Search
  • Search


Belgium: Tenders/Elia Asset/FA Protection Automation & Control Cubicles SPACS 3 Bis - 2027
  1. Competition notice published

    May 23, 2024 8:00 PMMay 23, 2024 8:00 PM
  2. Questions deadline

    Jun 21, 2024 2:30 PMJune 21, 2024 2:30 PM
  3. Qualification deadline

    Not stated
  4. Tender submission deadline

    Jul 3, 2024 2:30 PMJuly 3, 2024 2:30 PM
  5. Contract start date

    Jan 1, 2027 12:00 AMJanuary 1, 2027 12:00 AM
  6. Contract end date

    Dec 31, 2030 12:00 AMDecember 31, 2030 12:00 AM

Brief

FA Protection Automation & Control Cubicles SPACS 3 Bis - 2027

Published deadline passed

The published deadline has passed. For multi-stage competitions a later tender deadline may still apply — check the notice or portal for the current phase.

Qualification deadline
Jul 3, 2024Expired
Procedure
With negotiationTwo stages
Agreement
Framework agreement
Estimated value
€240Muntil Dec 2030

Brief

The subject of this tender is the design, engineering, manufacturing, factory testing (FAT), packaging, transport, delivery, unloading, after sales servicing of full protection cubicles (SPACS 3 Bis) including all necessary accessories and spare parts as well as related services in substations + Maintenance contract

Elektrisk utstyr og belysning

Register interest

Custom Assessment Criteria

  • Get answers to your bid/no-bid criteria

    Set them up once and Cobrief answers them in every tender

Will you bid?

The agent sets up the bid and writes the first draft. Free for 14 days.

Award Criteria

  • Description

    Will be described in the tender documents

    Source

    No source found in the documents. Check the weight against the tender documents.

Previous winners

  • Who are you up against?

    The suppliers who have won similar contracts at Elia Asset

From the notice

  • The subject of this tender is the design, engineering, manufacturing, factory testing (FAT), packaging, transport, delivery, unloading, after sales servicing of full protection cubicles (SPACS 3 Bis) including all necessary accessories and spare parts as well as related services in substations + Maintenance contract

  • Contact

    jeanpierre.falkenback@elia.be
  • Type
    Competition · Framework agreement · Prequalification
  • Main code
    Electrical apparatus for switching or protecting electrical circuits
    31210000

Similar active competitions

  • Elia Asset

    Framework agreement - Busbar Protection (BBP) cubicles - 2029-2037

    Elia Asset needs a framework agreement for the design, engineering, manufacture, factory testing, packaging, transport, delivery and unloading of busbar protection (BBP) cubicles, including accessories, spare parts, after-sales service and related substation services, as well as a maintenance contract. The agreement covers delivery in Belgium and has an 8-year duration with a maximum total value of €18 million.

    Framework agreement with qualification
    Jan 14, 2027(56 days)
    €18,000,000
  • Elia Transmission Belgium

    Elektrisk infrastruktur og veibelysning

    Installation services of electrical equipment in HV substations

    Elia Transmission Belgium heeft behoefte aan installatiediensten voor elektrische apparatuur in hoogspanningsstations. Dit omvat de installatie en controle van elektrische apparatuur en accessoires voor laag-, midden- en hoogspanningsniveaus, zoals verlichtingswerk, controle van aansluitingen, aansluiting van hoogspanningsapparatuur, plaatsing van kasten, installatie van cubicles en het leggen van laag-, midden- en hoogspanningskabels, interconnecties, bays, schakelinstallaties en transformatorassemblage. De werken zijn onderverdeeld in subcategorieën op basis van het spanningsniveau: MS/36, 70, 110, 150, 220 en 380.

    Qualification system
    Apr 14, 2029(100+ days)
  • Elia Transmission Belgium

    Onshore Substations in EPCIC-FIM model

    In accordance with the latest Capex Plan, and the on-going energy transition, Elia intends to outsource multiple investment projects for onshore substations in Belgium that were previously realized in-house. The aim is to construct some substations in a EPCIC-FIM model. Meaning that the engineering, procurement (without noble materials/FIM), construction, installation and commissioning will be (partly) tendered in one contract. Only candidates that qualify in the prequalification phase of this EU procurement (see section 5.1.6) of this Qualification System will have access the tender phases.

    Qualification system
    Jun 11, 2027(100+ days)