    Pre-qualification for process pumps to Datacenter Heat Pump plants project in Espoo and Kirkkonummi

    Fortum Power and Heat Oy

    Pre-qualification for process pumps to Datacenter Heat Pump plants project in Espoo and Kirkkonummi

    1. Competition notice published

      Oct 24, 2023 10:22 AMOctober 24, 2023 10:22 AM
    2. Qualification deadline

      Nov 23, 2023 10:00 AMNovember 23, 2023 10:00 AM
    3. Tender submission deadline

      Comes with the invitation

    Brief

    Finland: Tenders/Fortum Power and Heat Oy/Pre-qualification for process pumps to Datacenter Heat Pump plants project in Espoo and Kirkkonummi

    Published deadline passed

    The published deadline has passed. For multi-stage competitions a later tender deadline may still apply — check the notice or portal for the current phase.

    Qualification deadline
    Nov 23, 2023Expired
    Procedure
    Competitive dialogueTwo stages
    Agreement
    Buying goods

    Brief

    Scope of supply consists of the following complete Process pumps with motors. The final scope and options will be announced later in the Invitation to Tender (ITT) material: All pumps are horizontal centrifugal with single stage axial intake electric motor driven water pumps for continuous operation. Including the following process pumps with motors and services, but not limited to:  Process Pumps for KOL-heat pump plant with the following preliminary data DH WWHP Pumps 4 90 100 SS Electric Boiler DH Pumps 2 400 100 SS LTO WWHP Pumps 4 175 30 SS Heat Recovery Circuit Pump 1 700 75 SS Heat Recovery Circuit Pump 1 350 50 SS DH Accu Charge Pump, 30% 1 180 50 SS DH Accu Charge Pump, 70% 1 420 50 SS DH Accu Safety Valve Filling Pump 1 1 25 SS Transformer CW Circuit Pumps 2 20 25 SS Transformer Cooling water Pumps 2 30 20 SS Process Pumps for OPTION for HEP-heat pump plant with the following preliminary data DH WWHP Pumps 4 90 100 SS Electric Boiler DH Pumps 2 400 100 SS LTO WWHP Pumps 4 175 30 SS Heat Recovery Circuit Pump 1 700 75 SS Heat Recovery Circuit Pump 1 350 50 SS DH Accu Charge Pump, 30% 1 180 50 SS DH Accu Charge Pump, 70% 1 420 50 SS DH Accu Safety Valve Filling Pump 1 1 25 SS Transformer CW Circuit Pumps 2 20 25 SS Transformer Cooling water Pumps 2 30 20 SS Also: Frequency converters for all pumps as an OPTION Performance test at factory Packing for transportation Transportation of Process pumps to construction site Mechanical/electrical installation inspection Commissioning of pumps, motors, and frequency converters Final documentations Spare parts Training for operation and maintenance personnel

    Pumpestasjoner og pumpesystemer

    Register interest

    Custom Assessment Criteria

    • Get answers to your bid/no-bid criteria

      Set them up once and Cobrief answers them in every tender

    Will you bid?

    The agent sets up the bid and writes the first draft. Free for 14 days.

    Award Criteria

    • Source

      No source found in the documents. Check the weight against the tender documents.

    Previous winners

    • Who are you up against?

      The suppliers who have won similar contracts at Fortum Power and Heat Oy

    From the notice

    • Scope of supply consists of the following complete Process pumps with motors. The final scope and options will be announced later in the Invitation to Tender (ITT) material: All pumps are horizontal centrifugal with single stage axial intake electric motor driven water pumps for continuous operation. Including the following process pumps with motors and services, but not limited to:  Process Pumps for KOL-heat pump plant with the following preliminary data DH WWHP Pumps 4 90 100 SS Electric Boiler DH Pumps 2 400 100 SS LTO WWHP Pumps 4 175 30 SS Heat Recovery Circuit Pump 1 700 75 SS Heat Recovery Circuit Pump 1 350 50 SS DH Accu Charge Pump, 30% 1 180 50 SS DH Accu Charge Pump, 70% 1 420 50 SS DH Accu Safety Valve Filling Pump 1 1 25 SS Transformer CW Circuit Pumps 2 20 25 SS Transformer Cooling water Pumps 2 30 20 SS Process Pumps for OPTION for HEP-heat pump plant with the following preliminary data DH WWHP Pumps 4 90 100 SS Electric Boiler DH Pumps 2 400 100 SS LTO WWHP Pumps 4 175 30 SS Heat Recovery Circuit Pump 1 700 75 SS Heat Recovery Circuit Pump 1 350 50 SS DH Accu Charge Pump, 30% 1 180 50 SS DH Accu Charge Pump, 70% 1 420 50 SS DH Accu Safety Valve Filling Pump 1 1 25 SS Transformer CW Circuit Pumps 2 20 25 SS Transformer Cooling water Pumps 2 30 20 SS Also: Frequency converters for all pumps as an OPTION Performance test at factory Packing for transportation Transportation of Process pumps to construction site Mechanical/electrical installation inspection Commissioning of pumps, motors, and frequency converters Final documentations Spare parts Training for operation and maintenance personnel

    • Contact

      jarno.vainio@fortum.com
    • Type
      Competition · Dynamic purchasing system · Prequalification
    • Main code
      Pumps
      42122000

    Similar active competitions

    • Fortum Power and Heat Oy

      Laboratorie-, optisk- og presisjonsutstyr

      PREQUALIFICATION FOR DELIVERY OF FLOW- AND ENERGY METERS FOR THE DISTRIBUTION OF HEATING AND COOLING

      Fortum Power and Heat Oy needs flow and energy meters for the distribution of heating and cooling, including district heating and cooling calculators, flow sensors (from 1.5 up to 1000 m3/h flow rates, PN16 to PN25 nominal distribution pressure, G1” up to DN250 pipe connection), temperature sensors, auxiliary cards, communication devices/cards, and other compatible accessories. The goods are to be delivered in Helsinki-Uusimaa, Finland. This is a prequalification for a framework agreement.

      Framework agreement with qualification
      Oct 30, 2026(0 days)
    • Pääkaupunkiseudun Kaupunkiliikenne Oy

      Anleggsmaskiner og utstyr

      Pumppaamot metrolinjalle -puitejärjestely

      Pääkaupunkiseudun Kaupunkiliikenne Oy hankkii pumppaamoita metrolinjoille, mukaan lukien perusvesipumppaamot ja muita pumpputyyppejä. Hankinta toteutetaan puitejärjestelynä kolmen toimittajan kanssa kuuden vuoden ajaksi, ja sen ennakoitu kokonaisarvo on noin 2,5 miljoonaa euroa. Hankinta on jaettu kahteen osa-alueeseen: Kantametro (HKL) sekä Länsimetro ja Sammalvuoren Metrovarikko. Tarjoaja voi tarjota yhtä tai kahta osa-aluetta. Tarjoukset arvioidaan hinnan perusteella.

      Framework agreement
      Nov 16, 2026(17 days)
      €2,520,000
    • Fortum Power and Heat Oy

      Elektrisitet og energiforvaltning

      Esivalinta - Espoon, Kauniaisten ja Kirkkonummen alueen kaukolämpö- ja kaukojäähdytysverkoston rakentamisen vuosiurakoinnin raamisopimuskilpailutus

      Fortum Power and Heat Oy hakee raamisopimuskumppaneita Espoon, Kauniaisten ja Kirkkonummen kaukolämpö- ja kaukojäähdytysverkoston vuotuisiin korjaus-, saneeraus- ja uudisrakennustöihin. Urakkaan sisältyy rakennus-, putkiasennus- ja eristystöitä, ja työt sijoittuvat Fortumin verkkoalueille Espoossa, Kauniaisissa ja Kirkkonummella. Tarjouksia arvioidaan hinnan ja laadun perusteella; tarkemmat arviointiperusteet ilmoitetaan tarjouspyyntövaiheessa. Vuoden 2023 vastaavan kilpailutuksen voittivat Maalinja Oy ja Maarakennusliike Pusku Oy.

      Framework agreement with qualification
      Nov 11, 2026(12 days)