Italy: Tenders/OSSERVATORIO ASTRONOMICO DI CAPODIMONTE/MORFEO Main support structure
  1. Planning notice published

    Dec 12, 2025 1:33 PMDecember 12, 2025 1:33 PM
  2. Planned competition start

    Jan 31, 12:00 AMJanuary 31, 2026 12:00 AM

Brief

MORFEO Main support structure

Planned

The competition has not been announced yet.

Deadline
Jan 31,Expired
Agreement
Buying goods

Brief

1. ELT (Extremely Large Telescope) is the world’s largest telescope (39m diameter) under construction by ESO (https://elt.eso.org/) at Cerro Armazones in Chile. ELT is considered worldwide to be one of the highest priorities in ground based astronomy. MORFEO (http://wwwmaory.oabo.inaf.it/), as a first generation ELT instrument, will help compensate for the distortion of light caused by turbulence in the Earth’s atmosphere. MORFEO is a Multi-Conjugate Adaptive Optics (MCAO) module that will allow spatially uniform adaptive optics compensation over a large field of view (about 1 arcmin2) with high sky coverage. Wavefront sensing is performed by six Laser Guide Stars (LGS) and three Natural Guide Stars (NGS), for the measurement of high and low-order wavefront perturbations respectively. Finally, the wavefront error compensation is performed by two adaptive post focal Deformable Mirrors (DMs) located inside MORFEO (the core of the instrument), which work together with the telescope’s adaptive and tip-tilt mirrors M4 and M5 respectively. The overall optical path will consist of several 1m class optical elements: 6 flat folding mirrors, one corrective plate, two aspherical mirrors, a large dichroic filter, a refractive objective and 2 deformable mirrors (DMs). All the optical elements are hosted by the Main Support structure (see following definition) except the last one (M12M) that bends the light into the client instrument (called MICADO), which is supported by MICADO. MORFEO is being designed and built by a consortium of partners in Italy, France, Ireland, Canada and Japan together with ESO. INAF, as the leading institute, is responsible for all the major procurements. 2. The project has completed the Preliminary Design Phase and is in the Final Design Phase. The final design and the manufacturing of some components will be assigned to external companies. In particular, the MORFEO Consortium would like to inform all the industries concerned that a number of international public calls for tender are in publication and selection phase concerning the final design. In particular, this preliminary information note describes general requirements and conditions for the final design and the manufacturing of the Main Structure and handling tools for MORFEO. 3.The call for tender for Main Structure (MS) and AIV tools will be placed in the framework of the general technical specifications available at the link http://wwwmorfeo.oabo.inaf.it/index.php/info_mainstruct/ A Statement of Work including a detailed description of all procurement conditions and technical specifications (and applicable documents) will be published with the public call for tender. The actual design, E-MAO-000-00-00-00-00-INA-MOD-001_02 MAORY System Model, is provided as a reference and can be downloaded at the following link (http://wwwmorfeo.oabo.inaf.it/index.php/mainstruct_model/). The manufacturer is free to propose their own Main Structure Subsystem design, which may be completely different from the consortium one, a variation of it, or the consortium design itself. In any case, the manufacturer shall ensure performance of the system and the design itself shall be discussed with, and accepted by, the consortium

Custom Assessment Criteria

  • Get answers to your bid/no-bid criteria

    Set them up once and Cobrief answers them in every tender

Will you bid?

The agent sets up the bid and writes the first draft. Free for 14 days.

Previous winners

  • Who are you up against?

    The suppliers who have won similar contracts at OSSERVATORIO ASTRONOMICO DI CAPODIMONTE

From the notice

  • 1. ELT (Extremely Large Telescope) is the world’s largest telescope (39m diameter) under construction by ESO (https://elt.eso.org/) at Cerro Armazones in Chile. ELT is considered worldwide to be one of the highest priorities in ground based astronomy. MORFEO (http://wwwmaory.oabo.inaf.it/), as a first generation ELT instrument, will help compensate for the distortion of light caused by turbulence in the Earth’s atmosphere. MORFEO is a Multi-Conjugate Adaptive Optics (MCAO) module that will allow spatially uniform adaptive optics compensation over a large field of view (about 1 arcmin2) with high sky coverage. Wavefront sensing is performed by six Laser Guide Stars (LGS) and three Natural Guide Stars (NGS), for the measurement of high and low-order wavefront perturbations respectively. Finally, the wavefront error compensation is performed by two adaptive post focal Deformable Mirrors (DMs) located inside MORFEO (the core of the instrument), which work together with the telescope’s adaptive and tip-tilt mirrors M4 and M5 respectively. The overall optical path will consist of several 1m class optical elements: 6 flat folding mirrors, one corrective plate, two aspherical mirrors, a large dichroic filter, a refractive objective and 2 deformable mirrors (DMs). All the optical elements are hosted by the Main Support structure (see following definition) except the last one (M12M) that bends the light into the client instrument (called MICADO), which is supported by MICADO. MORFEO is being designed and built by a consortium of partners in Italy, France, Ireland, Canada and Japan together with ESO. INAF, as the leading institute, is responsible for all the major procurements. 2. The project has completed the Preliminary Design Phase and is in the Final Design Phase. The final design and the manufacturing of some components will be assigned to external companies. In particular, the MORFEO Consortium would like to inform all the industries concerned that a number of international public calls for tender are in publication and selection phase concerning the final design. In particular, this preliminary information note describes general requirements and conditions for the final design and the manufacturing of the Main Structure and handling tools for MORFEO. 3.The call for tender for Main Structure (MS) and AIV tools will be placed in the framework of the general technical specifications available at the link http://wwwmorfeo.oabo.inaf.it/index.php/info_mainstruct/ A Statement of Work including a detailed description of all procurement conditions and technical specifications (and applicable documents) will be published with the public call for tender. The actual design, E-MAO-000-00-00-00-00-INA-MOD-001_02 MAORY System Model, is provided as a reference and can be downloaded at the following link (http://wwwmorfeo.oabo.inaf.it/index.php/mainstruct_model/). The manufacturer is free to propose their own Main Structure Subsystem design, which may be completely different from the consortium one, a variation of it, or the consortium design itself. In any case, the manufacturer shall ensure performance of the system and the design itself shall be discussed with, and accepted by, the consortium

  • Contact

    MARCO RIVAmarco.riva@inaf.it
  • Type
    Planning
  • Location
    Bologna
  • Main code
    Structural products and parts except prefabricated buildings
    44212000

Similar active competitions

  • Mbryonics Ltd

    Laboratorie-, optisk- og presisjonsutstyr

    Procurement of a High-Precision Optical Ground Station (OGS) Telescope Unit for Uplink and Satellite Tracking

    Mbryonics Ltd requires the design, manufacture and turnkey delivery of a high-precision optical ground station telescope unit for satellite uplink and tracking, under a supply contract valued at up to €420,000 total, with a stated duration of 6 months and delivery required within 3–4 months of contract signature. The unit will support Ireland’s TransEuroOGS project and must include the mount, optics and control software; delivery is associated with Ireland’s West and South-West regions. Key requirements include a Ritchey–Chrétien optical system with at least a 700 mm aperture, high reflectivity at 1550 nm and capacity for a 40 W continuous-wave launch beam, a reflective Nasmyth focus path with at least 60 mm clear aperture, and a fast, precise mount capable of tracking LEO satellites, including near-zenith passes. The telescope must meet strict height and clearance limits and integrate with INDI/INDIGO or ASCOM/ALPACA, with a documented network API for robotic control and telemetry. Full CAD models and opto-mechanical layout files are required upon award.

    Competition
    Dec 4, 2026(15 days)
    €420,000
  • European Patent Organisation

    Laboratorie-, optisk- og presisjonsutstyr

    Optical components for an IFU

    Das Max-Planck-Institut für extraterrestrische Physik (MPE) benötigt die Lieferung optischer Komponenten für eine Integralfeld-Einheit (IFU). Die Lieferungen skal erfolgen nach München im Landkreis.

    Competition
    Dec 4, 2026(15 days)
  • OSSERVATORIO ASTRONOMICO DI CAPODIMONTE

    Laboratorie-, optisk- og presisjonsutstyr

    FORNITURA DELL'AGGIORNAMENTO DEL SISTEMA DI CONTROLLO DELLE DUE UNITA DI SPECCHIO SECONDARIO ADATTIVO DEL LARGE BINOCULAR TELESCOPE (LBT), nell'ambito del WP5.1 del progetto PNRIC 2021-2027 STILEMI (CUP: C83C26000120007)

    L’Osservatorio Astronomico di Capodimonte deve acquisire l’aggiornamento del sistema di controllo delle due unità di specchio secondario adattivo del Large Binocular Telescope (LBT), nell’ambito del progetto STILEMI, per un valore massimo complessivo di 4.445.924 euro. La fornitura riguarda apparati astronomici e ottici; le offerte saranno valutate in base alla proposta tecnica (45%), alla proposta gestionale (35%) e al ribasso sul prezzo (20%).

    Competition
    Dec 18, 2026(29 days)
    €4,445,924