    Implementation of Battery Energy Storage System at Čierny Váh

    Slovenské elektrárne, a.s.

    Implementation of Battery Energy Storage System at Čierny Váh

    1. Competition notice published

      Oct 26, 6:16 AMOctober 26, 2026 6:16 AM
    2. Qualification deadline

      Nov 26, 9:00 AMNovember 26, 2026 9:00 AM
    3. Tender submission deadline

      Comes with the invitation

    Brief

    Slovakia: Tenders/Slovenské elektrárne, a.s./Implementation of Battery Energy Storage System at Čierny Váh
    Qualification deadline
    Nov 26,28 days left
    Award
    Price only
    Procedure
    With negotiationTwo stages
    Agreement
    Buying goodsover 1,234 days

    Brief

    Slovenské elektrárne, a.s. seeks an EPC contractor to design, permit, supply, install, commission and put into operation a battery energy storage system at Čierny Váh in the Žilinský Region, over approximately 1,234 days. The BESS must provide at least 480 MWh of usable capacity and 120 MW of rated power, connect to the 400 kV substation through a new 400 kV bay, and support frequency reserves, electricity-market services, frequency-response functions and island operation to maintain the pumped-storage plant’s auxiliary supply during loss of its 22 kV connection. The scope includes civil, electrical and mechanical works; battery containers, conversion and control systems, transformers, switchgear and related equipment; integration with existing plant systems; protection, monitoring, communications, fire safety and security; and testing, performance verification, operational training and documentation needed for safe, reliable operation. The contract will be awarded solely on the lowest total price excluding VAT.

    Batterisystemer og energilagring

    Register interest

    Custom Assessment Criteria

    • Get answers to your bid/no-bid criteria

      Set them up once and Cobrief answers them in every tender

    Will you bid?

    The agent sets up the bid and writes the first draft. Free for 14 days.

    Award Criteria

    • Description

      The lowest total price without VAT.

      Source

      No source found in the documents. Check the weight against the tender documents.

    Previous winners

    • Who are you up against?

      The suppliers who have won similar contracts at Slovenské elektrárne, a.s.

    From the notice

    • The subject matter of the tender comprises EPC performance of all supplies and services related to design and engineering, permitting and other engineering activities, transportation, installation, commissioning and putting into operation of the newly installed equipment. The principal scope of supply is the construction and commissioning of a Battery Energy Storage System (BESS) providing the following functions and services: • Frequency Containment Reserve (FCR); • automatic Frequency Restoration Reserve (aFRR); • market services, including Day-Ahead and Intraday market participation, energy arbitrage and imbalance management; • Limited Frequency Sensitive Mode – Overfrequency (LFSM-O) and Underfrequency (LFSM-U), providing active power response in the event of an increase or decrease in grid frequency; and • island operation to ensure the auxiliary power supply of the pumped-storage hydropower plant in the event of a loss of the 22 kV power supply. The BESS shall have a total usable energy capacity of at least 480 MWh and a rated power of at least 120 MW and shall be connected to the 400 kV substation via a newly constructed 400 kV bay. The scope of works includes all engineering and permitting activities, preparation of design documentation, civil, electrical and mechanical works, delivery and installation of battery containers, power conversion systems, energy management systems, transformers, switchgear and associated equipment. The contractor shall also ensure integration with existing plant systems, implementation of control, protection, monitoring and communication systems, fire protection and security systems, testing, commissioning, performance verification and training of operating personnel. The tenderer shall provide all documentation, certifications, inspections and services necessary to ensure safe, reliable and long-term operation of the BESS installation.

    • Contact

      zuzana.kosecova@seas.sk
    • Type
      Competition · Prequalification
    • Location
      Žilinský kraj
    • Main code
      Batteries
      31440000
    • 03111200Peanuts31214000Switchgear31321000Electricity power lines31321210Low-voltage cable31321300High-voltage cable45000000Construction work45255400Fabrication work71300000Engineering services71632000Technical testing services80531200Technical training services

    Similar active competitions

    • VODÁRENSKÁ AKCIOVÁ SPOLEČNOST, a.s.

      Elektrisitet og energiforvaltning

      FVE VAS, ÚV Znojmo a ČOV Dobšice

      VODÁRENSKÁ AKCIOVÁ SPOLEČNOST, a.s. potřebuje do 30 týdnů vybudovat fotovoltaické elektrárny s bateriovými úložišti v areálu úpravny vody Znojmo a čistírny odpadních vod Znojmo v Jihomoravském kraji; maximální celková hodnota zakázky činí 25 milionů Kč. Dodávka zahrnuje pořízení, výstavbu a instalaci elektráren o povoleném výkonu 332,64 kW a 294,26 kW a úložišť o kapacitě 1 200 kWh/360 kW a 2 400 kWh/360 kW. Elektrárny budou sloužit pro vlastní spotřebu a nabíjení baterií, přebytky se budou dodávat do distribuční sítě. Zakázka je financována z projektu EU; nabídky budou hodnoceny výhradně podle nejnižší ceny bez DPH (100 %).

      Competition
      Dec 10, 2026(42 days)
      CZK 25,000,000
    • HOLDING SLOVENSKE ELEKTRARNE d.o.o.

      Rådgivende ingeniørtjenester for bygg og anlegg

      Izgradnja sončne elektrarne Zagorje ob Savi z baterijskim hranilnikom električne energije

      HOLDING SLOVENSKE ELEKTRARNE d.o.o. potrebuje projektiranje, dobavo, montažo, testiranje in zagon sončne elektrarne Zagorje ob Savi z inštalirano močjo 1,38 MWp ter pripadajočega baterijskega hranilnika električne energije (BHEE) moči 1,25 MW in kapacitete 5 MWh, z vso potrebno opremo za delovanje in vodenje ter povezavo v nadzorni center HSE. Naročilo bo izvedeno na območju zaprtega odlagališča komunalnih odpadkov Kamnolom Zagorje v občini Zagorje ob Savi, v trajanju 10 mesecev. Naročilo se izvede po načelu »ključ v roke«, po pogodbenih pogojih FIDIC Rumene knjige, izdaja 1999. Ponudbe se bodo ocenjevale izključno na podlagi cene (100 %). Za oddajo ponudbe sta obvezna dvig zaprtega dela dokumentacije in ogled lokacije.

      Competition
      Nov 19, 2026(21 days)
    • Slovenské elektrárne, a.s.

      Rådgivende ingeniørtjenester for bygg og anlegg

      Inžiniersko – projekčná činnosť v oblasti elektro a SKR, strojných technologických zariadení a stavebných objektov jadrových elektrární EBO a EMO“

      Slovenské elektrárne, a.s. potrebujú inžinierske služby v oblasti elektro, SKR, strojných technologických zariadení a stavebných objektov jadrových elektrární EBO a EMO na obdobie 36 mesiacov, s maximálnou celkovou hodnotou 3 570 000 EUR. Predmetom obstarávania je priebežné spracovávanie typových a realizačných projektových dokumentácií pre zmeny projektu, ekvivalentné zámeny komponentov technologického zariadenia strojnej časti projektu JE a drobné projekty stavebných úprav projektu jadrových elektrární EBO a EMO12, ako aj ekvivalentné zámeny komponentov elektro a SKR technologického zariadenia jadrových elektrární EBO34 a EMO123. Služby sa majú dodávať v Nitrianskom a Trnavskom kraji. AFRY CZ s.r.o. má dnes podobnú zmluvu. Ponuky budú hodnotené výlučne na základe ceny (100 %).

      Dynamic purchasing system
      Feb 28, 2028(100+ days)
      €3,570,000