BKP 244 Ventilation Systems | Vertical Extension of Gymnasiums TBS5, Weinfelden
Awarded
The competition has ended and a winner has been selected.
- Deadline
- Feb 13,Expired
- Award
Brief
Die Sekundarschulgemeinde Weinfelden (MLR Baumanagement GmbH) hat einen Vertrag mit EN_Die Klimamacher AG über die Lieferung von Lüftungssystemen für die vertikale Erweiterung der Turnhallen TBS5 in Weinfelden abgeschlossen. Im Rahmen des Projekts wird die bestehende Turnhalle um zwei Stockwerke für die Nutzung als Sekundarschule erweitert, wobei die Lüftungsanlage im Technikzentrum im 2. Stock installiert wird. Der Vertrag hat einen Wert von 396.186 CHF.
Bygg og anlegg - Oppføring og konstruksjon av bygninger
Result
- EN_Die Klimamacher AGWinner
- 8Number of tenders received
- CHF 396,186Contract value
Previous winners
Who are you up against?
The suppliers who have won similar contracts at Sekundarschulgemeinde Weinfelden (MLR Baumanagement GmbH)
Will you bid?
The agent sets up the bid and writes the first draft. Free for 14 days.
Award Criteria
Description
Award criteria
Source
No source found in the documents. Check the weight against the tender documents.
From the notice
Subject of the Contract: As part of the project, the existing gymnasium will be extended by adding two additional floors for use as a secondary school. The extension will be constructed using timber element construction. The new/extended staircases will be built as double-shell structures in exposed concrete. The two-story extension will include 12 classrooms (one of which will be equipped as a learning space), 7 group rooms, and two staff rooms with a terrace. At the heart of the school, a single-story atrium (open to the outside climate) is designed. Special Conditions: The renovation will take place predominantly during ongoing operations. A complete closure of the gymnasium is only planned for the duration of the timber construction work for the extension Ventilation Systems: The ventilation unit will be installed in the technical center on the 2nd floor, ensuring short duct runs for outdoor air intake and exhaust air discharge. A combined ventilation system is planned. Conditioned air will be supplied at two points per floor in the main circulation areas near floor level. Extract air will be captured near the ceiling. Classrooms will be ventilated using a so-called “lung ventilation” concept: the conditioned supply air is introduced into the circulation zone, which serves as the lung. Air exchange to classrooms and group rooms will occur via transfer fans. Only the WC rooms and the cleaning room will be continuously supplied and extracted through conventional ventilation ducts.
Contact
r.gubser@schuleweinfelden.ch- ResultType
- ThurgauLocation
- 45214000Main codeConstruction work for buildings relating to education and research
- 45331210Ventilation installation work