GGLF (Green Gas Lolland Falster) – 3 HDD’s
Awarded
The competition has ended and a winner has been selected.
- Qualification deadline
- Jan 11, 2023Expired
- Procedure
- With negotiationTwo stages
- Agreement
- Construction work
Brief
Three (3) HDD installation for the project GGLF (Green Gas Lolland Falster). The three crossings are world-class as they are long and deep, and working under strict environmental conditions. The Scope of Works will be considered to cover all phases of work from design maturation to installation, testing and pre-commissioning.
Veg- og baneinfrastruktur
Result
- Horizontal Drilling International S.A.S.Winner
- MT Højgaard Danmark A/SWinner
- SpiecapagWinner
- 0Number of bids
- €24,111,760Contract value
Custom Assessment Criteria
Get answers to your bid/no-bid criteria
Set them up once and Cobrief answers them in every tender
Will you bid?
The agent sets up the bid and writes the first draft. Free for 14 days.
Previous winners
Who are you up against?
The suppliers who have won similar contracts at Energinet Gastransmission A/S
From the notice
Three (3) HDD installation for the project GGLF (Green Gas Lolland Falster). The three crossings are world-class as they are long and deep, and working under strict environmental conditions. The Scope of Works will be considered to cover all phases of work from design maturation to installation, testing and pre-commissioning.
Contact
Procurement - Rindkob@energinet.dk- Result · PrequalificationType
- 45230000Main codeConstruction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork
- 44161100Gas pipelines45231200Construction work for oil and gas pipelines45231220Construction work for gas pipelines45262422Subsea drilling work