Find

  • All tenders
Ireland: Tenders/Tipperary County Council/R498 Latteragh Realignment Scheme

R498 Latteragh Realignment Scheme

Awarded

The competition has ended and a winner has been selected.

Deadline
Nov 4, 2025Expired
Award
Technical Merit, weight 70
Procedure
OpenSingle stage
Agreement
Construction work
Estimated value
€22Mover 18 months

Brief

Tipperary County Council has entered into an agreement with Wills Bros Ltd_21605 for the R498 Latteragh Realignment Scheme, involving the construction of 4.3km of a regional road in Co. Tipperary. The works include realignment of the R498 to a Type 2 single carriageway, a shared active travel route, realignment of three local side roads, site clearance, fencing, road restraint systems, drainage, earthworks, pavements, traffic signs, road markings, landscaping, environmental mitigation, contractor-designed structures, service ducts for utilities, and two new over bridges across the Nenagh River, and two new accommodation underpasses. The contract has a duration of 18 months and a final value of 19,778,350 EUR. Eight bids were received for this contract.

Vei- og gatearbeid

Result

TED
  • Wills Bros Ltd
    Winner
  • Number of tenders received
    8
  • Contract value
    €19,778,350

Previous winners

  • Who are you up against?

    The suppliers who have won similar contracts at Tipperary County Council

Will you bid?

The agent sets up the bid and writes the first draft. Free for 14 days.

Award Criteria

  • Description

    Price 30%

    Source

    No source found in the documents. Check the weight against the tender documents.

  • Description

    Technical Merit 70%

    Source

    No source found in the documents. Check the weight against the tender documents.

From the notice

  • The R498 Latteragh Realignment scheme involves the construction of 4.3km of a route improvement scheme for the R498 in Co. Tipperary. The scope of works of this contract involves: - Realignment of approximately 4.3 km of Regional road to a Type 2 single carriageway with a standard cross section consisting of a 7.0m carriageway with 2 x 0.5m hard strips and 2 x 2.5m grass verges in accordance with TII DN-GEO-03036. - Shared active travel route; - Realignment of 3 no. local side roads and the construction of numerous direct accesses; - Site Clearance; - Fencing, Boundary Treatments and Accommodation Works; - Road Restraint Systems; - Drainage; - Earthworks; - Pavements, Kerbs, Footways and Paved Areas; - Traffic Signs and Road Markings; - Landscaping and Environmental Mitigation; - Contractor Designed Structures; - Services ducts for Utilities works including diversions; - Two new over bridges across the Nenagh River; - Two new accommodation underpasses.

  • Contact

    secretary@tipperarycoco.ie
  • Type
    Result
  • Location
    Mid-West
  • Main code
    Road construction works
    45233120
  • 45221100Construction work for bridges45221111Road bridge construction work45233121Main road construction works45233162Cycle path construction work

Similar active competitions

  • Clare County Council

    Oppføring av bygninger

    Claureen Link Road Phase 1

    Clare County Council needs construction of the approximately 650-metre Claureen Link Road in the Mid-West of Ireland, with a maximum total contract value of €5.5 million and a duration of 1 year. The works will connect a proposed roundabout on Drumcliffe Road/Claureen Drive to a new arm on the N85/Lahinch Road roundabout and include site clearance, fencing and boundary works, drainage and culverts, earthworks, pavements, kerbs and footways, traffic signs and road markings, public lighting, landscaping, utility ducts, watermain works and diversions, and cycle-track works.

    Competition
    Dec 9, 2026(17 days)
    €5,500,000
  • Kildare County Council_385

    Anleggs- og infrastrukturbygging

    Newbridge Southern Ring Road and Bridge for Kildare County Council

    Kildare County Council needs civil engineering construction works for the Newbridge Southern Ring Road and Bridge, with a project duration of 18 months and a maximum total contract value of €18 million. The works comprise 790 metres of new road, including a five-span bridge approximately 170 metres long across the River Liffey, connections to existing roads and utilities, underground utilities, public lighting, and associated works. Construction will take place in a live environment in the Mid-East region of Ireland.

    Competition with qualification
    Nov 30, 2026(8 days)
    €18,000,000
  • Limerick City and County Council_103432

    Rådgivende ingeniørtjenester for bygg og anlegg

    Multidisciplinary Services for the Castletroy Link, Limerick - Stages 5-7

    Limerick City and County Council needs multidisciplinary services for the Castletroy Link, Limerick, for a new distributor road approximately 680m in length, including a 9.7m wide carriageway with two traffic lanes and a 3.5m wide bus lane, footpaths, segregated cycle track, and planted verges with 1 in 2 road embankment side slopes. The contract has a maximum total value of 1,500,000 EUR and a duration of 40 months. The project location is South-West.

    Competition
    Nov 23, 2026(1 day)
    €1,500,000