All tenders: Ireland/Medite Europe DAC/PQQ for MDF Blowline Upgrades at Medite Europe DAC

PQQ for MDF Blowline Upgrades at Medite Europe DAC

Expired

The competition has expired without a winner being announced.

Deadline
Dec 10, 2025Expired
Procedure
OpenSingle stage
Agreement
Buying goods
Estimated value
€250Kover 1 month

Brief

Medite Europe DAC needs resin products for Blowline Upgrades at their facility in Dublin. The project involves supplying Blowline resin injection and steam recovery systems for a Medium Density Fibre production line, with an anticipated order placement in Q1 2026 and project completion by Q3 2026. The maximum total contract value is 250,000 EUR. The resin injection system should control and modulate resin application to ensure efficient use while maintaining product quality, with a desirable capability to apply other additives. The steam recovery system must recover steam from the Blowline for reuse on the refining system, ensuring minimal wood/fibre content. Both systems must be fully automated, proven technology, conform to best practice design principles, and comply with all relevant European legislation, including CE marking.

Engineering and Design Services

Register interest

Previous winners

  • Who are you up against?

    The suppliers who have won similar contracts at Medite Europe DAC

Will you bid?

The agent sets up the bid and writes the first draft. Free for 14 days.

From the notice

  • MEDITE Europe DAC is invites expressions of interest from experience / qualified companies for the supply of Blowline resin injection and steam recovery systems for a Medium Density Fibre production line that operates up to 15 t/h of dry fibre and 20 to 70 l/min of resin. For Blowline resin injection technology a system will be required to control and modulate the correct application of resin based on specific product requirements within the above flows in order to ensure efficient use of resin while maintaining product quality and without negative impacts to the process or product itself. This efficient use of resin with the new system should result in a resin usage saving. A system that can also apply the other additives typically added in the Blowline in the MDF process such as dye, urea, wax and hardener would be desirable. The system should be fully automated. For Blowline steam recovery technology a system will be required to recover steam from the Blowline and return it for reuse on the refining system. The returned/recovered steam should have minimal wood/fibre content and not cause blocking of the Blowline or other parts of the refining system. The equipment must be a proven technology and conform to best practice design principles and all relevant European legislation including CE marking. It is anticipated that order placement will occur in Q1 2026 with project completion by Q3 2026.

  • Contact

    John.Browne@mdfosb.com
  • Type
    Competition
  • Location
    Dublin
  • Main code
    Resin products
    24327400
  • 42993000Chemical industry machinery45351000Mechanical engineering installation works71320000Engineering design services71323000Engineering-design services for industrial process and production71330000Miscellaneous engineering services77220000Timber-impregnation services

Similar active competitions

  • Iarnród Eireann-Irish Rail

    Trucks and Transport Vehicles

    8906 - QS for Fueling Facilities and Equipment

    Iarnród Éireann seek to establish a Qualification System for the Supply and Installation of Fueling Facilities and Equipment nationwide. It is anticipated that the following list of works and equipment will be required over the lift of the Qualification System, however Iarnród Éireann will rely on this process for other fuelling facilities and equipment which may be required. Supply and installation of: • Diesel Dispensers • Adblue Dispensers • Coolant Dispensers • Dispensing Accessories • Fuel Tanks • Storage Tanks • Hose management systems • Fuel and Discharge hoses • Hose cabinets • Design and civil works associated with above

    Qualification system
    Jul 5, 2027(100+ days)
  • Electricity Supply Board ( ESB )

    Construction machinery and equipment

    HEAT EFFICIENCY SYSTEMS

    Provision of Heat efficiency technology such as heat pump installations on a turnkey basis, design, fully installed and commissioned. The Contractor will be responsible for design, supply, and installation of all materials, and system commissioning including handover to the designated O and M (Operation and Maintenance) and /or Asset owner.

    Qualification system
    Jun 24, 2027(100+ days)
  • Bord na Móna PLC

    Electrical installation in buildings

    CM 06/24 - Electrical Balance of Plant Qualification System

    EBoP panel creation for all upcoming grid projects. QQD to included the following Lots – Lot 1-110 KV, Lot 2 - 220 KV and Lot 3 - 400 KV.

    Qualification system
    Sep 26, 2027(100+ days)