Search

  • Search


    Qualification System for Large Power Transformers (LPTs)

    EnBW Energie Baden-Württemberg AG

    Qualification System for Large Power Transformers (LPTs)

    1. Contract start date

      May 12, 12:00 AMMay 12, 2026 12:00 AM
    2. Competition notice published

      May 12, 5:32 PMMay 12, 2026 5:32 PM
    3. Tender submission deadline

      May 12, 7:32 PMMay 12, 2026 7:32 PM
    4. Contract end date

      Dec 31, 12:00 AMDecember 31, 2032 12:00 AM

    Brief

    Tender search/EnBW Energie Baden-Württemberg AG/Qualification System for Large Power Transformers (LPTs)
    Brief

    EnBW Energie Baden-Württemberg AG needs to prequalify suppliers for the supply of three-phase power transformers ranging from 15 MVA to 100 MVA for the 380kV grid. The qualification system contains critical electrical data and implementation guidelines to ensure performance, safety, and compatibility with their existing infrastructure. The project location is Karlsruhe, Stadtkreis.

    About the bid

      The present qualification system serves as the prequalification for the supply of three-phase power transformers ranging from 15 MVA to 100 MVA. Companies with the capability to deliver large power transformers for the 380kV grid in the above mentioned power range are invited to submit their requests for participation. This qualification system contains critical electrical data and implementation guidelines to ensure performance, safety and compatibility with our existing infrastructure.

      Contact phone
      +49 7216323252
      Contact email
      l.bernau@enbw.com
      Address
      Durlacher Allee 93, 76131 Karlsruhe

    Custom Assessment Criteria

    Start a free trial to ask your own questions about the tender and get AI-generated answers.

    Award Criteria

      Found no award criteria in the contract notice.

    Qualification requirements

      Found no qualification requirements in the contract notice.

    Previous Contract Winners

    Start a free trial to see who has won similar tenders for this buyer.

    See the full notice

    Contracting authority
    EnBW Energie Baden-Württemberg AG
    Title
    Qualification System for Large Power Transformers (LPTs)
    Type
    Competition
    Main code
    31171000Liquid dielectric transformers
    Supplemental codes

    No supplemental codes from buyer…

    Location
    Karlsruhe, Stadtkreis

    Active similar competitions

    • EnBW Energie Baden-Württemberg AG

      Elektrisk infrastruktur og veibelysning

      Qualification system for grounding transformers

      EnBW Energie Baden-Württemberg AG needs grounding transformers for the medium-voltage network (10-30 kV). This qualification system serves as prequalification to ensure all potential suppliers comply with technical requirements, commercial, and procedural criteria for approved supplier status.

      Qualification systemApr 29, 2026
      May 27, 2029(100+ days)
    • Netze BW GmbH

      Leistungstransformatoren 15-100 MVA

      The present qualification system serves as the prequalification for the supply of three-phase power transformers ranging from 15 MVA to 100 MVA. Companies with the capability to deliver power transformers in the above mentioned power range are invited to submit their requests for participation. This qualification system contains critical electrical data and implementation guidelines to ensure performance, safety and compatibility with our existing infrastructure.

      Qualification systemOct 10, 2024
      Nov 7, 2027(100+ days)
    • EnBW Energie Baden-Württemberg AG

      Elektrisk utstyr og belysning

      Qualifizierungssystem für die Herstellung und Lieferung von Niederspannungsverteilungen

      Die EnBW Energie Baden-Württemberg AG benötigt ein Qualifizierungssystem für die Herstellung und Lieferung von Niederspannungsverteilungen, die in Umspannstationen eingesetzt werden. Ziel ist es, geeignete Unternehmen für künftige Vergabeverfahren vorab zu qualifizieren. Alle Artikel müssen nachweislich die Vorgaben der Energiewirtschaftsgesetze (EnWG) erfüllen.

      Qualification systemJul 3, 2026
      Jul 31, 2029(100+ days)
    • Netze BW GmbH

      Elektrisk infrastruktur og veibelysning

      Combined Transformer 123 kV AIS (Air Insulated Switchgear)

      Netze BW is seeking requests for participation for high-quality combined current and voltage transformers for our 123 kV applications. Companies with the capability to meet our technical specifications are invited to submit their requests for participation. This qualification system contains critical electrical data and implementation guidelines to ensure performance, safety, and compatibility with our existing infrastructure.

      Qualification systemAug 21, 2024
      Sep 18, 2027(100+ days)
    • EAM GmbH & Co.KG

      Präqualifikationsverfahren für Mittelleistungstransformatoren (>20 kV)

      Präqualifikationsverfahren für Mittelleistungstransformatoren (>20 kV) Mittelleistungstransformatoren 6,3 bis 80 MVA Erstellung bzw. Erweiterung einer Liste qualifizierter Unternehmen zur weiteren Auswahl von Bietern im Rahmen von Verhandlungsverfahren zum Abschluss von Rahmenverträgen und Projektverträgen. Bereits präqualifizierte Lieferanten brauchen keinen neuen Teilnahmeantrag stellen.

      Qualification systemJul 1, 2025
      Jul 29, 2028(100+ days)