Search
  • Search


    Snubbing unit for recompletion of To-7 at Lille Torup

    Gas Storage Denmark A/S

    Snubbing unit for recompletion of To-7 at Lille Torup

    1. Contract signed

      25. mai 2022 kl. 00:0025. mai 2022 kl. 00:00
    2. Result notice published

      8. juni 2022 kl. 08:008. juni 2022 kl. 08:00

    Brief

    Denmark: Tenders/Gas Storage Denmark A/S/Snubbing unit for recompletion of To-7 at Lille Torup

    Awarded

    The competition has ended and a winner has been selected.

    Qualification deadline
    7. juni 2022Expired
    Procedure
    Without prior noticeTwo stages
    Agreement
    Buying services

    Brief

    Gas Storage Denmark A/S (GSD) owns and operates Denmark’s two underground gas storage facilities, which are located in Stenlille in the central part of Zealand (aquifer storage facility) and in Lille Torup in northern Jutland (salt cavern facility). GSD plans to execute the recompletion and gas fill of cavern Lille Torup 7 (To-7), which is currently brine filled. After the cavern To-7 is recompleted and the gas fill operation has taken place the installed debrining string has to be snubbed out of the cavern before the gas operation will start. To allow the gas fill to take place, the brine will be moved from cavern To-7 to cavern Lille Torup 8 (To-8). Therefore, a flooding string has to be snubbed into the cavern. The current contract concerns a snubbing unit performing the above mentioned operation.

    Result

    TED
    • Superior Energy Services (SPN) B.V.
      Winner
    • Number of bids
      0
    • Contract value
      €694,507

    Custom Assessment Criteria

    • Get answers to your bid/no-bid criteria

      Set them up once and Cobrief answers them in every tender

    Will you bid?

    The agent sets up the bid and writes the first draft. Free for 14 days.

    Previous winners

    • Who are you up against?

      The suppliers who have won similar contracts at Gas Storage Denmark A/S

    From the notice

    • Gas Storage Denmark A/S (GSD) owns and operates Denmark’s two underground gas storage facilities, which are located in Stenlille in the central part of Zealand (aquifer storage facility) and in Lille Torup in northern Jutland (salt cavern facility). GSD plans to execute the recompletion and gas fill of cavern Lille Torup 7 (To-7), which is currently brine filled. After the cavern To-7 is recompleted and the gas fill operation has taken place the installed debrining string has to be snubbed out of the cavern before the gas operation will start. To allow the gas fill to take place, the brine will be moved from cavern To-7 to cavern Lille Torup 8 (To-8). Therefore, a flooding string has to be snubbed into the cavern. The current contract concerns a snubbing unit performing the above mentioned operation.

    • Contact

      procurement@energinet.dk
    • Type
      Result · Prequalification
    • Main code
      Well-completion services
      76490000