Snubbing unit for recompletion of To-7 at Lille Torup
Published deadline passed
The published deadline has passed. For multi-stage competitions a later tender deadline may still apply — check the notice or portal for the current phase.
- Qualification deadline
- 11. jan. 2022Expired
- Procedure
- With negotiationTwo stages
Brief
Gas Storage Denmark A/S (GSD) owns and operates Denmark’s two underground gas storage facilities, which are located in Stenlille in the central part of Zealand (aquifer storage facility) and in Lille Torup in northern Jutland (salt cavern facility). GSD plans to execute the recompletion and gas fill of cavern Lille Torup 7 (To-7), which is currently brine filled. After the cavern To-7 is recompleted and the gas fill operation has taken place the installed debrining string has to be snubbed out of the cavern before the gas operation will start. Operation for this phase is planned for Q4/2022 - Q1/2023. To allow the gas fill to take place, the brine will be moved from cavern To-7 to cavern Lille Torup 8 (To-8). Therefore, a flooding string has to be snubbed into the cavern. Operation for this phase is planned for Q2 2022. The current tender concern a snubbing unit perform the above-mentioned operation. Further details can be found in the technical snubbing specification.
Custom Assessment Criteria
Get answers to your bid/no-bid criteria
Set them up once and Cobrief answers them in every tender
Will you bid?
The agent sets up the bid and writes the first draft. Free for 14 days.
Qualification requirements
Description
The applicant must confirm the economic ability in the ESPD part IV.B: “Economic and financial standing” with information from the latest annual report regarding the following economic indicators: 1. Equity (total equity incl. share capital, reserves, revaluation, retained earning etc.) 2. Equity ratio (equity/total assets) If the applicant is relying on the capacities of one or more other entities (e.g. a parent or sister company or a subcontractor) or the applicant is a group of economic operators (e.g. a consortium) the information for the ESPD part IV.B must also be given in a separate ESPD from each of these entities, cf. section VI.3 “Additional information”. It is the sole responsibility of the applicant to secure that the minimum level(s) of standards required are reached when the applicant is relying on the capacity of other entities or when the applicant is a group of economic operators (e.g. a consortium).
Documentation Requirement
Information from the latest annual report regarding equity (total equity incl. share capital, reserves, revaluation, retained earning etc.) and equity ratio (equity/total assets) in the ESPD part IV.B: “Economic and financial standing”. If relying on other entities, a separate ESPD from each of these entities.
Source
No source found in the documents. Check the requirement against the tender documents.
Description
The applicant must include the up to 5 most comparable and relevant references undertaken in the past six years as part of the application. Undertaken in the past six years implies that the reference must not have been completed prior to the date reached when counting six years backwards from the submission date for prequalification. References older than this will not be taken into consideration. References which have not yet been fully completed can be included as part of the application, but if this is the case, the applicant must describe the parts which have not yet been delivered, and this may affect the evaluation of the applicant, cf. section II.2.9. The references should include: • A specific description of the work performed for each reference, including a description of the provided services and the cavern/location • (if applicable) Gas cavern pressure level. • Place of performance (incl. country) • Contract value (if possible) • Contact information for the entity in question (if possible) • Date of initiation and final delivery (day, month, year) Any ambiguities and/or incomprehensibilities concerning the above information may have a negative effect on the selection of candidates, cf. section II.2.9. Please note the “description” box can contain more text than is visible. I.e. it is possible to copy paste text into the box. If the applicant is relying on the references of one or more other entities (e.g. a parent or sister company or a subcontractor) or the applicant is a group of economic operators (e.g. a consortium) the information for the ESPD part IV.C must also be given in a separate ESPD from each of these entities. The number of references should not surpass a maximum of the 5 most comparable and relevant references. If the applicant is relying on the capacity of one or more other entities (e.g. a parent or sister company or a subcontractor) or the applicant is a group of economic operators (e.g. a consortium) the maximum number of references to be submitted must still be respected and cannot exceed 5 when combined. If more than 5 references are submitted, the Contracting Authority will only consider the 5 most recent references determined by date of final delivery (in this case not yet finished references will not be included).
Documentation Requirement
Up to 5 most comparable and relevant references undertaken in the past six years, listed in the ESPD part IV.C: “Technical and professional ability”. Each reference should include: a specific description of the work performed, including services and cavern/location; gas cavern pressure level (if applicable); place of performance (incl. country); contract value (if possible); contact information for the entity (if possible); date of initiation and final delivery. If relying on other entities, a separate ESPD from each of these entities.
Source
No source found in the documents. Check the requirement against the tender documents.
Description
The applicant must submit a completed version of the ESPD. Applicants may not be subject to the mandatory grounds for exclusion, cf. the Danish Public Procurement Act (udbudsloven) Section 135 (1-3) and 136. Please see section VI.3 “Additional information” for further information regarding the ESPD. The application must be submitted through EU-Supply, cf. link in section I.1 in this notification. Applications not submitted via EU-supply or received after the deadline will not be accepted. The Contracting Authority reserves the right to request the applicant to supplement, specify or complete the information submitted.
Documentation Requirement
A completed version of the ESPD, confirming that the applicant is not subject to mandatory grounds for exclusion as per the Danish Public Procurement Act (udbudsloven) Section 135 (1-3) and 136. The application must be submitted through EU-Supply.
Source
No source found in the documents. Check the requirement against the tender documents.
Previous winners
Who are you up against?
The suppliers who have won similar contracts at Gas Storage Denmark A/S
From the notice
Gas Storage Denmark A/S (GSD) owns and operates Denmark’s two underground gas storage facilities, which are located in Stenlille in the central part of Zealand (aquifer storage facility) and in Lille Torup in northern Jutland (salt cavern facility). GSD plans to execute the recompletion and gas fill of cavern Lille Torup 7 (To-7), which is currently brine filled. After the cavern To-7 is recompleted and the gas fill operation has taken place the installed debrining string has to be snubbed out of the cavern before the gas operation will start. Operation for this phase is planned for Q4/2022 - Q1/2023. To allow the gas fill to take place, the brine will be moved from cavern To-7 to cavern Lille Torup 8 (To-8). Therefore, a flooding string has to be snubbed into the cavern. Operation for this phase is planned for Q2 2022. The current tender concern a snubbing unit perform the above-mentioned operation. Further details can be found in the technical snubbing specification.
Contact
Helle Barløseprocurement@energinet.dk- Competition · PrequalificationType
- 76490000Main codeWell-completion services