Slovenské elektrárne, a.s. has awarded Voith Hydro GmbH & Co KG a supply contract to modernize a pump and turbine system for variable-speed operation in the Žilina Region of Slovakia, improving efficiency, flexible power management and frequency regulation. The contract’s final value is €65,444,300, compared with a stated maximum of €63.1 million, and two bids were received.
Industrimaskiner
Result
- Voith Hydro GmbH & Co KGWinner
- 2Number of tenders received
- €65,444,300Contract value
Previous winners
Who are you up against?
The suppliers who have won similar contracts at Slovenské elektrárne, a.s.
Will you bid?
The agent sets up the bid and writes the first draft. Free for 14 days.
Qualification requirements
Description
A list of deliveries of goods/provided services of equal or similar nature and complexity as that of the tender subject matter carried out during the preceding twenty years prior to the declaration of the public procurement, with indication of delivery period, customers, contact person for the customer – name, phone number, email, scope of the project, main parameters of the project mainly highest maximum achieved efficiency in turbine operation demonstrated from model tests and highest maximum achieved efficiency in pump operation demonstrated from model tests. Minimum required level of the standard: The list of deliveries of goods/provided services and information about individual references should make it clear that the Candidate within the relevant period delivered the goods/provided services of equal or similar nature to that of the tender subject matter. Delivery of goods/provision of services of equal or similar nature to that of the tender subject matter shall be deemed to constitute the following activities on a power plant with minimum turbine power 80 MW with power control by variable speed in pump mode: • design of hydraulic profiles of the whole hydraulic parts of the unit with power control using variable speeds in pump and turbine mode. Design implemented using CFD modelling and physical model (model tests). • manufacture of a new turbine and pump runner with variable speed power control or a reversible turbine runner with variable speed power control in pump and turbine mode. • installation of equipment with variable speed control in pump mode. Evidence of each of the activities described does not need be from a single completed project. At least one reference for a design and implementation of a high-pressure hydraulic system for the control and regulation of a turbine with a capacity of at least 20 MW is required. Twenty years interval for the provided goods and services was chosen because the scale and the rare occurance of such projects. Therefore, the 3-year interval would not even cover the length of such projects.
Documentation Requirement
In accordance with the provision of Section 34 (a) of the Public Procurement Act: A list of deliveries of goods/provided services of equal or similar nature and complexity as that of the tender subject matter carried out during the preceding twenty years prior to the declaration of the public procurement, with indication of delivery period, customers, contact person for the customer – name, phone number, email, scope of the project, main parameters of the project mainly highest maximum achieved efficiency in turbine operation demonstrated from model tests and highest maximum achieved efficiency in pump operation demonstrated from model tests.
Source
No source found in the documents. Check the requirement against the tender documents.
Description
At least 1 person meeting the following requirements: • Working experience of at least 5 years in the field of designing hydraulic profiles of flowing parts of machinery using CFD modeling • At least one practical experience with designing hydraulic profiles of flowing parts of machinery with variable speed regulation in pump mode. A person on whose capacity a Candidate relies to prove the satisfaction of this condition must be involved in the performance of the Contract and in the Tasks during the Competitive Dialogue. Such workers shall also be indicated in the Contract.
Documentation Requirement
Information on education and professional experience or professional qualification of managerial staff (experts) responsible for managing the services/civil works. A Candidate shall prove their professional capacity to provide the required performance through a confirmation stating that the Candidate has available the below specified experts meeting the set requirements, in the required number. The below specified requirements for an expert shall be proven by the Candidate as follows: a) by presenting a professional CV containing at least the following: * first name and surname; * completed education; * current job position; * overview of professional experience relating to the performance of the tender subject matter; * signature in own hand of the expert. b) in the case that the Candidate is not the current employer of the relevant expert, by presenting a written contract entered into by and between the Candidate and the expert (pursuant to the identification below) concerning the use of professional capacity of the expert in performing the contract with the Candidate, provided that the Candidate succeeds in this public procurement. c) by presenting the original/verified copy of the requested document concerning the professional capacity d) by presenting a copy of the document on the completed education.
Source
No source found in the documents. Check the requirement against the tender documents.
Description
At least 1 person meeting the following requirements: • Working experience of at least 5 years in the field of hydropower – design of suspension structures • At least one practical experience with designing of suspension structures on a project with minimum turbine power 80 MW with power control by variable speed in pump mode. A person on whose capacity a Candidate relies to prove the satisfaction of this condition must be involved in the performance of the Contract and in the Tasks during the Competitive Dialogue. Such workers shall also be indicated in the Contract.
Documentation Requirement
Information on education and professional experience or professional qualification of managerial staff (experts) responsible for managing the services/civil works. A Candidate shall prove their professional capacity to provide the required performance through a confirmation stating that the Candidate has available the below specified experts meeting the set requirements, in the required number. The below specified requirements for an expert shall be proven by the Candidate as follows: a) by presenting a professional CV containing at least the following: * first name and surname; * completed education; * current job position; * overview of professional experience relating to the performance of the tender subject matter; * signature in own hand of the expert. b) in the case that the Candidate is not the current employer of the relevant expert, by presenting a written contract entered into by and between the Candidate and the expert (pursuant to the identification below) concerning the use of professional capacity of the expert in performing the contract with the Candidate, provided that the Candidate succeeds in this public procurement. c) by presenting the original/verified copy of the requested document concerning the professional capacity d) by presenting a copy of the document on the completed education.
Source
No source found in the documents. Check the requirement against the tender documents.
Description
Minimum of 1 person with the following requirements: • Working experience of at least 5 years on hydro power projects. A person on whose capacity a Candidate relies to prove the satisfaction of this condition must be involved in the performance of the Contract and in the Tasks during the Competitive Dialogue. Such workers shall also be indicated in the Contract.
Documentation Requirement
Information on education and professional experience or professional qualification of managerial staff (experts) responsible for managing the services/civil works. A Candidate shall prove their professional capacity to provide the required performance through a confirmation stating that the Candidate has available the below specified experts meeting the set requirements, in the required number. The below specified requirements for an expert shall be proven by the Candidate as follows: a) by presenting a professional CV containing at least the following: * first name and surname; * completed education; * current job position; * overview of professional experience relating to the performance of the tender subject matter; * signature in own hand of the expert. b) in the case that the Candidate is not the current employer of the relevant expert, by presenting a written contract entered into by and between the Candidate and the expert (pursuant to the identification below) concerning the use of professional capacity of the expert in performing the contract with the Candidate, provided that the Candidate succeeds in this public procurement. c) by presenting the original/verified copy of the requested document concerning the professional capacity d) by presenting a copy of the document on the completed education.
Source
No source found in the documents. Check the requirement against the tender documents.
Award Criteria
Description
The criteria for evaluating offers (hereinafter referred to as the "Criteria") established for the purpose of selecting the best price-quality ratio.
Source
No source found in the documents. Check the weight against the tender documents.
From the notice
Modernization of the turbine and the pump with variable speed range with regard to optimal efficiency of the whole machine system, flexible power management in the individual modes and with best frequency regulation of the power system while meeting or exceeding the needs and requirements – Objectives of the Tender. The scope of the subject matter will be defined during the procurement process and can be adjusted by SE based on technical, economical, commercial, environmental or permitting circumstances. The subject of this tender is a part of the project Integrator SE.
Contact
ema.cveckova@seas.sk- Result · PrequalificationType
- Žilinský krajLocation
- 42112200Main codeHydraulic turbines
- 42112000Turbine installations42113200Parts of hydraulic turbines42120000Pumps and compressors45220000Engineering works and construction works45315200Turbine works71320000Engineering design services