Brief
Waterways Ireland_225 has entered into an agreement with Priority Geotechnical Limited for Ground Investigation (GI) works at Lower Tinnahinch Weir And Rock Fish Pass in Dublin. The works include cable percussion drilling, in-situ SPT N testing, permeability testing, trial pits, geophysical surveying, grab samples, and geotechnical and environmental laboratory testing. The contract has a duration of 6 months and a final value of 82,192 EUR.
Construction machinery and equipment
Result
- Priority Geotechnical LimitedWinner
- 3Number of tenders received
- €82,192Contract value
Previous winners
Who are you up against?
The suppliers who have won similar contracts at Waterways Ireland
Will you bid?
The agent sets up the bid and writes the first draft. Free for 14 days.
Award Criteria
Description
Cost
Source
No source found in the documents. Check the weight against the tender documents.
From the notice
Ground Investigation (GI) works at Lower Tinnahinch Weir And Rock Fish Pass comprises the following: • Cable percussion to maximum depth of 10m BGL • Insitu SPT N testing in all boreholes. • Insitu permeability testing in selected boreholes where ground conditions allow. • Trial pits to 3m BGL or effective refusal. • Geophysical Surveying • Grab samples • In-situ and laboratory geotechnical testing. • Laboratory environmental testing. • Standard re-instatement of works for all locations. The investigations are distributed throughout the Tinnahinch Weir And Fish Pass. Refer to the tender documents for more details.
Contact
procurement@waterwaysireland.org- ResultType
- DublinLocation
- 45120000Main codeTest drilling and boring work
- 45121000Test drilling work45122000Test boring work