Empreitada de Construção da Central Fotovoltaica Flutuante da Estação Elevatória da Amoreira
Awarded
The competition has ended and a winner has been selected.
- Deadline
- Feb 20, 2025Expired
- Award
- Performance Ratio (PR) 20% and 3 more
Brief
Elaboração do Projeto de Execução, Construção, Instalação, Operação e Manutenção de uma UPAC na Estação Elevatória da Amoreira.
Result
- EDP COMERCIAL – COMERCIALIZAÇÃO DE ENERGIA, S.A.Winner
- GREENVOLT NEXT PORTUGAL, LDA.Winner
- 6Number of tenders received
- €9,318,681Contract value
Custom Assessment Criteria
Get answers to your bid/no-bid criteria
Set them up once and Cobrief answers them in every tender
Will you bid?
The agent sets up the bid and writes the first draft. Free for 14 days.
Award Criteria
Description
F4 - Valor do encargo total da empreitada
Source
No source found in the documents. Check the weight against the tender documents.
Description
F1 - Performance Ratio (PR) da solução proposta
Source
No source found in the documents. Check the weight against the tender documents.
Description
F3 - Garantias dos equipamentos adicionais ao prazo legalmente previsto
Source
No source found in the documents. Check the weight against the tender documents.
Description
F2 - Qualidade da solução proposta
Source
No source found in the documents. Check the weight against the tender documents.
Description
F5 - Utilização de materiais reutilizados ou reciclados incorporados
Source
No source found in the documents. Check the weight against the tender documents.
Previous winners
Who are you up against?
The suppliers who have won similar contracts at Edia - Empresa de Desenvolvimento e Infra-Estruturas do Alqueva, SA
From the notice
Elaboração do Projeto de Execução, Construção, Instalação, Operação e Manutenção de uma UPAC na Estação Elevatória da Amoreira.
Contact
edia@edia.pt- ResultType
- Baixo AlentejoLocation
- 45000000Main codeConstruction work
- 45251100Construction work for power plant