CABLE PLOUGHING - STRENGLÖGN - Vatnshamrar að Ferjubakka - Vesturland
Expired
The competition has expired without a winner being announced.
- Deadline
- May 18Expired
- Procedure
- OpenSingle stage
- Agreement
- Construction workuntil Aug 2026
Brief
RARIK ohf. needs cable ploughing services for two sections, Vatnshamrar to Hvítá and Ferjubakki to Hvítá, in Vesturland, Iceland. The project involves installing 6 high-voltage cables (3 units of 1x300 mm², 36 kV and 3 units of 1x240 mm², 36 kV) in parallel over approximately 6.3 km, along with fiber optic ducts. The work is expected to commence on June 22 and be completed by August 17, 2026.
Groundwork and rental of construction machinery
Previous winners
Who are you up against?
The suppliers who have won similar contracts at RARIK ohf.
Will you bid?
The agent sets up the bid and writes the first draft. Free for 14 days.
From the notice
There are two work sections involved, namely cable laying from Vatnshamrar to Hvítá and from Ferjubakki to Hvítá. The cable installation is a pure transmission line, and therefore no ground-mounted substations are required along the route. The high-voltage cables consist of 3 units of 1x300 mm², 36 kV over approximately 6.3 km, and 3 units of 1x240 mm², 36 kV over approximately 6.3 km. In total, 6 cables are to be ploughed in parallel along a section of approximately 6.3 km. It is requested that fiber optic ducts be installed in parallel with the works on behalf of RARIK. It is assumed that the project will commence on June 22 and be completed by August 17, 2026.
Contact
ulfing@rarik.is- CompetitionType
- LandsbyggðLocation
- 45231400Main codeConstruction work for electricity power lines