    Przedmiot zamówienia obejmuje dostawę (bez montażu i uruchomienia) komponentów systemu magazynowania energii elektrycznej typu BESS

    ENEA Nowa Energia sp. z o.o.

    Przedmiot zamówienia obejmuje dostawę (bez montażu i uruchomienia) komponentów systemu magazynowania energii elektrycznej typu BESS

    1. Questions deadline

      Jan 20, 11:00 AMJanuary 20, 2026 11:00 AM
    2. Tender submission deadline

      Feb 3, 11:00 AMFebruary 3, 2026 11:00 AM
    3. Competition notice published

      Mar 17, 12:57 PMMarch 17, 2026 12:57 PM
    4. Change in competition

      Apr 1, 7:29 AMApril 1, 2026 7:29 AM
    5. Change in competition

      Apr 15, 11:01 AMApril 15, 2026 11:01 AM
    6. Change in competition

      Apr 23, 10:57 AMApril 23, 2026 10:57 AM
    7. Contract start date

      Apr 30, 10:00 PMApril 30, 2026 10:00 PM
    8. Tender validity period

      May 3, 10:00 AMMay 3, 2026 10:00 AM
    9. Result notice published

      May 21, 6:03 AMMay 21, 2026 6:03 AM

    Brief

    Poland: Tenders/ENEA Nowa Energia sp. z o.o./Przedmiot zamówienia obejmuje dostawę (bez montażu i uruchomienia) komponentów systemu magazynowania energii elektrycznej typu BESS

    Cancelled

    The competition has been cancelled.

    Brief

    Elektrisk utstyr og belysning

    ENEA Nowa Energia sp. z o.o. zamierzała zawrzeć umowę na dostawę komponentów systemu magazynowania energii elektrycznej typu BESS o docelowej pojemności 840 MWh, z gwarancją zakupu co najmniej 600 MWh w ciągu 24 miesięcy od zawarcia umowy, z opcją zwiększenia zamówienia o 240 MWh. Umowa miała obowiązywać przez 36 miesięcy. Wymagano urządzeń kompletnych, fabrycznie nowych, przygotowanych do montażu i uruchomienia, a wykonawca miał uczestniczyć w uruchomieniu systemu BESS. Kryteria oceny ofert obejmowały cenę (80%), serwis gwarancyjny (5%, min. 5 lat), liczbę cykli (5%, min. 10 000 przy DoD 90% i SoH 65%) oraz sprawność na szynach rozdzielni SN (10%, min. 84%). Zamówienie zostało anulowane z powodu braku finansowania. W postępowaniu wpłynęły 3 oferty, a zwycięzcą zostało Konsorcjum: Lider: Przedsiębiorstwo „AGAT” Partner: TAKOM ENERGIA sp. z o.o., TECLOMAN ENERGY, LG ENERGY SOLUTION WROCŁAW Sp. z o.o.

    Result

    Reason for cancellation
    Besluttning av oppdragsgiveren på grunn av manglende finansiering
    Winners
    • AGAT S.A.
    • LG Energy Solution Wrocław sp. z o.o.
    • TECLOMAN ENERGY
    Number of bids
    3
    Contract value
    Not stated

    About the bid

      Przedmiot zamówienia obejmuje dostawę (bez montażu i uruchomienia) komponentów systemu magazynowania energii elektrycznej typu BESS o mocy użytkowej i pojemności użytkowej zgodnie z Załącznikiem nr 1a do OPZ („Lista projektów BESS”). Wykonawca dostarczy urządzenia kompletne, fabrycznie nowe, przygotowane do sprawnego montażu i uruchomienia przez Zamawiającego lub odrębnego Wykonawcę, oraz będzie uczestniczył w uruchomieniu dostarczonego systemu BESS – zgodnie z OPZ. Umowa będzie obowiązywać przez okres 36 miesięcy od jej zawarcia. Na szczegółowy Opis Przedmiotu Zamówienia składają się następujące dokumenty: 1) Opis Przedmiotu Zamówienia („OPZ”) 2) Lista projektów BESS będąca Załącznikiem nr 1a do OPZ 1. Zamawiający planuje realizację dostaw systemów BESS o łącznej docelowej pojemności 840 MWh pojemności użytkowej, w różnych konfiguracjach mocy/pojemności, zgodnie z Załącznikiem nr 1a do OPZ 2.Zamawiający gwarantuje złożenie zamówień i zakup łącznie na co najmniej 600 MWh pojemności użytkowej w ciągu 24 miesięcy od dnia zawarcia umowy w konfiguracjach wynikających z potrzeb Zamawiającego oraz Załącznika nr 1a do OPZ. 3.Zamawiający przewiduje możliwość skorzystania z prawa opcji zgodnie z art. 441 uPZP zwiększającego zakres zamówienia o 240 MWh do poziomu planowanego 840 MWh. Szczegółowy sposób skorzystania z prawa opcji opisano w dokumentacji zamówienia. 4. Zamawiający dopuszcza możliwość udzielenia Wykonawcy zaliczek na poczet wykonania przedmiotu zamówienia, zgodnie z art. 442 ust.1 uPZP. Łączna wartość zaliczek nie przekroczy 100% wynagrodzenia umownego brutto. Szczegółowy sposób udzielania zaliczek opisano w dokumentacji zamówienia.

      Contact name
      Marta Kozłowska
      Contact phone
      +48(61)8848376
      Contact email
      marta.kozlowska@enea.pl
      Address
      ENEA Nowa Energia sp. z o.o., 26-610 Radom

    Custom Assessment Criteria

    Start a free trial to ask your own questions about the tender and get AI-generated answers.

    Award Criteria

    • Description

      Kryterium K1 - cena Oferty brutto

    • Description

      Kryterium K2 - serwis gwarancyjny w latach (min. 5 lat)

    • Description

      Kryterium K3 - ilość cykli (min. 10.000 przy DoD 90% i SoH 65%)

    • Description

      Kryterium K4 - sprawność na szynach rozdzielni SN w % (min. 84 %)

    Qualification requirements

      Found no qualification requirements in the contract notice.

    Previous Contract Winners

    Start a free trial to see who has won similar tenders for this buyer.

    See the full notice

    Contracting authority
    ENEA Nowa Energia sp. z o.o.
    Title
    Przedmiot zamówienia obejmuje dostawę (bez montażu i uruchomienia) komponentów systemu magazynowania energii elektrycznej typu BESS
    Type
    ResultPrequalification
    Main code
    31154000Uninterruptible power supplies
    Supplemental codes
    31121110Power converters31155000Inverters31170000Transformers31320000Power distribution cables31321000Electricity power lines31400000Accumulators, primary cells and primary batteries31430000Electric accumulators31440000Batteries45232221Transformer substation
    Duration
    36 months

    Active similar competitions

    • TAURON BME9 sp. z o.o.

      Elektrisk utstyr og belysning

      Dostawa komponentów systemu magazynowania energii elektrycznej dla BESS Bytom

      TAURON BME9 sp. z o.o. potrzebuje dostawy komponentów systemu magazynowania energii elektrycznej dla BESS Bytom. Dostawa ma miejsce w Bytomiu. Kryteriami oceny ofert są: Cena oferty brutto (85%), Gwarancja (5%), Parametry techniczne (stopień integracji fabrycznej i gotowości instalacyjnej) (5%) oraz Efektywność w obie strony (5%).

      CompetitionOct 7, 2026
      Oct 20, 2026(11 days)
    • TAURON BME9 sp. z o.o.

      Elektrisk utstyr og belysning

      Dostawa komponentów systemu magazynowania energii elektrycznej BESS Ostrów Szlachecki

      TAURON BME9 sp. z o.o. potrzebuje dostawy komponentów systemu magazynowania energii elektrycznej (BESS Ostrów Szlachecki) w Krakowie. Kryteriami oceny ofert są: cena oferty brutto (85%), gwarancja (5%), parametry techniczne (stopień integracji fabrycznej i gotowości instalacyjnej) (5%) oraz efektywność w obie strony (5%).

      CompetitionOct 7, 2026
      Oct 21, 2026(12 days)
    • TAURON BME8 sp. z o.o.

      Elektrisk utstyr og belysning

      Dostawa komponentów systemu magazynowania energii elektrycznej BESS Laryszów

      TAURON BME8 sp. z o.o. potrzebuje dostawy komponentów systemu magazynowania energii elektrycznej (BESS) do lokalizacji w Bytomiu. Kryteriami oceny ofert są: cena oferty brutto (85%), gwarancja (5%), parametry techniczne (stopień integracji fabrycznej i gotowości instalacyjnej) (5%) oraz efektywność w obie strony (5%).

      CompetitionOct 7, 2026
      Oct 19, 2026(10 days)
    • Gmina Wilamowice

      Bygningsarbeid og installasjoner

      Poprawa efektywności energetycznej obiektów użyteczności publicznej na terenie Gminy Wilamowice.

      Gmina Wilamowice potrzebuje dostawy, montażu, podłączenia, konfiguracji i uruchomienia magazynów energii, a także instalacji fotowoltaicznych, wraz z robotami towarzyszącymi, pomiarami, próbami, rozruchem, dokumentacją powykonawczą i szkoleniem użytkowników, w celu poprawy efektywności energetycznej obiektów użyteczności publicznej na terenie Gminy Wilamowice. Czas trwania zamówienia wynosi 5 miesięcy. Kryteria oceny ofert to cena brutto (60%) i gwarancja udzielona przez wykonawcę (40%). Wymagane jest wykazanie, że w ciągu ostatnich 3 lat wykonawca zrealizował co najmniej jedno zadanie polegające na dostawie, montażu i uruchomieniu magazynu energii o pojemności co najmniej 15 kWh.

      CompetitionSep 8, 2026
      Oct 20, 2026(11 days)
    • Gmina Bieruń reprezentowana przez Burmistrza Miasta Bierunia

      Elektrisitet og energiforvaltning

      Zielona energia – Budowa instalacji OZE w Gminie Bieruń

      Gmina Bieruń potrzebuje dostawy i montażu kompletnych mikroinstalacji fotowoltaicznych dla 8 obiektów użyteczności publicznej, montażu magazynów energii dla 9 budynków, modernizacji istniejącej instalacji wyłączników ppoż. oraz wykonania niezbędnych robót ogólnobudowlanych towarzyszących i systemu monitoringu produkcji energii. Zamówienie ma zostać zrealizowane w ciągu 6 miesięcy w powiecie Tyskim. Kryteria oceny ofert to cena (60%), gwarancja i rękojmia za wady – moduły fotowoltaiczne (10%), gwarancja i rękojmia za wady – magazyny energii i falowniki hybrydowe (20%) oraz termin usunięcia wad (10%). Wymagane jest posiadanie co najmniej jednej osoby z uprawnieniami budowlanymi do kierowania robotami budowlanymi w specjalności konstrukcyjno-budowlanej bez ograniczeń oraz co najmniej jednej osoby z uprawnieniami budowlanymi do kierowania robotami budowlanymi w specjalności instalacyjnej w zakresie sieci, instalacji i urządzeń elektrycznych i elektroenergetycznych bez ograniczeń. Wykonawca musi również wykazać, że w ciągu ostatnich 3 lat należycie wykonał instalację i uruchomienie co najmniej jednej instalacji fotowoltaicznej o mocy minimum 30 kWp i pojemności magazynu energii co najmniej 30 kWh.

      CompetitionSep 17, 2026
      Oct 20, 2026(11 days)