Conception et réalisation d'une usine de production d'eau potable de 400 m³/h à Sarralbe
Awarded
The competition has ended and a winner has been selected.
- Qualification deadline
- Nov 5, 2025Expired
- Procedure
- With negotiationTwo stages
- Agreement
- Construction workover 54 months
Brief
Les travaux seront réalisés en trois phases : - phase 1 : construction de la nouvelle usine, des pompage d'eau brute dans la Sarre et d'eau traitée vers l'Europôle et le réservoir du Knopp, - phase 2 : déconstruction de l'usine existante, - phase 3 : construction du bassin de rétention d'eau brute de 6 000 m³
Anleggs- og infrastrukturbygging
Result
- SAURWinner
- 0Number of tenders received
- €14,497,835Contract value
Custom Assessment Criteria
Get answers to your bid/no-bid criteria
Set them up once and Cobrief answers them in every tender
Will you bid?
The agent sets up the bid and writes the first draft. Free for 14 days.
Previous winners
Who are you up against?
The suppliers who have won similar contracts at Communauté d'Agglomération Sarreguemines Confluences
From the notice
Les travaux seront réalisés en trois phases : - phase 1 : construction de la nouvelle usine, des pompage d'eau brute dans la Sarre et d'eau traitée vers l'Europôle et le réservoir du Knopp, - phase 2 : déconstruction de l'usine existante, - phase 3 : construction du bassin de rétention d'eau brute de 6 000 m³
Contact
ROTH Rolandcorrespondre@aws-france.com- Result · PrequalificationType
- 45252126Main codeDrinking-water treatment plant construction work
- 45111100Demolition work45232454Rain-water basin construction work45262660Asbestos-removal work