Find

  • All tenders
All tenders: Ireland/Donegal County Council_1193/Arranmore/Árainn Mhór Slipway Repairs 2026 - Donegal County Council

Arranmore/Árainn Mhór Slipway Repairs 2026 - Donegal County Council

Expired

The competition has expired without a winner being announced.

Deadline
Aug 20,Expired
Procedure
OpenSingle stage
Agreement
Construction work
Estimated value
€1over 1 month

Brief

Donegal County Council needs works for breaking out of existing slipway, construction of new slipway toe and new slipway deck on Arranmore Island in a marine, coastal and tidal environment. The project has a maximum total value of 1 EUR and a duration of 1 month.

Asfalt og veioverflater

Register interest

Previous winners

  • Who are you up against?

    The suppliers who have won similar contracts at Donegal County Council_1193

Will you bid?

The agent sets up the bid and writes the first draft. Free for 14 days.

From the notice

  • Breaking out of existing slipway, construction of new slipway toe and new slipway deck. Works are on Arranmore Island in a marine, coastal and tidal environment.

  • Contact

    procurement@donegalcoco.ie
  • Type
    Competition
  • Location
    Northeim
  • Main code
    Pier construction work
    45241300
  • 45241000Harbour construction works45244000Marine construction works

Similar active competitions

  • Donegal County Council_1193

    Geotekniske undersøkelser

    Consultancy Services for Machaire Rabhartaigh Harbour Tidal Access Restriction Study

    Donegal County Council needs a suitably qualified environmental and marine engineering consultant for a 9-month study of tidal access restrictions on the approach to Machaire Rabhartaigh Harbour. The work will assess whether the restriction can be removed to create a channel with a depth of 3–4 metres below Chart Datum without adversely affecting coastal morphology. The project is located in the Border region of Ireland.

    Competition
    Dec 11, 2026(15 days)
    €0
  • Port of Cork Company

    Asfalt og veioverflater

    Re-development of Ringaskiddy Port at Ringaskiddy West

    Port of Cork Company needs construction services for the re-development of Ringaskiddy Port at Ringaskiddy West, which includes extending the deep-water berth, surfacing land, dredging the seabed to -13.4m Chart Datum, lighting, drainage, and other associated civil engineering and mechanical/electrical works. The project duration is 24 months.

    Qualification system
    Nov 27, 2026(1 day)
  • APDL - Administração dos Portos do Douro, Leixões e Viana do Castelo, SA

    Ferjekaier og maritime anlegg

    Empreitada de reconstrução do Cais da Ferradosa e estabilização dos taludes adjacentes

    A APDL – Administração dos Portos do Douro, Leixões e Viana do Castelo, SA, pretende contratar uma empreitada de reconstrução do Cais da Ferradosa e estabilização dos taludes adjacentes, na Área Metropolitana do Porto. O contrato de obras terá uma duração de 2 anos e um valor máximo total de 6,7 milhões de euros; os detalhes técnicos constam das peças do procedimento. A adjudicação será baseada no preço.

    Competition
    Dec 21, 2026(25 days)
    €6,700,000