MISSION DE MAITRISE D'OEUVRE RELATIVE A LA CONSTRUCTION DU CENTRE SOCIAL LANOUX A RIVE DE GIER
Awarded
The competition has ended and a winner has been selected.
- Qualification deadline
- Jan 27, 2025Expired
- Award
- Qualité architecturale, weight 10 and 2 more
Brief
Un concours de maîtrise d'oeuvre est organisé en vue de la construction du Centre social Lanoux d'environ 870m² de surface utile sur la Commune de RIVE DE GIER. Le montant estimé des travaux est de 2 800 000 euro(s) HT. Compétences demandées : architecte, BE structure, BE fluide, économiste et OPC
Arkitekttjenester
Result
- ATELIER DES VERGERSWinner
- 47Number of tenders received
- €371,000Contract value
Previous winners
Who are you up against?
The suppliers who have won similar contracts at Mairie de Rive de Gier
Will you bid?
The agent sets up the bid and writes the first draft. Free for 14 days.
Award Criteria
Description
Qualité de la réponse apportée au programme
Source
No source found in the documents. Check the weight against the tender documents.
Description
Qualité architecturale
Source
No source found in the documents. Check the weight against the tender documents.
Description
Intégration paysagère dans le site
Source
No source found in the documents. Check the weight against the tender documents.
Description
Prix
Source
No source found in the documents. Check the weight against the tender documents.
From the notice
Un concours de maîtrise d'oeuvre est organisé en vue de la construction du Centre social Lanoux d'environ 870m² de surface utile sur la Commune de RIVE DE GIER. Le montant estimé des travaux est de 2 800 000 euro(s) HT. Compétences demandées : architecte, BE structure, BE fluide, économiste et OPC
Contact
Monsieur Le Mairemairie@ville-rivedegier.fr- Result · PrequalificationType
- 71200000Main codeArchitectural and related services