Modification notice to CFT 3109037 Award of Contract for Waste Removal and Wall construction to Breffni Building and Civil Engineering Ltd
Awarded
The competition has ended and a winner has been selected.
Anleggs- og infrastrukturbygging
Dublin City Council has entered into an agreement with Breffni Group Ltd. for the clearance and removal of approximately 40,000 tonnes of illegally dumped waste material and the construction of boundary treatments, including a 117m new 2.5m high precast boundary wall and footpath between Darndale Park and the Northern Sites in Dublin. The works also involve site clearance, removal of various waste materials (including potential hazardous waste, asbestos, end-of-life vehicles, and electrical goods), treatment of invasive species, construction of a new footpath, environmental monitoring, and temporary works such as a construction stage haul road. The final contract value is 12,708,064 EUR.
Result
- Winner
- Breffni Group Ltd.
- Number of bids
- 1
- Contract value
- €12,708,064
About the bid
- Contact phone
- 01 2222222
- Contact email
- procurementunit@dublincity.ie
- Address
- Civic Offices, Wood Quay, D08 RF3F Dublin
This Contract Award Notice is acting as a Modification Notice under Article 72 of 2014/24/EU to CFT 3109037 Contract for Darndale Park Waste Removal and Wall Construction to Breffni Building and Civil Engineering. Description of the procurement at the time of conclusion of the contract: The Contract comprises clearance and removal of approximately 40,000 tonnes of illegally dumped waste material and construction of boundary treatments and 117m of new 2.5m high precast boundary wall and footpath between Darndale Park and a group of Traveller Accommodation site known as the Northern Sites on the north side of Dublin within the boundaries of Darndale and Priorswood. The works shall include site clearance, removal of all waste material (investigations suggest non-hazardous), removal of asbestos, removal of end-of-life vehicles and other electrical goods, treatment and removal of invasive species, construction of concrete boundary walls, construction of new footpath, environmental monitoring. There is a requirement for removal of hazardous waste should it be encountered. Temporary works shall include construction of a construction stage haul road through Darndale Park to provide site access and all associated reinstatement works, protection to all existing services, fencing of works areas etc. Design of temporary works shall form part of the works. Changes arose in the following areas which were instructed in accordance with the provisions of the Public Works Contract - Removal and disposal of additional waste - Removal and disposal of horse carcass, contaminated waste, oil - Removal and disposal of large amount of historic concealed waste - Filling of excavated area with Article 27 backfill - Continued delays due to local obstruction of drainage construction - Construction of a new watermain that burst during excavation for drainage - Extensions of time under contract
Custom Assessment Criteria
Start a free trial to ask your own questions about the tender and get AI-generated answers.
Award Criteria
Description
This Contract Award Notice is acting as a modification notice under Article 72 of 2014/24/EU to this competition. The contract was awarded on the basis of the most economically advantageous tender. Contract award notice concerning this contract: Notice number in the OJ S: 2025/S 89-295381.
Qualification requirements
Found no qualification requirements in the contract notice.
Previous Contract Winners
Start a free trial to see who has won similar tenders for this buyer.
See the full notice
- Contracting authority
- Dublin City Council
- Title
- Modification notice to CFT 3109037 Award of Contract for Waste Removal and Wall construction to Breffni Building and Civil Engineering Ltd
- Type
- Main code
- Supplemental codes
- Location
- Dublin
- Estimated value
- €12,708,064.00