Construction of the wastewater treatment plant, wastewater collection system and implementation of water supply priority measures in the Municipality of Kolašin
Awarded
The competition has ended and a winner has been selected.
- Award
- Procedure
- OpenSingle stage
- Agreement
- Construction workover 4 years
Brief
The Municipality of Kolašin has entered into an agreement with JV SPIGA srl & Ibi IDROBIOIMIPIANTI S.R.L. & M.E.C. S.r.l. MECCANICA ECOLOGICA for the construction of a wastewater treatment plant, a wastewater collection system, and the implementation of water supply priority measures in the Municipality of Kolašin, Montenegro. The contract, valued at 9,714,645 €, has a duration of 48 months and includes the construction of approximately 9.2 km of sewerage network, water supply priority measures, and the design and construction of a Wastewater Treatment Plant (WWTP) in Bakovići settlement, with Phase I for 4000 PE and Phase II for an additional 2000 PE. The works will be implemented according to FIDIC Yellow Book (1999 ed) and Montenegrin legislation, with particular consideration for licensing and permits.
Result
- JV SPIGA srl & Ibi IDROBIOIMIPIANTI S.R.L. & M.E.C. S.r.l. MECCANICA ECOLOGICAWinner
- 3Number of tenders received
- €9,714,645Contract value
Previous winners
Who are you up against?
The suppliers who have won similar contracts at Municipality of Kolašin
Will you bid?
The agent sets up the bid and writes the first draft. Free for 14 days.
Award Criteria
Description
Price is the only selection criterion
Source
No source found in the documents. Check the weight against the tender documents.
From the notice
This contract includes the following elements: 1. Sewerage network: Construction of sewerage network in the approximate length of 9.2 km. 2. Water supply priority measures: Water supply priority measures include services, supplies and construction works to be designed, supplied, installed and constructed by the Contractor. 3. Wastewater Treatment Plant Design and Construction of WWTP in Bakovići settlement - Conventional Activated Sludge Process and aerobic sludge stabilization. Design and construction of the WWTP shall include two phases: › Phase I – 4000 PE (to be constructed) › Phase II – additional 2000 PE (to be considered in design) Works will be implemented according to FIDIC Yellow Book (1999 ed), in compliance with requirements of the Montenegrin legislation and relevant EU and EIB requirements. The Contractor must particularly consider licensing and permits requirements in the Law on Spatial Planning and Construction of Structures in Montenegro in force.
Contact
Damjana Bulatovićbulatovicdamjana@gmail.com- ResultType
- 45252127Main codeWastewater treatment plant construction work