obtain the same points.
Source
No source found in the documents. Check the weight against the tender documents.
From the notice
Aalborg University - AAU Energy is set to create a new hybrid Energy Storage (HES) facility representing a pioneering advancement in scalable, controllable, modular, and flexible energy storage solutions. This cutting-edge facility addresses critical challenges in grid stability, power quality management, and future renewable energy integration while providing essential grid balancing services. The HES facility integrates storage technologies, including Supercapacitors and Battery modules, coupled with Power Electronic interfaces, a Real-Time Digital Simulator, and a Linear Power Amplifier. Operating at a 750-kW capacity level, the facility is designed to: • Stabilize power demand fluctuations from renewable energy sources • Enable both grid-connected and islanded operational modes • Support energy services and power system-level applications This tender concerns an Agreement for battery modules.Main features of the procedureThe call for tender is an open procedure subject to the provisions of section 56-57 of the Danish Act on Tender Procedures (Udbudsloven) (Act No. 116 of 03/02/2025), which means that any interested Tenderer may submit a tender. The conditions for submitting tenders are set out in section 7 of the tender specifications. Provisions on award are set out in section 8 of the tender specifications. Costs in connection with participation in this tender procedure are irrelevant to AAU, including if AAU decides to cancel the tender procedure without awarding an agreement. AAU is not obliged to return tenders.
Contact
Anne Kielgast Andersenanneka@adm.aau.dk- ResultType
- NordjyllandLocation
- 31000000Main codeElectrical machinery, apparatus, equipment and consumables; lighting
- 31440000Batteries