Construction Works for Wastewater Collection and Treatment System in the City of Čačak
Awarded
The competition has ended and a winner has been selected.
- Award
- Procedure
- OpenSingle stage
- Agreement
- Construction workover 1,099 days
Brief
Ministarstvo finansija, Odeljenje za ugovaranje i finansiranje programa finansiranih iz EU fondova (CFCU) Vlade Republike Srbije, dodelilo je ugovor kompaniji STRABAG.AG za izvođenje radova na sistemu za sakupljanje i prečišćavanje otpadnih voda u gradu Čačku. Projekat obuhvata projektovanje i izgradnju postrojenja za prečišćavanje otpadnih voda Prelići sa pristupnim putem, projektovanje i rehabilitaciju crpnih stanica Ljubić Polje, Beljina i Košutnjak, inspekciju, projektovanje i rehabilitaciju kanalizacije, kao i nabavku opreme za čišćenje i ispitivanje kanalizacije. Vrednost ugovora iznosi 45.127.044 evra, a trajanje projekta je 1099 dana. Na tender je pristiglo 8 ponuda.
Pumpestajoner og VA-pumper
Result
- STRABAG.AGWinner
- 8Number of tenders received
- €45,127,044Contract value
Previous winners
Who are you up against?
The suppliers who have won similar contracts at Ministry of Finance, Government of the Republic of Serbia Department for Contracting and Financing of EU Funded Programmes (CFCU)
Will you bid?
The agent sets up the bid and writes the first draft. Free for 14 days.
Award Criteria
Description
Please consult the procurement documents.
Source
No source found in the documents. Check the weight against the tender documents.
From the notice
The main objective of the project is to improve wastewater management in the city of Čacak, in particular wastewater collection and to provide treatment of the wastewater in compliance with the EU Urban Wastewater Treatment Directive. The Scope of Works comprise four parts as follows: Part 1: Design and construction of WWTP Prelići with construction of the access road to the WWTP; Part 2: Design and rehabilitation of pumping stations PS Ljubić Polje, PS Beljina and PS Košutnjak with construction of the access road to the pumping station PS Ljubić Polje; Part 3: CCTV inspection, design and rehabilitation of sewers; Part 4: Supply of sewer cleaning and investigation equipment. The Contractor is responsible for provision of fit for purpose facilities and equipment and execution of all associated required design and construction works, including commissioning, testing and taking over upon completion.
Contact
cfcu.questions@mfin.gov.rs- ResultType
- 45252127Main codeWastewater treatment plant construction work
- 45232400Sewer construction work45232431Wastewater pumping station