Brief
FAIR - Facility for Antiproton and Ion Research in Europe GmbH har inngått en avtale med PREVAC sp. z o.o. om å levere en HEBT charge stripper, et apparat designet for å strippe elektroner fra stråleioner for å produsere ionestråler med definerte ladningstilstander for FAIR. Leveransen skal skje i Darmstadt, Tyskland, over en periode på 20 måneder, til en verdi av 136 469 €. Apparatet må oppfylle spesielle krav for bruk i UHV-systemer, og aktuatoren styres av en dedikert kontroller i et elektronikkstativ som gir grensesnitt til FAIR-kontrollsystemet. Det ble lagt vekt på pris (30%), samt kvaliteten på tilbudet, design- og produksjonskonseptet, kvalitetssikringskonseptet og tidsplanen/leveringsplanen (hver med 21%, 21%, 21% og 7% vekt).
Anleggsmaskiner og utstyr
Result
- PREVAC sp. z o.o.Winner
- 2Number of tenders received
- €136,469Contract value
Previous winners
Who are you up against?
The suppliers who have won similar contracts at FAIR - Facility for Antiproton and Ion Research in Europe GmbH
Will you bid?
The agent sets up the bid and writes the first draft. Free for 14 days.
Award Criteria
Description
Consideration of the price through the valuation method "Preis-Quotient-Methode"
Source
No source found in the documents. Check the weight against the tender documents.
Description
A clear and comprehensive presentation of the offer is evaluated positively. The bidder should show how the requirements of the specification and the technical guidelines can be achieved and list the system components and interfaces required for this. A high level of detail in the submitted cost breakdown is also evaluated positively. 9-10 points: Very good: particularly outstanding fulfillment of the performance criteria 7-8 points: Good: performance criteria fulfillment significantly above average requirements despite minor deficiencies 5-6 points: Satisfactory: performance criteria fulfillment that still meets average requirements despite minor to moderate deficiencies 3-4 points: Sufficient: fulfillment of the criteria suffering from significant deficiencies, which on the whole is only just usable 0-2 points: Poor to unsatisfactory: completely unusable fulfillment of the required criteria
Source
No source found in the documents. Check the weight against the tender documents.
Description
As part of the tender, the general production concept should be set out in a clear description of all production steps. It should be made clear which work steps will be carried out directly by the bidder and which will be carried out by external service providers or subcontractors. An overview of the machines, tools and semi-finished products relevant to the planned production that are available in the bidder's machine park is requested. If concepts for manufacturing processes and integration of the components already exist, these can be presented as part of the bid. It will also be evaluated positively if the concept shows how the bidder ensures the longevity, reliability and ease of maintenance of the product and if sustainability aspects are considered and documented. Finally, a positive evaluation is given if reliable processes for material selection and procurement are presented. 9-10 points: Very good: particularly outstanding fulfillment of the performance criteria 7-8 points: Good: performance criteria fulfillment significantly above average requirements despite minor deficiencies 5-6 points: Satisfactory: performance criteria fulfillment that still meets average requirements despite minor to moderate deficiencies 3-4 points: Sufficient: fulfillment of the criteria suffering from significant deficiencies, which on the whole is only just usable 0-2 points: Poor to unsatisfactory: completely unusable fulfillment of the required criteria
Source
No source found in the documents. Check the weight against the tender documents.
Description
As part of the offer, it should be explained which measuring equipment and procedures, tools and semi-finished products can be used to verify and ensure the specified technical requirements. The approach of the acceptance tests, the layout of the production facility and the QA documentation must be explained. It must also be explained how the bidder intends to prepare the documentation of the development and manufacturing process. The software used for tracking the project, production and CAD design in relation to the fulfillment of the specified requirements should be mentioned. It is considered positive if the required measuring and auxiliary equipment (e.g. necessary vacuum components) as well as the planned measuring procedures are listed in detail. 9-10 points: Very good: particularly outstanding fulfillment of the performance criteria 7-8 points: Good: performance criteria fulfillment significantly above average requirements despite minor deficiencies 5-6 points: Satisfactory: performance criteria fulfillment that still meets average requirements despite minor to moderate deficiencies 3-4 points: Sufficient: fulfillment of the criteria suffering from significant deficiencies, which on the whole is only just usable 0-2 points: Poor to unsatisfactory: completely unusable fulfillment of the required criteria
Source
No source found in the documents. Check the weight against the tender documents.
Description
As part of the offer, a reliable presentation of the chronological sequence of the project milestones should be presented. A comprehensible presentation that realistically depicts the time periods required for planning, material procurement, production and acceptance testing will be evaluated positively. 9-10 points: Very good: particularly outstanding fulfillment of the performance criteria 7-8 points: Good: performance criteria fulfillment significantly above average requirements despite minor deficiencies 5-6 points: Satisfactory: performance criteria fulfillment that still meets average requirements despite minor to moderate deficiencies 3-4 points: Sufficient: fulfillment of the criteria suffering from significant deficiencies, which on the whole is only just usable 0-2 points: Poor to unsatisfactory: completely unusable fulfillment of the required criteria
Source
No source found in the documents. Check the weight against the tender documents.
From the notice
The HEBT charge stripper, that is to be procured with this tender, is a device designed to strip electrons from beam ions in order to produce ion beams with defined charge states for FAIR. This device will be positioned behind the heavy ion synchrotron SIS18, in the first beamline arc towards the FAIR facility. It consists of several fast and slow actuators to move thin foils in and outside of the ionbeam path, as well as a dedicated controller rack. As part of the beam vacuum system of FAIR, the charge stripper must meet various special requirements in terms of applicability in UHV systems. The actuators are controlled by a dedicated controller in an electronics rack, which is placed further away from the beamline due to radiation issues. The rack provides the interface to the FAIR control system in order to enable the movement in synchronization with the accelerator machine cycle and to monitor the required interlock logic.
Contact
proekf35@gsi.de- Result · PrequalificationType
- Darmstadt, Kreisfreie StadtLocation
- 42990000Main codeMiscellaneous special-purpose machinery
- 31643000Particle accelerators