Health Service Executive (HSE) has entered into an agreement with John Sisk and Son (Holdings) Ltd for the construction of a three-storey Surgical Hub building at Merlin Park University Hospital Galway, Ireland. The project, valued at 38,415,300 EUR, includes operating theatres, recovery areas, staff services, 108 car parking spaces, a new bus stop, and associated site development works, with a duration of 15 months. The development is a RAPID build construction project utilizing modern methods to address national and local healthcare provision targets for day surgery in the West region.
Bygg og anlegg - Oppføring, renovering og vedlikehold av bygninger
Result
- John Sisk and Son (Holdings) LtdWinner
- 1Number of tenders received
- €38,415,300Contract value
Previous winners
Who are you up against?
The suppliers who have won similar contracts at State Laboratory
Will you bid?
The agent sets up the bid and writes the first draft. Free for 14 days.
Award Criteria
Description
Quality Design 60%
Source
No source found in the documents. Check the weight against the tender documents.
Description
Price at 40%
Source
No source found in the documents. Check the weight against the tender documents.
From the notice
The development will comprise of the following: •The provision of a three storey Surgical Hub building (Gross Floor Area: 4,265 sq.m) to include: o Staff Services, Storage and Plant Rooms at Ground Floor Level; o Operating Theatres, Preparation Area, Recovery Area , Waiting Area and ancillary support services at First Floor Level; and o Plant and associated equipment at Second Floor Level. • The provision of roof mounted Solar PV Panels; • The provision of 108 no. car parking spaces (including 6 no. accessible spaces and 20 no. EV charging spaces); • The provision of a new bus stop to be located adjacent to the proposed development; and • All landscaping and other associated site development works required to facilitate the proposed development. The contractor should note that this project is to be undertaken as a RAPID build construction project implementing modern methods of construction and innovation to deliver within necessary project requirements and constraints. Progression of the Surgical Hub at MPUH in 2023 has been identified as a key focus of government initiatives per the Slaintecare Action Plan 2023. The facility is urgently required to address national and local healthcare provision targets and needs for day surgery across the West region. It will reduce waiting lists for day cases and ensure the provision of surgical day case procedures of lower acuity in a timely manner whilst receiving the best quality service.
Contact
procurement.helpdesk@hse.ie- Result · PrequalificationType
- WestLocation
- 45210000Main codeBuilding construction work