Offshore Array Cable installation for Gode Wind 3 (GOW03) and Borkum Riffgrund 3 (BKR03) Offshore Wind Farms

Awarded

The competition has ended and a winner has been selected.

Qualification deadline
Nov 18, 2021Expired
Procedure
With negotiationTwo stages
Agreement
Construction work

Brief

The Works comprises: - Transport, installation and Burial campaign of Array Cables for GOW03 and BKR03 . Totally 106 cables

Road and Cable Laying

Result

TED
  • Boskalis Subsea Cables B.V
    Winner
  • Number of tenders received
    0
  • Contract value
    Not stated

Previous winners

  • Who are you up against?

    The suppliers who have won similar contracts at Ørsted Wind Power A/S

Will you bid?

The agent sets up the bid and writes the first draft. Free for 14 days.

From the notice

  • The Works comprises: - Transport, installation and Burial campaign of Array Cables for GOW03 and BKR03 . Totally 106 cables

  • Contact

    STERN@ORSTED.COM
  • Type
    Result · Prequalification
  • Main code
    Construction work
    45000000
  • 45231000Construction work for pipelines, communication and power lines45231400Construction work for electricity power lines45231600Construction work for communication lines45232000Ancillary works for pipelines and cables45232200Ancillary works for electricity power lines45252125Rock-dumping work45314300Installation of cable infrastructure45314310Installation of cable laying60630000Cable-laying ship services

Similar active competitions

  • Energistyrelsen

    Electrical equipment and lighting

    North Sea I, South, Offshore Wind Farm

    Danish Energy Agency har udbudt en koncessionsaftale for etablering og drift af havvindmølleparken "North Sea I, South" ud for Vestjylland. Projektet omfatter opførelse og drift af en havvindmøllepark med en minimumskapacitet på 1 GW, med en kontraktvarighed på 40 år og en maksimal totalværdi på 6,6 milliarder DKK ekskl. moms (2025-priser) i form af statsstøtte over 20 år. Koncessionshaveren bærer den kommercielle risiko, men vil modtage økonomisk støtte via en tovejs Contract for Difference (CfD) ordning. Tildelingskriteriet er den laveste budpris (100%). Kvalifikationskrav inkluderer mindst én reference fra et storskala offshore energiproduktionsprojekt inden for de seneste ti år, med anlægsomkostninger på minimum 500.000.000 DKK, fastgjort til havbunden på mindst 10 meters dybde, og en kontraktvarighed på minimum 25 år. Referencen skal desuden vise erfaring inden for mindst tre af følgende områder: projektledelse, engineering, indkøb, udførelse, drift eller kvalitetskontrol.

    Competition
    Oct 23, 2028(100+ days)
    DKK 6,600,000,000
  • GRAND PORT MARITIME DE MARSEILLE

    PROJET DEOS - CONCEPTION/REALISATION DES INFRASTRUCTURES PORTUAIRES POUR LE DEVELOPPEMENT DE L'EOLIEN OFFSHORE

    Le Grand Port Maritime de Marseille (GPMM) recherche un groupement chargé de concevoir et réaliser, en 40 mois et pour un montant maximal total de 302,4 millions d’euros, les infrastructures portuaires du projet DEOS, destiné à accueillir le développement de l’éolien flottant. Le chantier, situé dans les Bouches-du-Rhône, prévoit une plateforme dédiée sur une parcelle de 30 hectares, un espace de stockage à flot de 31 hectares, un quai, des estacades en mer, des terre-pleins lourds et des travaux de dragage. La procédure avec négociation comprend une phase de candidature, puis une phase d’offre réservée à un maximum de trois candidats. Le marché de conception-réalisation sera rémunéré par un prix global et forfaitaire.

    Competition with qualification
    Dec 15, 2026(17 days)
    €302,400,000
  • EWE Netz GmbH

    Qualifizierungssystem für Seekabel

    Die EWE Netz GmbH benötigt Seekabel für 7 Inseln im deutschen Wattenmeer. Das Qualifizierungssystem hat eine Laufzeit von 10 Jahren. Es werden technische, berufliche sowie wirtschaftliche und finanzielle Leistungsfähigkeit gemäß dem Fragebogen gefordert.

    Qualification system
    May 30, 2036(100+ days)