Estimated value
€80Kover 2 months

Brief

Tawnagh Group Water Scheme needs civil engineering works for the supply, installation, and commissioning of approximately 855m of new sections of 110mm OD PE80 SDR11 pipeline, replacing existing 2-inch and 1-inch diameter distribution mains and extending the network, over 2 months, with a maximum total value of 80,000 EUR.

Vei- og kabeltrekking

Register interest

Previous winners

  • Who are you up against?

    The suppliers who have won similar contracts at Tawnagh Group Water Scheme

Will you bid?

The agent sets up the bid and writes the first draft. Free for 14 days.

From the notice

  • This Contract includes all civil engineering works associated with the supply, installation, and commissioning of approximately 855m of new sections of 110mm OD PE80 SDR11 pipeline, comprising the replacement of existing 2-inch and 1-inch diameter distribution mains and the extension of the network.

  • Contact

    LiamBrennan@sligococo.ie
  • Type
    Competition
  • Main code
    Ancillary works for pipelines and cables
    45232000
  • 45231111Pipeline lifting and relaying45231113Pipeline relaying works45232100Ancillary works for water pipelines

Similar active competitions

  • Raheen Group Water Scheme

    Oppføring av bygninger

    Raheen Group Water Scheme Watermain Replacement

    Raheen Group Water Scheme needs works to replace approximately 2.3 km of existing watermain and install a new booster pump station, including ancillary works, in Ireland’s Mid-West region. The project has a maximum total value of €900,000 and a duration of 4 months.

    Competition
    Jan 29, 2027(68 days)
    €900,000
  • Tooreen Aghamore GWS

    Rørlegger- og sanitærarbeid

    Tooreen Aghamore Group Water Supply Scheme - Water Meter Upgrade and Network Improvement Works Phase 2

    Tooreen Aghamore GWS needs water network improvement works in Ireland’s Western Region over 6 months, with a maximum contract value of €500,000. The works comprise replacing and installing water distribution pipelines, consumer water meters and bulk flow meters, including data loggers. The contract will be awarded to the most economically advantageous tender based on quality and price.

    Competition
    Dec 11, 2026(19 days)
    €500,000
  • MM S.p.A.

    Anleggs- og infrastrukturbygging

    06/01/SQ-LAVORI SU RETE IDRICA

    MM S.p.A. necessita di lavori di manutenzione, bonifica, miglioramento e potenziamento della rete idrica di distribuzione e degli impianti connessi, di derivazione per utenza, attinenti il servizio idrico integrato, anche in regime di pronto intervento. Questi lavori riguardano in particolare la rete di distribuzione idrica urbana, composta da condotte, apparecchiature e manufatti per l'alimentazione di utenze private e pubbliche (utenze private e pubbliche, idranti antincendio, fontanelle stradali, idranti da innaffiamento, ecc.).

    Qualification system
    Feb 4, 2029(100+ days)