Find

  • All tenders
Ireland: Tenders/Department of Housing Local Government and Heritage/Shannon Harbour Hard Edge

Shannon Harbour Hard Edge

Awarded

The competition has ended and a winner has been selected.

Deadline
Jun 3,Expired
Award
Quality, weight 30 and 2 more
Procedure
OpenSingle stage
Agreement
Construction work
Estimated value
€447.8Kover 4 months

Brief

Waterways Ireland_225 has entered into an agreement with Brian Conneely and Company. Ltd for the delivery of works related to the "Shannon Harbour Hard Edge" project, which involves stripping the existing canal bank, driving timber piles, constructing timber jetties with bank supports and bracing, installing service bollards with associated utility works, and constructing connecting access pathways and landscaping. The contract has a duration of 4 months and a final value of 447,751 EUR. The award was based on cost (70%) and quality (30%).

Anleggs- og infrastrukturbygging

Result

TED
  • Brian Conneely and Company. Ltd
    Winner
  • Number of tenders received
    4
  • Contract value
    €447,751

Previous winners

  • Who are you up against?

    The suppliers who have won similar contracts at Department of Housing Local Government and Heritage

Will you bid?

The agent sets up the bid and writes the first draft. Free for 14 days.

Award Criteria

  • Description

    Cost

    Source

    No source found in the documents. Check the weight against the tender documents.

  • Description

    Quality

    Source

    No source found in the documents. Check the weight against the tender documents.

  • Description

    Cost

    Source

    No source found in the documents. Check the weight against the tender documents.

  • Description

    Quality

    Source

    No source found in the documents. Check the weight against the tender documents.

From the notice

  • The proposed Works involve stripping of the existing canal bank for the length of the proposed jetties, driving timber piles into the canal edge and bank, construction of timber jetties including bank supports and bracing, installation of service bollards with associated utility works, construction of connecting access pathways and landscaping.

  • Contact

    procurement@waterwaysireland.org
  • Type
    Result
  • Location
    Dublin
  • Main code
    Construction work
    45000000
  • 45100000Site preparation work45200000Works for complete or part construction and civil engineering work

Similar active competitions

  • APDL - Administração dos Portos do Douro, Leixões e Viana do Castelo, SA

    Ferjekaier og maritime anlegg

    Empreitada de reconstrução do Cais da Ferradosa e estabilização dos taludes adjacentes

    A APDL – Administração dos Portos do Douro, Leixões e Viana do Castelo, SA, pretende contratar, por empreitada com duração de 2 anos e valor máximo total de 6,7 milhões de euros, a reconstrução do Cais da Ferradosa e a estabilização dos taludes adjacentes, na Área Metropolitana do Porto. A adjudicação será baseada no preço.

    Competition
    Nov 26, 2026(4 days)
    €6,700,000
  • Údarás Na Gaeltachta_289

    Anleggs- og infrastrukturbygging

    Bealach Seanadh Mhach- Phase 2

    Údarás na Gaeltachta needs construction works for Phase 2 of the Bealach Seanadh Mhach Trails Project in Ireland’s Mid-West, with a maximum total contract value of €450,000 and a duration of 1 year. The project comprises approximately 325 metres of recycled-plastic boardwalk, 140 metres of geogrid walkway and three bridge crossings, together with associated civil engineering, structural and ancillary works.

    Competition
    Dec 9, 2026(17 days)
    €450,000
  • Dublin City Council

    Anleggs- og infrastrukturbygging

    DCC - Multi-Party Framework Agreement for carrying out Roadworks in a City and Suburban Environment for Contracts greater than €1.0m and less than €8.0m

    Dublin City Council needs roadworks, public realm improvement works, cycle track works, and other engineering works in a live city and sub-urban environment in Dublin, Ireland, through a multi-party framework agreement over 4 years, with a maximum total value of 150,000,000 EUR. The contracts under the framework will be for values greater than 1,000,000 EUR and less than 8,000,000 EUR.

    Framework agreement with qualification
    Nov 25, 2026(3 days)
    €150,000,000