Cityringen Extension Nordhavn - Early Contractor Involvement

Published deadline passed

The published deadline has passed. For multi-stage competitions a later tender deadline may still apply — check the notice or portal for the current phase.

Qualification deadline
Mar 6, 2025Expired
Award
Hourly rates, weight 5 and 4 more
Procedure
Competitive dialogueTwo stages
Agreement
Construction workover 6 years

Brief

Metroselskabet I/S trenger en utvidelse av Cityringen M4 metro til Nordhavn, som inkluderer to metro-stasjoner fra Orientkaj til ytre Nordhavn, planlagt som en forhøyet linje. Prosjektet er delt inn i to hovedfaser: Samarbeidsfasen, hvor prosjektet designes og utvikles i nært samarbeid med den integrerte entreprenøren, og Byggefasen, som inkluderer detaljert design og konstruksjon. Kontrakten har en varighet på 6 år. Det er krav om erfaring fra minst 2 lignende prosjekter fullført innen de siste 10 årene, og søkere må levere inntil 6 referanser som oppfyller dette kravet. Tildelingskriteriene vektlegger pris (25%), samarbeid (25%), prosesser (30%), og nøkkelpersonell og organisasjon (20%). Prosjektet fokuserer på bærekraft, passasjeropplevelse og operasjon, med en ambisjon om å redusere klimaavtrykket med 50%.

Register interest

Previous winners

  • Who are you up against?

    The suppliers who have won similar contracts at Metroselskabet I/S

Will you bid?

The agent sets up the bid and writes the first draft. Free for 14 days.

Qualification requirements

  • Description

    Leverandøren skal ha erfaring fra minst 2 lignende prosjekter som er fullført innen de siste 10 årene regnet fra datoen for prekvalifiseringsfristen. Med "lignende" prosjekter menes: (1) Prosjekter som viser erfaring med design og konstruksjon av metroer, viadukter, jernbaner og/eller broer som krysser vann. (2) Prosjekter som viser erfaring med tidlig entreprenørinvolvering, der leverandøren er del av et team bestående av en designkonsulent og en utførende entreprenør som, sammen med kunden, utvikler og ferdigstiller prosjektet basert på et prosjekt utlyst på et tidlig stadium før overgangen til utførelsesfasen. (3) Prosjekter som viser erfaringer som inkluderer arkitektoniske løsninger for de ovennevnte strukturene og/eller strukturer av lignende kompleksitet som en stasjon (store skoler, store bygninger med offentlig tilgang, andre offentlige transportanlegg), og hvor det har vært fokus på klimapåvirkning i overordnet konseptdesign.

    Documentation Requirement

    Leverandøren skal oppgi maksimalt 6 referanser i sitt ESPD som individuelt eller samlet oppfyller minimumskravet. Hvis en søker inkluderer mer enn 6 referanser, vil Metroselskabet kun vurdere de 6 nyeste (i år) referansene bestemt ut fra tidspunktet for ferdigstillelse. Hver referanse må ikke overstige 3 A4-sider. Hvis en referanse overstiger 4 A4-sider, vil Metroselskabet se bort fra sider utover 3 A4-sider. Referansene skal inkludere følgende informasjon: a) Klient for prosjektet, b) Start- og ferdigstillelsesdato, c) Total kontraktsverdi for hele prosjektet i euro eksklusive MVA, d) Honoraret betalt til søkeren for tjenestene, e) Kort beskrivelse av prosjektet inkludert type konstruksjon og art av tjenestene – levert. De leverte tjenestene kan inkludere aktiv bruk av digitale byggemodeller, digitale verktøy, data i planlegging av prosjektet, design av prosjektet og i byggefasen, bruk av åpen bok under samarbeid, overvåking av karbonreduksjoner gjennom alle faser av prosjektet. f) Søkerens rolle i prosjektet (f.eks. konsulent, hovedkonsulent, underkonsulent, design-bygg entreprenør, hovedentreprenør, underleverandør).

    Source

    No source found in the documents. Check the requirement against the tender documents.

Award Criteria

  • Description

    Schedule of Prices

    Source

    No source found in the documents. Check the weight against the tender documents.

  • Description

    Hourly rates

    Source

    No source found in the documents. Check the weight against the tender documents.

  • Description

    Overhead and Profit

    Source

    No source found in the documents. Check the weight against the tender documents.

  • Description

    Collaboration

    Source

    No source found in the documents. Check the weight against the tender documents.

  • Description

    Processes

    Source

    No source found in the documents. Check the weight against the tender documents.

  • Description

    Key Personnel and Organisation

    Source

    No source found in the documents. Check the weight against the tender documents.

From the notice

  • Metroselskabet is tendering for an extension of the Cityringen M4 metro to Nordhavn (CRNHE). CRNHE will consists of two metro-stations from Orientkaj to outer Nordhavn. CRNHE is planned as an elevated line. The metro line will be crossing Skudeløbet in Nordhavn. The extension is expected to ready to open in 2030. The existing M4 line in Nordhavn is an attractive and function part of the network, but the CRNHE project aims to improve in terms of sustainability, passenger experience and operation. The project is divided into two major contracts: Integrated Works Contract (IWC Contract) – This contract overall covers design, civil works, permanent way and access control and is procured by this contract notice. For further details on the services and works included in the contract see below and for at detailed description please refer to: Scope of Works, doc id.CR-MS-GEN=NHE-CG-CON-SPE-000004. Transportation System Contract (TS-contractor) - all other transportation systems. Besides the two major contracts Metroselskabet will be entering into contract with different consultants on other parts of the project, such as Areas and Rights, Environmental Impact Assessment consultancy etc. The IWC contract covers the following disciplines: Viaducts & elevated structures, including sub-structure Elevated Stations Temporary works for completion of the permanent works. Architectural Finishes Sustainability & Carbon Initiatives Alignment & Permanent way Noise screens, noise & vibration monitoring and mitigation Geology & Hydrogeology Technical Buildings & installations Electrical Works & Power Supply for stations and elevated structures Mechanical Works for stations and elevated structures Access Control Traction Power (3rd rail) Interface to SCADA Preparatory Works Technical Safety (Jernbanesikkerhed) Technical Interfaces Finishing Works Worksites Identification & planning for utility relocation Climate Protection Strategy Environmental Management Risk Management Interfaces with city development, Østlig Ringvej. Construction Programming Construction Budgeting The IWC might also be asked to do some early works, such as diversion of utilities and public road diversions, certain utility diversions, demolition or other tasks identified as part of the collaboration phase. CRNHE is one of the first larger projects where Metroselskabet´s ambitions of reducing the climate impact by 50% will be a significant factor impacting the solution of the project. And Metroselskabet would like to benefit from the contractor´s knowledge and experiences with the construction industry. Metroselskabet has assessed that to achieve the reduction of the climate footprint it is necessary for Metroselskabet and the contractor to work very closely together by bringing in the contractor and his design team (Integrated Works Contractor) at a very early stage of the project. Thus, Metroselskabet has decided to procure the CRNHE as an Early Contractor Involvement (ECI) project. After the designing of the metro line, Metroselskabet will enter into a Design and Build contract (based on ABT18) with the Integrated Works Contractor (IWC) The project is divided into two main phases with underlying stages and gate stages: Phase 1: Collaboration Phase – A phase where the project will be designed and developed in close collaboration between Metroselskabet, the Integrated Works Contractor. The collaboration Phase is contractually regulated by a collaboration agreement, Collaboration Terms and Conditions, doc. id. CR-MS-GEN=NHE-CG-CON-SPE-000002-ATT14 and a conditional Design and Build contract (ABT18). doc. id CR-MS-GEN=NHE-CG-CON-SPE-000002. The collaboration agreement can be terminated by the Integrated Works Contractor and/or Metroselskabet at convenience. The conditioned ABT18 contract will enter into force if the pre-requisites, are met. Please Refer to the Design and Build Contract, doc id: CR-MS-GEN=NHE-CG-CON-SPE-000002, section 1.1. In the collaboration phase the Integrated Works Contractor is liable for the design as well as the time schedule, pricing and constructability of the project. Also, the contractor should focus on ensuring a close collaboration with the Transportation System contractor, EIA consultant, the Areas and Rights consultant and possible early works contractors. The engineers and the architects of the Integrated Works Contractor are expected to focus on the development of the design, reducing carbon emissions and improving passenger experience. Phase 2: Construction Phase – After signing the ABT18 contract, the project moves into the construction phase. The Construction consists of a detailed design stage and a construction stage. In the construction phase the Integrated Works Contractor is expected (among other things) to keep focus on collaborating closely with Metroselskabet and the Transportation System contractor, reducing the carbon footprint, time, costs and quality during construction The applicant should apply for prequalification with a design team - both architects and engineering discipline consultants. Metroselskabet will focus on the architectural appearance and materiality proposed for the two new stations. The architecture should comply with the ambition of significantly reducing the carbon footprint. Metroselskabet would like to be challenged by the architects of the two new stations and the possibility for development under/over the viaduct. The applicant is encouraged to include an architect with substantial experience with similar complex and onerous functional type projects, yet providing creative and innovative architectural solutions, while maintaining high level of functional clarity in the design.Main features of the procedureIn accordance with the Utilities Directive section 48 subsection 3 all parts of the descriptive document (tender documentation) can be subject to discussions during the dialogue phase. The overall themes for the dialogue phase is: 1)Collaboration - establishing and maintaining a joint culture of collaboration, onboarding and disagreement management, 2) Processes for design, planning (time schedule), risk management and open books, calculations and cost break down, 3)Key Personnel and Organisation and 4)Price, including definition of overhead and profit and the range between minimum and maximum percentage. Please refer to Instructions to Tenderers section 5. Due to the competitive dialogue procedure, Metroselskabet has decided to pay each tenderer a Tender Fee DKK 500,000 excl. VAT for the participation in the dialogue phase and for the submission of a compliant final tender that meets all the requirements of the tender documentation.documents, cf. section 4.1 (“Tender Fee”). The winning tenderer will not receive a Tender Fee. If the tenderer submits a tender as a consortium, joint venture or similar association of companies (“Consortium”), the Tender Fee will only be paid to the Consortium and not to each participant in the Consortium.

  • Contact

    Vibeke Jessenvij@m.dk
  • Type
    Competition · Prequalification
  • Location
    Byen København
  • Main code
    Construction work
    45000000
  • 45230000Construction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork71000000Architectural, construction, engineering and inspection services71220000Architectural design services71300000Engineering services71311230Railway engineering services

Similar active competitions

  • Udviklingsselskabet By & Havn I/S

    Construction and Civil Engineering - Bridges and Tunnels

    Udbud af Bro 23 - anlæggelse af Bro 23 mellem Svanemølleholm og det kommende Skudehavnskvarter

    Udviklingsselskabet By & Havn I/S udbyder en hovedentreprise på anlæg af Bro 23 i København med en maksimal samlet kontraktværdi på 55 mio. DKK og en udførelsesperiode på 13 måneder. Projektet omfatter en betonvejbro og to stibroer i stål mellem Svanemølleholm og det kommende Skudehavnskvarter samt ramper, spuns, pæle, vederlag, underbygning og tilhørende arbejder. Konkurrencen gennemføres i to faser: op til fem ansøgere prækvalificeres til at afgive tilbud. Udvælgelsen vægter sammenlignelige referencer fra de seneste 10 år; der skal indsendes 1–5 referencer, og erfaring med broer og anlægsarbejder, jord- og funderingsarbejder, tilslutning til eksisterende konstruktioner samt tilsvarende logistiske og stedbundne forhold prioriteres. Tilbuddene vurderes på pris (60 %), projektorganisation inklusive nøglepersoner (20 %) og proces med fokus på tid, økonomi og samarbejde (20 %).

    Competition with qualification
    Dec 17, 2026(21 days)
    DKK 55,000,000
  • Energinet Eltransmission A/S

    Building work and installations

    Entreprisekontrakt om udførelse af bygge-og anlægsarbejder på Station Lyngerup og Station Ølstykkegaard -25/12717 - 23/03693

    Energinet Eltransmission A/S søger en entreprenør til en toårig bygge- og anlægskontrakt i Nordsjælland med en maksimal samlet værdi på 70 millioner DKK. Opgaven omfatter opførelse af 132 kV-stationen Lyngerup med terrænarbejder, fundamenter og AC-bygning samt nedtagning af den eksisterende station, og opførelse af 132 kV-stationen Ølstykkegaard med terrænarbejder, en to-etagers GIS-bygning og to transformerfundamenter. Tilbudsgivere skal byde på begge delaftaler, som tildeles samlet til én leverandør. Udvælgelsen omfatter højst fem referencer fra de seneste fem år, herunder mindst én reference fra arbejde på en 132/150 kV-højspændingsstation i drift. Tilbuddet vurderes på pris (60 %), CV’er og projektorganisation (30 %) samt tidsplan (10 %); der kræves detaljerede CV’er for nøglemedarbejdere og en realistisk, robust plan for udførelsen af begge projekter sideløbende.

    Competition with qualification
    Dec 3, 2026(7 days)
    DKK 70,000,000
  • Københavns Kommune

    Architectural services

    Totalrådgivning for 2 nye daginstitutioner med lavt klimaaftryk

    Københavns Kommune søger totalrådgivning til opførelse af to daginstitutioner med hver fem grupper på en fælles grund på Svanemølleholm Øst i Nordhavn: Den ene skal være CO₂-neutral, og den anden skal opfylde BR18’s lavemissionsklasse. Opgaven omfatter arkitekt-, landskabsarkitekt- og ingeniørrådgivning fra idéoplæg til étårseftersyn, herunder at finde synergier i projektering, udførelse og drift uden at gå på kompromis med institutionernes funktion og pædagogiske behov. Ansøgere skal dokumentere relevant erfaring fra projekter afleveret inden for de seneste tre år, herunder erfaring med reduktion af klimaaftryk, lavt klimaaftryk og lav driftsenergi i nybyggeri med tilsvarende eller højere personbelastning samt optimering af konstruktioners klimaaftryk; der kræves erfaring inden for alle tre områder. Tilbuddene vurderes på pris (30 %), organisation og bemanding (35 %) samt tilgang og proces (35 %).

    Competition with qualification
    Jan 4, 2027(39 days)