Framework Agreement on Geotechnical Seabed Surveys for Export Cables
Published deadline passed
The published deadline has passed. For multi-stage competitions a later tender deadline may still apply — check the notice or portal for the current phase.
- Qualification deadline
- Dec 15, 2025Expired
- Procedure
- With negotiationTwo stages
Brief
50Hertz and Elia tender a framework agreement on geotechnical investigations for export cable routes. 50Hertz, as part of the Elia Group, foresees the construction of several offshore high-voltage DC and AC stations (HVDC and HVAC), including the installation of the export cables in the North Sea and Baltic Sea. For this purpose, geotechnical investigations for the export cable route shall be performed to acquire all necessary information for the conceptual and detailed design phases. The geotechnical specifications will be used in several projects (e.g. LanWin6, as well as other OWF (offshore wind farm) clusters in the North Sea and future OWF areas in the Baltic Sea in addition to the existing windfarm areas). Quantities given in the tender documents are for the purpose of comparison and calculation. They do not constitue a guarantee.
Miljøovervåking og naturvitenskapelige tjenester
Previous winners
Who are you up against?
The suppliers who have won similar contracts at 50Hertz Transmission GmbH
Will you bid?
The agent sets up the bid and writes the first draft. Free for 14 days.
Qualification requirements
Description
Self-declaration of the applicant that there are no exclusion reasons according to §§ 123, 124 GWB applying to the applicant. The GWB, or "Gesetz gegen Wettbewerbsbeschränkungen", is the German Act Against Restraints of Competition. This law regulates anti-competitive behaviour and is designed to ensure fair competition within the market. It includes sections (such as §§ 123, 124) that provide grounds for exclusion.
Documentation Requirement
This criterion is met if you confirm to us with the selection "Yes" that there are no exclusion reasons according to §§ 123, 124 GWB applying.
Source
No source found in the documents. Check the requirement against the tender documents.
Description
The applicant provides References of geotechnical surveys (as described in section II.2.4 of the Contract notice) during the last 5 years: Three (3) references for offshore geotechnical site investigations including drilling, continuous sampling and CPT up to minimum 5 mbsf (meters below sea floor). Note: Same project can be used as reference for a) and b), if applicable. References can be from surveys in North and Baltic Sea.
Documentation Requirement
Please upload the file with the requested references here. The use of the "Template References" is mandatory. The Employer needs to be able to validate the references.
Source
No source found in the documents. Check the requirement against the tender documents.
Description
The applicant provides References of geotechnical surveys (as described in section II.2.4 of the Contract notice) during the last 5 years: Two (2) references of experience with advanced laboratory tests (like direct simple shear testing, triaxial testing). Note: Same project can be used as reference for a) and b), if applicable. References can be from surveys in North and Baltic Sea.
Documentation Requirement
Please upload the file with the requested references here. The use of the "Template References" is mandatory. The Employer needs to be able to validate the references.
Source
No source found in the documents. Check the requirement against the tender documents.
Description
The applicant provides information on (potential) subcontracting: - List the activities that applicant intends to subcontract and their estimated percentage of the global activity - List of intended subcontractors for each activity and statement for how long the business relationship has already existed.
Documentation Requirement
If there is no subcontracting or similar, please upload a document stating this.
Source
No source found in the documents. Check the requirement against the tender documents.
Description
Does the applicant have a recognized quality management certification?
Documentation Requirement
If YES, what type of certification and what is the date of validity? Provide a copy of the certificate. Please provide details if the certification is in progress. If NO, please provide detailed information on how Quality Management is managed in the company. If available, please provide the Quality Management Handbook or Project Management Handbook.
Source
No source found in the documents. Check the requirement against the tender documents.
From the notice
50Hertz and Elia tender a framework agreement on geotechnical investigations for export cable routes. 50Hertz, as part of the Elia Group, foresees the construction of several offshore high-voltage DC and AC stations (HVDC and HVAC), including the installation of the export cables in the North Sea and Baltic Sea. For this purpose, geotechnical investigations for the export cable route shall be performed to acquire all necessary information for the conceptual and detailed design phases. The geotechnical specifications will be used in several projects (e.g. LanWin6, as well as other OWF (offshore wind farm) clusters in the North Sea and future OWF areas in the Baltic Sea in addition to the existing windfarm areas). Quantities given in the tender documents are for the purpose of comparison and calculation. They do not constitue a guarantee.Main features of the procedureThe tender documents are available with unrestricted, complete and direct access free of charge here: https://eliagroup.sharepoint.com/:f:/s/EFSS/EFSS/Ev1kwknYX-tMsjQsEkh7EHQBRhV38sNY1f36Qh4rlyMXvg?e=EteRNg Further information can be obtained from the above-mentioned contact point.
Contact
Vincent Sigwarth, GPS-Svincent.sigwarth@50hertz.com- Competition · Framework agreement · PrequalificationType
- BerlinLocation
- 71332000Main codeGeotechnical engineering services