EST Constr - Sligo University Hospital, Sligo, HSE NW - Medical Beds Development

Expired

The competition has expired without a winner being announced.

Deadline
Dec 20, 2024Expired
Procedure
OpenSingle stage
Agreement
Construction work
Estimated value
€0

Brief

The proposed site is near the Out-Patient Department entrance of the hospital on the East side and is accessible from the main circulation concourse of the hospital at all levels. The proposed design creates two 21 bed wards on the first two storeys at Level 3 and Level 4. The beds spaces are all provided in single rooms with two isolation rooms per floor as per Strategy for the control of Antimicrobial Resistance in Ireland (SARI) guidelines with all necessary ancillary accommodation self-contained on each level. The upper storeys at Level 5 and 6 keep the established building line to create a design that will integrate with the surrounding environs. The accommodation requirements for Levels 5 and 6 have yet to be fully established and these areas shall be shell and core only. A new covered ramped approach to the Level 3 entrance and improved public access as well as site works and roads infrastructure are also included. The Undercroft at level 2 shall accommodate parking visitors and Ambulance and provide accommodation for staff and plant. The floor area at each level can be summarised as follow: Level 2 = 524.91m2 Level 3= 1172.15m2 Level 4= 1209.75m2 Level 5= 620.97m2 Level 6= 527.74m2 Level 7= 190.89m2 Total floor area= 4246.41m2 The Works will be completed in Multiple Phases with Sectional handovers.

Building and construction - Healthcare, courthouses, and dams

Register interest

Previous winners

  • Who are you up against?

    The suppliers who have won similar contracts at Health Service Executive (HSE)

Will you bid?

The agent sets up the bid and writes the first draft. Free for 14 days.

From the notice

  • The proposed site is near the Out-Patient Department entrance of the hospital on the East side and is accessible from the main circulation concourse of the hospital at all levels. The proposed design creates two 21 bed wards on the first two storeys at Level 3 and Level 4. The beds spaces are all provided in single rooms with two isolation rooms per floor as per Strategy for the control of Antimicrobial Resistance in Ireland (SARI) guidelines with all necessary ancillary accommodation self-contained on each level. The upper storeys at Level 5 and 6 keep the established building line to create a design that will integrate with the surrounding environs. The accommodation requirements for Levels 5 and 6 have yet to be fully established and these areas shall be shell and core only. A new covered ramped approach to the Level 3 entrance and improved public access as well as site works and roads infrastructure are also included. The Undercroft at level 2 shall accommodate parking visitors and Ambulance and provide accommodation for staff and plant. The floor area at each level can be summarised as follow: Level 2 = 524.91m2 Level 3= 1172.15m2 Level 4= 1209.75m2 Level 5= 620.97m2 Level 6= 527.74m2 Level 7= 190.89m2 Total floor area= 4246.41m2 The Works will be completed in Multiple Phases with Sectional handovers.

  • Contact

    procurement.helpdesk@hse.ie
  • Type
    Competition
  • Location
    Border
  • Main code
    Construction work
    45000000
  • 45215100Construction work for buildings relating to health

Similar active competitions

  • Health Service Executive (HSE)

    Construction - Erection, Renovation and Maintenance of Buildings

    EST_MW - Maternity Emergency and Early Pregnancy Assessment Unit - University Maternity Hospital Limerick

    The Health Service Executive (HSE) needs construction works for an 18-month development at University Maternity Hospital Limerick in the Mid-West region of Ireland, with a maximum total contract value of €10 million. The project involves a new rapid-build facility of approximately 863 m² over two floors, including maternity emergency and assessment services, diagnostic scanning, labour induction, intensive care and procedure facilities, alongside staff and support areas. Works also include refurbishing approximately 263 m² of the existing main entrance and Medical Emergency Unit, upgrading the entrance and forecourt, landscaping, and constructing a replacement car park.

    Competition with qualification
    Dec 14, 2026(17 days)
    €10,000,000
  • Marymount University Hospital and Hospice

    Civil engineering and infrastructure construction

    FIRE REMEDIAL AND REINSTATEMENT WORKS AT MARYMOUNT UNIVERSITY HOSPITAL AND HOSPICE

    Marymount University Hospital and Hospice requires fire remedial and reinstatement works at its hospital and hospice in Ireland’s South-West region. The works contract has a duration of 1 year and a maximum total value of €8 million.

    Competition
    Dec 21, 2026(24 days)
    €8,000,000
  • Health Service Executive (HSE)

    Business consulting

    National Maternity Hospital at St Vincent’s University Hospital Programme Delivery Partner Services Prior Information Notice

    The Health Service Executive (HSE) is planning to procure delivery partner services for the National Maternity Hospital programme at St Vincent’s University Hospital in Dublin, supporting its team across construction, equipping, digital delivery, commissioning and transition to operations. The notice does not specify how suppliers can provide feedback or participate in the planning phase.

    Planning
    Feb 26, 2027(91 days)
    €0