All tenders: Ireland/Electricity Supply Board/D20/CON/869

D20/CON/869

Awarded

The competition has ended and a winner has been selected.

Qualification deadline
May 9, 2024Expired
Award
Quality
Procedure
With negotiationTwo stages
Agreement
Framework agreement

Brief

Civil Works associated with live substations in the Republic of Ireland

Oppføring av bygninger

Result

TED
  • Circet Networks (Ireland) Limited
    Winner
  • Fox Building & Engineering Ltd
    Winner
  • Gaeltec Utilities Ltd
    Winner
  • Kilcawley Building & Civil Engineering Ltd. t/a Kilcawley Construction
    Winner
  • Mainline Power Ltd
    Winner
  • Number of tenders received
    0
  • Contract value
    €304,000,000

Previous winners

  • Who are you up against?

    The suppliers who have won similar contracts at Electricity Supply Board

Will you bid?

The agent sets up the bid and writes the first draft. Free for 14 days.

Award Criteria

  • Description

    Per tender documents

    Source

    No source found in the documents. Check the weight against the tender documents.

  • Description

    Per tender documents

    Source

    No source found in the documents. Check the weight against the tender documents.

From the notice

  • Civil Works associated with live substations in the Republic of Ireland

  • Contact

    firstname.surname@esb.ie
  • Type
    Result · Framework agreement · Prequalification
  • Main code
    Substation construction work
    45232220
  • 45200000Works for complete or part construction and civil engineering work

Similar active competitions

  • Electricity Supply Board ( ESB )

    Elektroinstallasjon i bygninger

    Works Associated with the Design and Build of High Voltage Electrical Substations in the Republic of Ireland

    Works Associated with the Design and Build of High Voltage Electrical Substations in the Republic of Ireland

    Qualification system
    May 30, 2027(100+ days)
  • Electricity Supply Board ( ESB )

    Qualification System for Construction of Greenfield Civil Works Projects in the Republic of Ireland

    Qualification System for Construction of Greenfield Civil Works Projects in the Republic of Ireland

    Qualification system
    May 31, 2027(100+ days)
  • Electricity Supply Board ( ESB )

    Elektrisitet og energiforvaltning

    Commissioning and Engineering-related Services Qualification System

    Commissioning and Engineering-related Services Qualification System

    Qualification system
    Jun 4, 2027(100+ days)