Single Party Framework for Quay Walls and Marine and Civil Engineering Works at Dublin Port.

Awarded

The competition has ended and a winner has been selected.

Qualification deadline
May 25,Expired
Award
Cost, weight 40
Procedure
With negotiationTwo stages
Agreement
Framework agreement
Estimated value
€20M

Brief

Dublin Port Company has entered into a single-party framework agreement with Murphy International Limited for quay walls and marine and civil engineering works at Dublin Port, with an initial contract for Berth 29. The framework agreement has a maximum total estimated value of 20,000,000 EUR. The works may include removal of existing quay furniture, excavation, installation of quay walls, anchor walls, crane rails, tie rods, mechanical and electrical services, utility services, concrete pavement, marine furniture, marina, demolition works, services diversions, port buildings, conservation works, yard re-surfacing, fencing, roads, conveyors, link-spans, ramps, contractor design services, and marine works. Four bids were received for this contract.

Oppføring av bygninger

Result

TED
  • Murphy International Limited
    Winner
  • Number of tenders received
    4
  • Contract value
    Not stated
  • Maximum framework agreement valueUp to €200,000,000

Previous winners

  • Who are you up against?

    The suppliers who have won similar contracts at Dublin Port Company_411

Will you bid?

The agent sets up the bid and writes the first draft. Free for 14 days.

Award Criteria

  • Description

    A number of criteria under the quality banner - total 60 percent of marks.

    Source

    No source found in the documents. Check the weight against the tender documents.

  • Description

    Cost criterion

    Source

    No source found in the documents. Check the weight against the tender documents.

From the notice

  • Dublin Port invited tenders on foot of a qualification system notice advertised in 2022. The competition relates to the establishment of a framework agreement with an initial contract for Berth 29 at Dublin Port. Subsequent Packages may consist of adjacent master-plan projects. These subsequent work packages may be negotiated with the Single Party framework Contractor. The works, in general, may include: Removal of existing quay furniture, excavation of existing hard standings, installation of quay walls, anchor walls, crane rails, tie rods, Mechanical and Electrical, utility services, concrete pavement, marine furniture, marina, demolition works, services diversions, port buildings, conservation works, yard re-surfacing, fencing, roads, conveyors, link-spans, Ramps, contractor design Services, marine works, etc.Main features of the procedureA qualification system notice was published in the Official Journal on 30th April 2022. This system entitled Dublin Port to shortlist intersted parties for specific contracts or framework agreements.

  • Contact

    pburns@dublinport.ie
  • Type
    Result · Framework agreement · Prequalification
  • Location
    Dublin
  • Main code
    Works for complete or part construction and civil engineering work
    45200000
  • 45244000Marine construction works

Similar active competitions

  • The Land Development Agency

    Anleggs- og infrastrukturbygging

    Multi-Party Framework Agreement for the Provision of Technical Construction Quality Assurance and Quality Control (QAQC) Services (Pro450)

    The Land Development Agency needs technical construction quality assurance and quality control (QA/QC) monitoring services for residential units at different stages of development across Dublin, through a multi-party framework agreement lasting 4 years, with a maximum total value of €50 million. The services will support quality monitoring across the Agency’s residential development portfolio.

    Framework agreement
    Dec 15, 2026(22 days)
    €50,000,000
  • Dublin City Council

    Anleggs- og infrastrukturbygging

    DCC - Multi-Party Framework Agreement for carrying out Roadworks in a City and Suburban Environment for Contracts greater than €1.0m and less than €8.0m

    Dublin City Council needs roadworks, public realm improvement works, cycle track works, and other engineering works in a live city and sub-urban environment in Dublin, Ireland, through a multi-party framework agreement over 4 years, with a maximum total value of 150,000,000 EUR. The contracts under the framework will be for values greater than 1,000,000 EUR and less than 8,000,000 EUR.

    Framework agreement with qualification
    Nov 25, 2026(2 days)
    €150,000,000
  • APDL - Administração dos Portos do Douro, Leixões e Viana do Castelo, SA

    Ferjekaier og maritime anlegg

    Empreitada de reconstrução do Cais da Ferradosa e estabilização dos taludes adjacentes

    A APDL – Administração dos Portos do Douro, Leixões e Viana do Castelo, SA, pretende contratar, por empreitada com duração de 2 anos e valor máximo total de 6,7 milhões de euros, a reconstrução do Cais da Ferradosa e a estabilização dos taludes adjacentes, na Área Metropolitana do Porto. A adjudicação será baseada no preço.

    Competition
    Nov 26, 2026(3 days)
    €6,700,000