SC Penz - Impianto alta tensione GIS 72.5 kV
Awarded
The competition has ended and a winner has been selected.
- Deadline
- Nov 5, 2025Expired
- Award
Brief
AGE SA hat einen Vertrag mit IT_GE Grid (Switzerland) GmbH über die Lieferung, Montage und Inbetriebnahme einer 72,5 kV GIS-Hochspannungs-Primärverteilungsanlage für die Umspannstation Penz in Chiasso, Tessin, im Wert von 1.674.469 CHF abgeschlossen. Die Anlage wird aus 6 Hochspannungs-Ständen (72,5 kV, 1600 A) mit einfacher Sammelschiene bestehen.
Elektrisk utstyr og belysning
Result
- IT_GE Grid (Switzerland) GmbHWinner
- 1Number of tenders received
- CHF 1,674,469Contract value
Previous winners
Who are you up against?
The suppliers who have won similar contracts at AGE SA
Will you bid?
The agent sets up the bid and writes the first draft. Free for 14 days.
Award Criteria
Description
Criteri di aggiudicazione
Source
No source found in the documents. Check the weight against the tender documents.
From the notice
Fornitura, montaggio e messa in servizio di un impianto di distribuzione primaria alta tensione GIS 72.5 kV per la sottocentrale Penz di Chiasso. L'impianto sarà composto da 6 stalli AT 72.5 kV, 1600 A a sbarra semplice (2 semi-sbarre collegate attraverso uno stallo di congiunzione, 3 stalli linea e 2 stalli trasformatore).
Contact
info@age-sa.ch- ResultType
- TicinoLocation
- 31200000Main codeElectricity distribution and control apparatus
- 31214000Switchgear