Budowa drogi S16 Olsztyn (S51) – Ełk (S61) odcinek Olsztyn – Biskupiec (budowa drugiej jezdni) odcinek Barczewo - Biskupiec
Awarded
The competition has ended and a winner has been selected.
- Award
- Agreement
- over 39 months
Brief
Generalna Dyrekcja Dróg Krajowych i Autostrad zawarła umowę z PORR S.A. na budowę drugiej jezdni drogi S16 Olsztyn (S51) – Ełk (S61) na odcinku Barczewo - Biskupiec. Wartość kontraktu wynosi 456 919 411 PLN, a czas realizacji to 39 miesięcy.
Veibygging og asfaltarbeid
Result
- PORR S.A.Winner
- 0Number of tenders received
- PLN 456,919,411Contract value
Custom Assessment Criteria
Get answers to your bid/no-bid criteria
Set them up once and Cobrief answers them in every tender
Will you bid?
The agent sets up the bid and writes the first draft. Free for 14 days.
Award Criteria
Description
Waga kryterium wynosi 55%
Source
No source found in the documents. Check the weight against the tender documents.
Previous winners
Who are you up against?
The suppliers who have won similar contracts at Generalna Dyrekcja Dróg Krajowych i Autostrad Oddział w Olsztynie
From the notice
Przedmiotem zamówienia jest realizacja zadania pod nazwą „Budowa drogi S16 Olsztyn (S51) – Ełk (S61) odcinek Olsztyn – Biskupiec (budowa drugiej jezdni) odcinek Barczewo - Biskupiec”.
Contact
Al. Warszawska 89, 10-083 Olsztynakrawczyk@gddkia.gov.pl- ResultType
- 45233100Main codeConstruction work for highways, roads
- 45213310Construction work for buildings relating to road transport45221100Construction work for bridges45221120Viaduct construction work45233000Construction, foundation and surface works for highways, roads45233123Secondary road construction work45233125Road junction construction work45233130Construction work for highways71320000Engineering design services