24018 - CABLE PLOUGHING - STRENGLÖG - Gilsbakki að Kalmanstungu
Awarded
The competition has ended and a winner has been selected.
- Deadline
- Nov 6, 2024Expired
- Award
Brief
The work includes cable laying from Gilsbakki to the "Into the Glacier" tourism service at Hvítá, together with soil replacement for transformers. High-voltage cables are 3x25q 24kV about 12.8 km long, low-voltage cables about 360m, ground wire about 1,400m or about 14.6 km in total. 12 substations and 2 junctions boxes are expected in this project. It is assumed that the project will start on 1st July and end on 6th September 2024.
Groundwork and rental of construction machinery
Result
- Vinnuvélar Símonar ehf.Winner
- 2Number of tenders received
- ISK 62,881,392Contract value
Previous winners
Who are you up against?
The suppliers who have won similar contracts at RARIK ohf.
Will you bid?
The agent sets up the bid and writes the first draft. Free for 14 days.
Award Criteria
Description
Laveste pris
Source
No source found in the documents. Check the weight against the tender documents.
From the notice
The work includes cable laying from Gilsbakki to the "Into the Glacier" tourism service at Hvítá, together with soil replacement for transformers. High-voltage cables are 3x25q 24kV about 12.8 km long, low-voltage cables about 360m, ground wire about 1,400m or about 14.6 km in total. 12 substations and 2 junctions boxes are expected in this project. It is assumed that the project will start on 1st July and end on 6th September 2024.
Contact
Úlfar Reyr Ingvarssonulfing@rarik.is- ResultType
- LandsbyggðLocation
- 45231400Main codeConstruction work for electricity power lines