Obras Relativas al Proyecto de “Recinto número cuatro para material procedente de dragado en la margen derecha de la ría de Huelva. 2ª Fase”. “Plan de Recuperación, Transformación y Resiliencia-Financiado por la Unión Europea – NextGenerationEU”.
Awarded
The competition has ended and a winner has been selected.
- Deadline
- Apr 7, 2025Expired
- Award
- Calidad Técnica, weight 50
Brief
Procedimiento abierto ordinario
Result
- ACCIONA CONSTRUCCIÓN, S.A.Winner
- 4Number of tenders received
- €9,350,983Contract value
Previous winners
Who are you up against?
The suppliers who have won similar contracts at Presidencia de la Autoridad Portuaria de Huelva
Will you bid?
The agent sets up the bid and writes the first draft. Free for 14 days.
Award Criteria
Description
Precio.
Source
No source found in the documents. Check the weight against the tender documents.
Description
Calidad Técnica.
Source
No source found in the documents. Check the weight against the tender documents.
From the notice
Procedimiento abierto ordinario
Contact
Presidencia de la Autoridad Portuaria de Huelvaaph@puertohuelva.com- ResultType
- HuelvaLocation
- 45244000Main codeMarine construction works