    Estates MW Radiology and MRI expansion project at University Hospital Limerick

    Health Service Executive (HSE)

    Estates MW Radiology and MRI expansion project at University Hospital Limerick

    1. Competition notice published

      Apr 17, 1:23 PMApril 17, 2025 1:23 PM
    2. Tender submission deadline

      May 22, 2:00 PMMay 22, 2025 2:00 PM

    Brief

    Ireland: Tenders/Health Service Executive (HSE)/Estates MW Radiology and MRI expansion project at University Hospital Limerick

    Published deadline passed

    The published deadline has passed. For multi-stage competitions a later tender deadline may still apply — check the notice or portal for the current phase.

    Brief

    Bygg og anlegg - Helsevesen, tinghus og demning

    The development consists of: a 701m2 single-storey extension to the Radiology Department overhead at Level 2; the creation of a 730m2 interstitial plantroom floor between the existing and the extension at Level1; a 36m2 new bridge link at Level 2 connecting the extension to the existing building; an 112m2 extensionto the existing MRI building at ground level (level 0); and a stair core connecting the existing Radiology withthe extension along with supporting services, associated site works and associated ancillary works. The works will include modifications to internal layouts and fitout at 162.1m2. Green Public Procurement and Embodied Carbon Reduction government guidance and best practice will befollowed in procuring the main construction contract. Further details are included in the enclosed Project Information Memorandum.

    About the bid

      The development consists of: a 701m2 single-storey extension to the Radiology Department overhead at Level 2; the creation of a 730m2 interstitial plantroom floor between the existing and the extension at Level1; a 36m2 new bridge link at Level 2 connecting the extension to the existing building; an 112m2 extensionto the existing MRI building at ground level (level 0); and a stair core connecting the existing Radiology withthe extension along with supporting services, associated site works and associated ancillary works. The works will include modifications to internal layouts and fitout at 162.1m2. Green Public Procurement and Embodied Carbon Reduction government guidance and best practice will befollowed in procuring the main construction contract. Further details are included in the enclosed Project Information Memorandum.

      Contact phone
      0879660226
      Contact email
      ben.walsh@hse.ie
      Address
      Oak House, Millennium Park Naas Co. Kildare, RE Kildare

    Custom Assessment Criteria

    Start a free trial to ask your own questions about the tender and get AI-generated answers.

    Award Criteria

      Found no award criteria in the contract notice.

    Qualification requirements

      Found no qualification requirements in the contract notice.

    Previous Contract Winners

    Start a free trial to see who has won similar tenders for this buyer.

    See the full notice

    Contracting authority
    Health Service Executive (HSE)
    Title
    Estates MW Radiology and MRI expansion project at University Hospital Limerick
    Type
    CompetitionPrequalification
    Main code
    45215100Construction work for buildings relating to health
    Supplemental codes
    45210000Building construction work45215130Clinic construction work45215140Hospital facilities construction work45310000Electrical installation work45350000Mechanical installations
    Location
    Dublin
    Estimated value
    €8,870,000.00

    Active similar competitions

    • Health Service Executive (HSE)

      Bygg og anlegg - Oppføring, renovering og vedlikehold av bygninger

      EST_MW - Maternity Emergency and Early Pregnancy Assessment Unit - University Maternity Hospital Limerick

      Health Service Executive (HSE) needs construction services for a new rapid build facility with a gross internal floor area of approximately 863m2, plus a rooftop plantroom area of approximately 150m2, and the refurbishment of the existing Main Entrance and Medical Emergency Unit (area approximately 263m2) at the University Maternity Hospital Limerick. The project, with a maximum total value of 12,000,000 EUR, will last for 18 months and includes a new main entrance draught lobby, entrance canopy, upgraded main entrance forecourt, associated landscape works, and a new car park.

      Competition with qualificationSep 28, 2026
      Oct 16, 2026(6 days)
      €12,000,000
    • Health Service Executive (HSE)

      Rådgivende ingeniørtjenester for bygg og anlegg

      Mini-Competition for M and E Services for the Decentralization of the Campus Central Heating System at University Hospital Galway.

      Health Service Executive (HSE) needs Building Services (M and E) Consultant services for the decentralization of the Campus Central Heating System at University Hospital Galway, located in the West region of Ireland. The contract has a duration of 42 months and a maximum total value of 160,000 EUR. J.V. Tierney and Co (2002) Ltd likely has a similar contract today.

      Competition with qualificationOct 5, 2026
      Nov 2, 2026(23 days)
      €160,000
    • Health Service Executive (HSE)

      Rådgivende ingeniørtjenester for bygg og anlegg

      Mini-Competition for Civil/Structural Engineering for the Decentralization of the Campus Central Heating System at University Hospital Galway

      Health Service Executive (HSE) needs civil/structural engineering consulting services for the decentralization of the Campus Central Heating System at University Hospital Galway, with a maximum total value of 160,000 EUR over 42 months. The services are to be delivered in the West region of Ireland. This is a mini-competition tendered from an existing framework.

      Competition with qualificationOct 5, 2026
      Nov 2, 2026(23 days)
      €160,000
    • Health Service Executive (HSE)

      Byggeteknisk konsulentvirksomhet

      HSE ESTATES SW - Ballyseedy Refurbishment and New Build Disability Respite Housing

      Health Service Executive (HSE) needs Architect Lead Integrated Design Team services for the Ballyseedy Refurbishment and New Build Disability Respite Housing project in the South-West region of Ireland. The contract duration is 3 years.

      CompetitionSep 25, 2026
      Oct 23, 2026(13 days)
      €0
    • Health Service Executive (HSE)

      Arkitekttjenester

      Multi- Party Framework Agreement for HSE Design Team Services Framework 2024 - Framework 02 Acute Healthcare Capital Works - Project Value €1M to €15M excl. VAT for HSE NW

      Health Service Executive (HSE) needs design team services for a multi-party framework agreement over 4 years, with a maximum total value of 600 million EUR. The framework will cover Acute Healthcare Capital Works projects valued between 1 million EUR and 15 million EUR (excluding VAT) within the HSE North West Area. Services are divided into seven lots: Architect (as Principal Service Provider with Planner, Project Supervisor Design Process, Fire Safety Consultant, and BIM Information Manager specialists), Quantity Surveyor, Building Services Engineer (M+E), Civil/Structural Engineer (C+S), Employer’s Representative, Energy Efficient Design Facilitator, and Assigned Certifier. The initial project under this framework will be a proposed Microbiology Lab with ancillary site works and enabling work at Sligo University Hospital.

      Framework agreement with qualificationSep 30, 2026
      Oct 30, 2026(20 days)
      €600,000,000