Ireland: Tenders/Kerry County Council_1204/South Kerry Greenway - Design and Build Contract

South Kerry Greenway - Design and Build Contract

Published deadline passed

The published deadline has passed. For multi-stage competitions a later tender deadline may still apply — check the notice or portal for the current phase.

Qualification deadline
Mar 19,Expired
Procedure
With prequalificationTwo stages
Agreement
Construction work
Estimated value
€24Mover 30 months

Brief

Kerry County Council needs design and build services for the South Kerry Greenway, specifically for Greenway Section 2A (Ch 18,150 to Ch 21,231), Greenway Section 2C (Ch 22,145 to Ch 25,678), N70 Overbridge (CH 26,870), and Kells Car Park (CH 18,150), with a maximum total value of 24,000,000 EUR over 30 months. The works encompass all necessary elements to complete the greenway, including design, PSDP Services, PSCS Services, environmental management, earthworks, drainage, pavement, fencing, landscaping, signage, slope stabilization, retaining wall construction, rehabilitation of existing structures, construction of new structures, road realignment, and traffic management. The project requires strict environmental controls, including adherence to the Construction Environmental Management Plan (CEMP) and other environmental management plans, particularly concerning the Kerry Slug. The competition has multiple phases, with pre-qualified candidates invited to a second stage tender, where awards will be based on the Most Economically Advantageous Tender, with 70% weighting on Quality and 30% on Price.

Bygg og anlegg - Bruer og tunneler

Register interest

Previous winners

  • Who are you up against?

    The suppliers who have won similar contracts at Kerry County Council_1204

Will you bid?

The agent sets up the bid and writes the first draft. Free for 14 days.

From the notice

  • Kerry County Council, with the support of Transport Infrastructure Ireland (TII), are developing the South Kerry Greenway which involves the construction of a 27 km greenway between Glenbeigh and Cahersiveen Co. Kerry. The route has been split up into several construction packages with Kerry County Council undertaking the construction of some of the works under direct labour. This tender competition covers the Design and Build elements of the scheme only, which includes Greenway Section 2A (Ch 18,150 to Ch 21,231), Greenway Section 2C (Ch 22,145 to Ch 25,678), N70 Overbridge (CH 26,870) and Kells Car Park (CH 18,150). The works requirements for the above sections will encompass all works necessary to complete the greenway including, design, PSDP Services, PSCS Services, environmental management, earthworks, drainage, pavement, fencing, landscaping, signage, slope stabilization, retaining wall construction, rehabilitation of existing structures, construction of new structures, road realignment, traffic management and all other services necessary to complete the works. The Design and Build Section contains a number of tunnels of historical and cultural significance. Please note the Cahersiveen (Valentia Estuary) Bridge, the Gleensk Viaduct and the N70 Underpass are not included in the scope of this Design and Build competition. It is a requirement that all the conditions imposed by the Planning Consent, the Environmental Impact Assessment Report, the associated Schedule of Environmental Commitments, and the Natura Impact Statement, and any Wildlife and Derogation Licences are complied with in full. The greenway route traverses or is in close proximity to several Special Areas of Conservation (SAC) and Special Protection Areas (SPA). The project is subject to strict environmental controls in accordance with the plans, particulars and conditions associated with the project consents. Environmental management will form a key part of the successful execution of this project. In particular, it is a requirement that construction is carried out in accordance with the Construction Environmental Management Plan (CEMP), other environmental management plans required under the EIAR and NIS, relevant Wildlife and derogation licences to create and manage a suitable receiving environment for the Kerry Slug in the area affected by the proposed greenway. A series of advance works contracts have been completed. These include the construction of a Gabion Trial Section at Mountain Stage and Site Clearance and Temporary Fencing. Candidates that are pre-qualified and shortlisted on the basis of their responses to this first stage Pre-Qualification may be invited to participate in the second stage Tender. That tender competition will be awarded on the basis of the Most Economically Advantageous Tender based on Award Criteria made up of 70 (Quality) and 30 (Price).

  • Contact

    CPCU@kerrycoco.ie
  • Type
    Competition · Prequalification
  • Location
    South-West
  • Main code
    Construction work
    45000000
  • 45221000Construction work for bridges and tunnels, shafts and subways45221243Pedestrian tunnel construction work45233162Cycle path construction work

Similar active competitions

  • Údarás Na Gaeltachta_289

    Anleggs- og infrastrukturbygging

    Bealach Seanadh Mhach- Phase 2

    Údarás na Gaeltachta needs construction works for Phase 2 of the Bealach Seanadh Mhach Trails Project in Ireland’s Mid-West, with a maximum total contract value of €450,000 and a duration of 1 year. The project comprises approximately 325 metres of recycled-plastic boardwalk, 140 metres of geogrid walkway and three bridge crossings, together with associated civil engineering, structural and ancillary works.

    Competition
    Dec 9, 2026(15 days)
    €450,000
  • Údarás Na Gaeltachta_289

    Bygg og anlegg - Grunnarbeid, vann og kloakk

    Erris Looped Walks, Corclough Village, Mullet Peninsula, Co. Mayo

    Údarás na Gaeltachta needs construction and upgrading works for walking trails at Corclough Village and the existing Erris Head Loop on the Mullet Peninsula in County Mayo, Ireland, over 18 months, with a maximum total contract value of €450,000. The works include new and improved paths, an extension to the existing boardwalk, an accessible eco-friendly public toilet, trail signage and waymarking, fencing, drainage and associated infrastructure. The procurement is an open procedure for suitably qualified and experienced contractors.

    Competition
    Jan 4, 2027(41 days)
    €450,000
  • Department of Housing Local Government and Heritage

    Landskapsarkitektur

    Garden Design for Knockreer Gardens Killarney National Park

    The Department of Housing Local Government and Heritage needs landscape architecture services for the preparation of a Conservation Design and Development Plan (CDDP) focused on the long-term practice of conservation horticulture at Knockreer House Gardens in Killarney National Park, Ireland. The contract has a duration of 1 year and a maximum total value of 70,000 EUR. The CDDP will be guided by best international practice in conservation design and interpretation, aiming to preserve the unique character and style of the gardens.

    Competition
    Jan 27, 2027(64 days)