Ireland: Tenders/Health Service Executive (HSE)/Fitout - Rotunda, Dominick St Lower

Fitout - Rotunda, Dominick St Lower

Published deadline passed

The published deadline has passed. For multi-stage competitions a later tender deadline may still apply — check the notice or portal for the current phase.

Qualification deadline
Apr 10,Expired
Procedure
With prequalificationTwo stages
Agreement
Construction work
Estimated value
€10Mover 8 months

Brief

Health Service Executive (HSE) needs construction services for the fit-out of an existing retail-style shell space on the ground floor of Dominick Hall, Dominick Street Lower, as part of a decant project for the Rotunda hospital, with an approximate budget of 10 million EUR (excluding VAT) over 8 months. The project involves fitting out approximately 2,703 m2 to include non-acute laboratory services, gynaecology outpatient department, phlebotomy, and associated ancillary staff facilities for the Rotunda Hospital. The fit-out will include new pathology labs and various clinical healthcare observation, diagnosis, treatment, and examination rooms, as well as other ancillary rooms. The works must achieve a minimum BER A3 rating and comply with applicable Health Building Notes and Health Technical Memoranda. The mechanical and electrical installations will be domestic sub-contracts, requiring full fit-out of clinical and laboratory areas, and upgrades to existing plant and equipment. The Main Contractor and its specialist subcontractors for Mechanical and Electrical installations must have training, knowledge, and experience in completing similar previous Pathology and Laboratory installations, and be fully aware of HTM03 and HBN 15 specialist ventilation requirements for a Hospital Pathology Department. The project will be delivered in BIM to ISO 19650.

Bygg og anlegg - Helsevesen, tinghus og demning

Register interest

Previous winners

  • Who are you up against?

    The suppliers who have won similar contracts at Health Service Executive (HSE)

Will you bid?

The agent sets up the bid and writes the first draft. Free for 14 days.

From the notice

  • The proposed project involves the fit out of an existing retail style shell space on the ground floor of Dominick Hall, Dominick Street Lower, as part of a decant project for the Rotunda hospital. Units 1 to 6 Dominick Hall were designed as commercial space with 5 floors of residential units above. The net fit out internal floor area is approximately 2,703 m2. The fit out will include non-acute laboratory services, gynaecology outpatient department, phlebotomy and associated ancillary staff facilities for the Rotunda Hospital. The proposed works are to include minor strip out of existing finishes and fit out of 3 no. units, as ambulatory healthcare facility with associated ancillary staff facilities. This will include the fit-out of new pathology labs as well as various types of clinical healthcare observation, diagnosis, treatment and examination rooms and other associated ancillary rooms such as waiting areas, offices, comms room, dirty and clean utilities, staff changing and staff rest areas. The fit out works will be designed to achieve a minimum BER A3 rating, in accordance with the requirements of the Climate Action Plan (CAP), and various applicable BCAR technical guidance documents and in compliance with applicable Health Building Notes and Health Technical Memoranda. The mechanical and electrical installations will be domestic sub-contracts and will entail the full fit-out of the clinical and laboratory areas, as well as some upgrades and additions to the existing mechanical and electrical plant and equipment. Ventilation from the laboratory spaces will be via the existing risers on the residential floors above. The Main Contractor and its specialist subcontractors for the Mechanical and Electrical installations, and their agents and specialist vendors shall be fully aware of the requirements of HTM03 and HBN 15 specialist ventilation requirements for a Hospital Pathology Department. They should have training, knowledge, and experience in completing similar previous Pathology and Laboratory installations. The development includes associated alterations to existing plant and storerooms at basement level and plant a plant enclosure and bin store at grade level. The project will be delivered in BIM to ISO 19650. The approximate budget for the construction work is €10m, excluding Vat.

  • Contact

    Stefany GeorgievaStefany.Georgieva@hse.ie
  • Type
    Competition · Prequalification
  • Location
    Dublin
  • Main code
    Construction work
    45000000
  • 45200000Works for complete or part construction and civil engineering work45210000Building construction work45214610Laboratory building construction work45215100Construction work for buildings relating to health45215130Clinic construction work45215140Hospital facilities construction work45215143Diagnostic screening room construction work

Similar active competitions

  • Health Service Executive (HSE)

    Bygg og anlegg - Oppføring, renovering og vedlikehold av bygninger

    EST_MW - Maternity Emergency and Early Pregnancy Assessment Unit - University Maternity Hospital Limerick

    The Health Service Executive (HSE) needs construction works for an 18-month development at University Maternity Hospital Limerick in the Mid-West region of Ireland, with a maximum total contract value of €10 million. The project involves a new rapid-build facility of approximately 863 m² over two floors, including maternity emergency and assessment services, diagnostic scanning, labour induction, intensive care and procedure facilities, alongside staff and support areas. Works also include refurbishing approximately 263 m² of the existing main entrance and Medical Emergency Unit, upgrading the entrance and forecourt, landscaping, and constructing a replacement car park.

    Competition with qualification
    Dec 14, 2026(21 days)
    €10,000,000
  • Health Service Executive (HSE)

    Bedriftsrådgivning

    National Maternity Hospital at St Vincent’s University Hospital Programme Delivery Partner Services Prior Information Notice

    The Health Service Executive (HSE) is planning to procure delivery partner services for the National Maternity Hospital programme at St Vincent’s University Hospital in Dublin, supporting its team across construction, equipping, digital delivery, commissioning and transition to operations. The notice does not specify how suppliers can provide feedback or participate in the planning phase.

    Planning
    Feb 26, 2027(95 days)
    €0
  • Enable Ireland Disability Services Ltd

    Bygg og anlegg - Oppføring, renovering og vedlikehold av bygninger

    CfT for fitout and renovations of Day Services Hub - Tallaght Cross

    Enable Ireland Disability Services Ltd needs construction services for the fit-out and renovation of an existing ground floor retail unit into a Day Care Centre / Day Service Hub in Dublin. The project, with a maximum total value of 480,000 EUR, will last for 1 year and includes internal alterations, partitions and doors, accessible sanitary accommodation, finishes, mechanical and electrical services, fire safety and accessibility works, signage, and all associated works.

    Competition
    Nov 24, 2026(1 day)
    €480,000