Road Markings, thermoplastic in northern part of West Region, North Region, and East Region 2024-2026
Awarded
The competition has ended and a winner has been selected.
- Deadline
- Jun 16, 2025Expired
- Award
Brief
The Icelandic Road and Coastal Administration opens tender for thermoplastic road markings in the northern part of the country. The work is divided into three regions: Northen part of West Region, North Region and East Region. This involves marking midlines and other lines on roads with bound road surfaces for the years 2024 - 2026. The project is tendered for three years with the possibility of extending the contract in the summers of 2027 and 2028. The estimated work length is 1,658 km. The main quantities, based on one year, are: Sprayplasted midlines 0.7 mm thick 1,100 km Sprayplasted midlines 1.0 mm thick 280 km Sprayplasted midlines 1.5 mm thick 270 km Plastic stripes b = 200 mm, thickness = 1.0 mm 4 km Plastic stripes b = 200 mm, thickness = 1.5 mm 4 km Working days 100 days The project must be fully completed by October 1, each year.
Asphalt and road surfaces
Result
- Vegamálun ehfWinner
- G.I. Halldórsson ehfBidder
- Vegamál Vegmerking ehf.Bidder
- 3Number of tenders received
- ISK 119,478,000Contract value
Previous winners
Who are you up against?
The suppliers who have won similar contracts at Vegagerðin
Will you bid?
The agent sets up the bid and writes the first draft. Free for 14 days.
Award Criteria
Description
Lowest price
Source
No source found in the documents. Check the weight against the tender documents.
From the notice
The Icelandic Road and Coastal Administration opens tender for thermoplastic road markings in the northern part of the country. The work is divided into three regions: Northen part of West Region, North Region and East Region. This involves marking midlines and other lines on roads with bound road surfaces for the years 2024 - 2026. The project is tendered for three years with the possibility of extending the contract in the summers of 2027 and 2028. The estimated work length is 1,658 km. The main quantities, based on one year, are: Sprayplasted midlines 0.7 mm thick 1,100 km Sprayplasted midlines 1.0 mm thick 280 km Sprayplasted midlines 1.5 mm thick 270 km Plastic stripes b = 200 mm, thickness = 1.0 mm 4 km Plastic stripes b = 200 mm, thickness = 1.5 mm 4 km Working days 100 days The project must be fully completed by October 1, each year.
Contact
Gísli Gíslasongigi@vegagerdin.is- ResultType
- 45233220Main codeSurface work for roads