France: Tenders/LIMOGES METROPOLE - Communauté urbaine/MISSION DE MAITRISE D'OEUVRE RELATIVE A LA REHABILITATION DU RESERVOIR 10 000 N°2 (ET DU RESERVOIR 10 000 N°1) – STATION DE PRODUCTION D’EAU POTABLE DE LA BASTIDE - PHASE CANDIDATURE
  1. Competition notice published

    Jul 6, 2:16 PMJuly 6, 2026 2:16 PM
  2. Change in competition

    Jul 17, 8:17 AMJuly 17, 2026 8:17 AM
  3. Qualification deadline

    Sep 25, 10:00 AMSeptember 25, 2026 10:00 AM
  4. Tender submission deadline

    Comes with the invitation

Brief

MISSION DE MAITRISE D'OEUVRE RELATIVE A LA REHABILITATION DU RESERVOIR 10 000 N°2 (ET DU RESERVOIR 10 000 N°1) – STATION DE PRODUCTION D’EAU POTABLE DE LA BASTIDE - PHASE CANDIDATURE

Published deadline passed

The published deadline has passed. For multi-stage competitions a later tender deadline may still apply — check the notice or portal for the current phase.

Qualification deadline
Sep 25,Expired
Procedure
With negotiationTwo stages
Agreement
Buying servicesover 46 months

Brief

LIMOGES METROPOLE - Communauté urbaine a besoin de services de maîtrise d'œuvre pour la réhabilitation des réservoirs 10 000 n°1 et n°2 de la station de production d'eau potable de La Bastide, pour une durée de 46 mois. Le marché vise à désigner un maître d'œuvre pour piloter les études et les travaux de réhabilitation durable des réservoirs afin de réduire leur vulnérabilité.

Rådgivende ingeniørtjenester for bygg og anlegg

Register interest

Custom Assessment Criteria

  • Get answers to your bid/no-bid criteria

    Set them up once and Cobrief answers them in every tender

Will you bid?

The agent sets up the bid and writes the first draft. Free for 14 days.

Previous winners

  • Who are you up against?

    The suppliers who have won similar contracts at LIMOGES METROPOLE - Communauté urbaine

From the notice

  • Des travaux de de réhabilitation sont nécessaires sur les deux ouvrages de stockage d’eau potable de 10 000 m3 de la station de production d’eau de La Bastide. Le présent marché permettra de désigner un maitre d’œuvre qui assurera le pilotage des études et des travaux pour la réhabilitation pérenne des réservoirs afin de réduire leur vulnérabilité.

  • Contact

    Services des achats et des marchés publicsflorence.simonnet@limoges-metropole.fr
  • Type
    Competition · Prequalification
  • Location
    Haute-Vienne
  • Main code
    Feasibility study, advisory service, analysis
    71241000
  • 71300000Engineering services71311000Civil engineering consultancy services71313000Environmental engineering consultancy services

Similar active competitions

  • LIMOGES METROPOLE - Communauté urbaine

    Rådgivende ingeniørtjenester for bygg og anlegg

    MISSION DE MAITRISE D'OEUVRE RELATIVE A LA REHABILITATION DU RESERVOIR 10 000 N°2 (ET DU RESERVOIR 10 000 N°1) – STATION DE PRODUCTION D’EAU POTABLE DE LA BASTIDE - PHASE CANDIDATURES - Relance du marché 2026-F102

    Limoges Métropole recherche une maîtrise d’œuvre pour piloter les études et les travaux de réhabilitation durable des deux réservoirs d’eau potable de 10 000 m³ de la station de production de La Bastide, afin de réduire leur vulnérabilité. Le marché de services se déroulera sur 60 mois en Haute-Vienne.

    Competition with qualification
    Dec 2, 2026(25 days)
  • CLERMONT AUVERGNE METROPOLE

    Bygg og anlegg - Grunnarbeid, vann og kloakk

    TRAVAUX DE CONSTRUCTION DU BASSIN DE STOCKAGE-RESTITUTION D’HERBET, DE SES OUVRAGES ET RÉSEAUX ASSOCIÉS

    CLERMONT AUVERGNE METROPOLE a besoin de travaux de construction pour le bassin de stockage-restitution d'Herbet, ses ouvrages et réseaux associés, pour une durée de 75 mois. Ces travaux d'ingénierie hydraulique seront réalisés dans le Puy-de-Dôme.

    Competition with qualification
    Nov 6, 2026(0 days)
  • Communauté d'agglomération Grand Saint-Dizier Der et Vallées

    Arkitekttjenester

    Etude technico-économique du traitement, au stockage et à la distribution de l’eau potable de la commune de Montier-en-Der (La Porte du Der) et Maîtrise d’Œuvre-.

    La Communauté d'agglomération Grand Saint-Dizier Der et Vallées a besoin de services d'architecture et services connexes pour une étude technico-économique du traitement, du stockage et de la distribution de l'eau potable de la commune de Montier-en-Der (La Porte du Der) et de Maîtrise d'Œuvre, pour une durée de 84 mois. Les services comprennent une étude technico-économique et la maîtrise d'œuvre. Les candidats doivent fournir tout document justifiant de leur capacité économique et financière ainsi que de leurs capacités techniques et professionnelles.

    Competition
    Nov 18, 2026(11 days)