Hospital Facilities Company HOCH Health Ostschweiz requires the construction and installation of a geothermal probe system for Building 07B at St. Gallen Cantonal Hospital. The works include site establishment, drilling, supply and installation of probes with complete backfilling, horizontal connection pipes and associated earthworks, connection to the probe manifolds, and flushing, tightness and flow-rate testing, filling and documentation. Work must be coordinated with the building contractors and construction management team, with the interface to the heating system set at the handover points specified in the tender documents. Evaluation considers price, five comparable company references from the preceding five years—particularly hospital projects—project-specific quality management and organization, and the proposed methods, resources and equipment; the Project Manager and Deputy Project Manager must each have at least five years of industry experience.
Previous winners
Who are you up against?
The suppliers who have won similar contracts at Hospital Facilities Company HOCH Health Ostschweiz
Will you bid?
The agent sets up the bid and writes the first draft. Free for 14 days.
Award Criteria
Description
Net tendered contract price, including VAT, as stated in the tender summary reviewed and adjusted by the Client (Part B, Tender and Supporting Documents for the Award Procedure for Construction Works; KBOB Document No. 13).
Source
No source found in the documents. Check the weight against the tender documents.
Description
Company references demonstrating the completion of five projects comparable to the intended assignment, particularly with regard to execution in a hospital environment, within the five years preceding the tender submission deadline. Form 4 (Part B, Tender and Supporting Documents for the Award Procedure for Construction Works; KBOB Document No. 13) must be used to provide the required information.
Source
No source found in the documents. Check the weight against the tender documents.
Description
Is not assessed separately. The sustainability requirements stipulated in the other tender documents remain binding.
Source
No source found in the documents. Check the weight against the tender documents.
Description
Development of an effective, project-specific quality management system (PQM), including an analysis of the risks, potential mitigation measures and opportunities (contract analysis). Compliance with the concepts specified by the client and the specialist planners. Complete provision of all information required in the bill of quantities. Particular emphasis will be placed on the key personnel designated for the project (Project Manager and Deputy Project Manager). They must demonstrate at least five years of industry experience. Supporting evidence must be submitted as appendices to Forms 5, 6 and 8 (Part B, Tender and Supporting Documents for Procurement Procedures for Construction Works; KBOB Document No. 13).
Source
No source found in the documents. Check the weight against the tender documents.
Description
Project-specific organizational chart showing the designated personnel and their responsibilities; overview of human and technical resources, particularly the site facilities and installations; machinery concept, including the equipment and drilling rigs to be used; resource concept describing resource allocation and deployment planning; work processes and execution methods; and a description of the planned inspection, monitoring, and testing procedures. The supporting documentation must be submitted as annexes to Form 3 (Part B, Tender and Supporting Documents for Procurement Procedures for Construction Works; KBOB Document No. 13).
Source
No source found in the documents. Check the weight against the tender documents.
From the notice
The tender for geothermal boreholes covers the installation of the geothermal probe system for Building 07B at St. Gallen Cantonal Hospital. The scope of work includes site establishment, drilling operations, and the supply, installation, and complete backfilling of the geothermal probes in accordance with the tender documents. The scope also includes the horizontal connection pipes and their connection to the geothermal probe manifolds, including all required earthworks. The system must be flushed, tested for tightness and flow rate, and filled in accordance with the design specifications. All completed works and tests must be documented. The interface with the building-side heating system is defined by the handover points specified in the tender documents. All works must be coordinated with the contractors involved and the construction management team.
Contact
ausschreibungen.bau@kssg.ch- CompetitionType
- St. GallenLocation
- 45000000Main codeConstruction work
- 45215140Hospital facilities construction work45251141Geothermal power station construction work45262200Foundation work and water-well drilling