Brief
Limerick City and County Council has entered into an agreement with John Sisk and Son (Holdings) Ltd and Sorensen Civil Engineering Ltd (together the Sisk Sorensen Joint Venture) for the construction of the Foynes to Limerick Road (including Adare Bypass) – Adare to Attyflin Construction Contract. This contract, valued at 35,470,266 €, involves approximately 3.5km of new M21 motorway from Adare to Attyflin, including 1.5km of offline works and 2km of online works along the existing N21, as well as 0.5 km of pavement inlay works, associated road realignments, site clearance, demolition, structures like VMS signage gantries, noise barriers, mammal underpasses, culverts, and highway drainage. The project, located in Ireland, has a duration of 12 months and is required to be fully operational by June 2027.
Vei- og gatearbeid
Result
- John Sisk and Son (Holdings) LtdWinner
- 0Number of tenders received
- €35,470,266Contract value
Previous winners
Who are you up against?
The suppliers who have won similar contracts at Limerick City and County Council_103432
Will you bid?
The agent sets up the bid and writes the first draft. Free for 14 days.
Award Criteria
Description
Quality @ 60%
Source
No source found in the documents. Check the weight against the tender documents.
From the notice
Limerick City and County Council in partnership with Transport Infrastructure Ireland (TII) is seeking tenders for the Foynes to Limerick Road (including Adare Bypass) - Adare to Attyflin Construction Contract, which will be procured under the NEC4 Option C form of Contract. The Adare to Attyflin Construction Contract includes but is not limited to: - approximately 3.5km of new M21 motorway from Adare to Attyflin which will involve approximately 1.5km of offline works and approximately 2km of online works along the existing N21. The works also include approximately 0.5 km of pavement inlay works towards the tie-in at the Attyflin junction, associated connections to and realignment of existing National, and Local roads, site clearance, including demolition of existing structures/non-structures, structures/non-structures include 2 no. VMS signage gantries; noise barriers and various accommodation works, mammal underpasses, culverts and modification of existing structures/non-structures, Highway drainage and associated attenuation ponds. The Adare to Attyflin section of the Project, is required to be fully operational by June 2027, in advance of the 2027 Ryder Cup. The above paragraphs are a summary only and Tenderers are directed to read and formulate their Tenders based on all of the provisions of the Contract as detailed in the Scope and other Tender Documents that can be found in the Virtual Data Room (VDR).
Contact
procurement@midwestroads.ie- ResultType
- Mid-WestLocation
- 45233120Main codeRoad construction works
- 45200000Works for complete or part construction and civil engineering work45221111Road bridge construction work45221220Culverts45233110Motorway construction works45233121Main road construction works45233124Trunk road construction work45233125Road junction construction work45233126Grade-separated junction construction work45233130Construction work for highways