Germany: Tenders/TEP Vesta GmbH & Co. KG/Delivery and service for battery storage projects in Mecklenburg-Vorpommern & Brandenburg (2 lots) for TEP Vesta GmbH & Co. KG and TEP Flora GmbH & Co. KG

Delivery and service for battery storage projects in Mecklenburg-Vorpommern & Brandenburg (2 lots) for TEP Vesta GmbH & Co. KG and TEP Flora GmbH & Co. KG

Awarded

The competition has ended and a winner has been selected.

Qualification deadline
Dec 22, 2025Expired
Award
Content of Term Sheet, weight 15 and 1 more
Procedure
With negotiationTwo stages
Agreement
Buying goodsuntil Jun 2026

Brief

TEP Vesta GmbH & Co. KG has awarded a contract to Huawei Technology Deutschland GmbH and Hyperstrong International (Germany) GmbH for the delivery and service of core components for battery storage projects in Mecklenburg-Vorpommern ("Rom I") and Brandenburg ("Göhlsdorf II"). The core components include battery storage, battery inverter, transformer station, and battery management system (BMS), with suppliers also responsible for commissioning. The contract also includes long-term service agreements with warranty extensions. The award was based on the LCOS Value (80%), Content of Term Sheet (15%), and SOH after 15 years (5%).

Elektrisk utstyr og belysning

Result

TED
  • HYPERSTRONG INTERNATIONAL (GERMANY) GMBH
    Winner
  • Huawei Technology Deutschland GmbH
    Winner
  • Number of tenders received
    -2
  • Contract value
    -€1

Previous winners

  • Who are you up against?

    The suppliers who have won similar contracts at TEP Vesta GmbH & Co. KG

Will you bid?

The agent sets up the bid and writes the first draft. Free for 14 days.

Award Criteria

  • Description

    LCOS Value

    Source

    No source found in the documents. Check the weight against the tender documents.

  • Description

    Content of Term Sheet

    Source

    No source found in the documents. Check the weight against the tender documents.

  • Description

    SOH after 15a (1,7 cycles/day)

    Source

    No source found in the documents. Check the weight against the tender documents.

From the notice

  • Founded in 1999, Trianel GmbH ("Trianel") is a joint venture of independent municipal utilities based in Aachen. As a Europe-wide municipal utility cooperation, Trianel taps the potential of liberalized energy markets by bundling complementary interests in the municipal environment with the aim of strengthening municipal utilities in their competitiveness and thus their independence. Trianel's shareholders are more than 50 municipal utilities from Germany, Austria, Switzerland and the Netherlands, which together supply around 6 million people with electricity and gas. More than 100 municipal utilities are linked to Trianel via subsidiaries and associated companies as well as partnership agreements. The Trianel Group currently has around 15 subsidiaries and associated companies. TEP Vesta GmbH & Co. KG and TEP Flora GmbH & Co. KG ("TEP") are project company of Trianel Energieprojekte GmbH & Co. KG and want to implement the battery storage project in Mecklenburg-Pomerania ("Rom I", TEP Vesta) and Brandenburg ("Göhlsdorf II", TEP Flora) from Q1/2026. TEP Vesta and TEP Flora are looking for suitable suppliers to deliver the core components consisting of battery storage, battery inverter, transformer station and battery management system (BMS). The suppliers are also responsible for commissioning the components they supply. In addition, long-term service contracts will be awarded, which will include warranty extensions and ensure the performance of the systems. Following successful application, selected companies will be invited to submit a tender on the basis of a project profile including performance requirements and a term sheet. The aim of TEP Vesta and TEP Flora is to award the supply and service contract within the next few months so that implementation can begin in Q1/2026, depending on the delivery times.

  • Contact

    GÖRG Partnerschaft von Rechtsanwälten mbB / Dr. Oliver Jauchojauch@goerg.de
  • Type
    Result · Prequalification
  • Location
    Ludwigslust-Parchim
  • Main code
    Uninterruptible power supplies
    31154000
  • 31000000Electrical machinery, apparatus, equipment and consumables; lighting31100000Electric motors, generators and transformers31400000Accumulators, primary cells and primary batteries31422000Battery packs

Similar active competitions

  • SWN Stadtwerke Neumünster GmbH

    Elektrisk infrastruktur og veibelysning

    Lieferung, Montage und Inbetriebnahme Batteriespeichersystem (BESS)

    Die SWN Stadtwerke Neumünster GmbH benötigt ein schlüsselfertig geliefertes, errichtetes und in Betrieb genommenes Batteriespeichersystem mit 16 MW Leistung und rund 45 MWh Speicherkapazität am Betriebsgelände in Neumünster. Zum Auftrag gehören außerdem die Herstellung der Bodenplatte, eine Schallschutzmauer, die 20-kV-Übergabestation sowie Wartungsleistungen; die Tiefbauarbeiten übernimmt SWN. Vorgesehen sind netzbildende Wechselrichter für die Vermarktung an Regelenergie- und Spotmärkten sowie für künftige Strommärkte. Die Inbetriebnahme ist für 2028 verbindlich zuzusichern; Umfang und Systemparameter können im Projektverlauf angepasst werden. Die Teilnahme erfordert bis zu vier Referenzen zu Batteriespeichern über 5 MW mit einem Auftragswert von mindestens 5 Millionen Euro, einen entsprechenden Umsatz im Produktbereich, ISO-9001-Zertifizierung und ein Informationssicherheitsmanagementsystem gemäß ISO/IEC 27001. Die drei Bewerber mit den höchsten Referenzbewertungen werden zur Angebotsabgabe aufgefordert; der Zuschlag richtet sich nach dem wirtschaftlichsten Angebot.

    Competition with qualification
    Dec 14, 2026(22 days)
  • Stadtwerke Schneeberg GmbH

    Batterisystemer og energilagring

    Projektierung, Lieferung und Errichtung eines Batteriespeichersystems (BESS)

    Die Stadtwerke Schneeberg GmbH benötigt im Erzgebirgskreis die Projektierung, Lieferung, Errichtung und Inbetriebnahme eines Batteriespeichersystems (BESS) mit 3 MW Leistung und 6 MWh Kapazität einschließlich Übergabe-Trafostation. Der Auftrag hat eine Laufzeit von 18 Monaten und einen maximalen Gesamtwert von 1,9 Millionen Euro. Für die Eignung sind Eigenerklärungen zu zwei vergleichbaren Referenzobjekten sowie eine Berufshaftpflichtversicherung mit jeweils mindestens 3 Millionen Euro Deckung für Personen- und sonstige Schäden nachzuweisen. Gewertet werden der Gesamtpreis mit 60 %, der Wirkungsgrad (RTE) mit 20 % und das Degradationsverhalten mit 20 %.

    Competition
    Nov 30, 2026(8 days)
    €1,900,000
  • Teplárna České Budějovice, a.s.

    Elektrisk infrastruktur og veibelysning

    Dodávka bateriového úložiště

    Teplárna České Budějovice, a.s. potřebuje v Jihočeském kraji dodat a namontovat bateriové úložiště s maximální celkovou hodnotou 62 milionů Kč. Zakázka zahrnuje dva bateriové kontejnery a dvě trafostanice, elektroinstalaci pro připojení úložiště a řízení jeho technologií pro poskytování podpůrných služeb výkonové rovnováhy sítě. Součástí je také zpracování a posouzení projektové dokumentace pro provádění stavby, dodávka a montáž všech projektovaných komponent a související práce a služby. Nabídky budou hodnoceny výhradně podle ceny; rozhoduje nejnižší nabídková cena bez DPH.

    Competition
    Dec 7, 2026(15 days)
    CZK 62,000,000