Spare parts to gas compressors
Awarded
The competition has ended and a winner has been selected.
- Deadline
- May 26, 2025Expired
- Award
- Quality 20%
Brief
Evida Service A/S har inngått en avtale med Terotech A/S og Regaco A/S for levering av reservedeler til gasskompressorer som brukes til biometaninjeksjon ved biogassanlegg i Jylland, Fyn og Sjælland samt øyer forbundet med fastlandet via bro. Avtalen dekker reservedeler til 99 Fornovogas West - Fornovo Gas, 5 Neumann Esser, og 5 Kwangshin gasskompressorer, og er delt inn i seks delkontrakter, to for hver kompressortype. Den totale kontraktsverdien er 36,2 millioner danske kroner. Konkurransen ble evaluert basert på pris og kvalitet, med vekt på leveringstid. Det var to deltakere i konkurransen.
Result
- Regaco A/SWinner
- Terotech A/SWinner
- 2Number of tenders received
- DKK 36,200,000Contract value
Custom Assessment Criteria
Get answers to your bid/no-bid criteria
Set them up once and Cobrief answers them in every tender
Will you bid?
The agent sets up the bid and writes the first draft. Free for 14 days.
Award Criteria
Description
Price evaluated on the basis of the overall price for evaluation purposes (referred to as the "evaluation-technical price"). The overall evaluation-technical price is calculated as specified in Appendix 4 – Prices. The financial framework is lowest price + 50% (the gradient). Correction model with extension of financial framework is outlined in the Tender specifications (in short the secondary gradient is 100 % and tertiary gradient 150%)
Source
No source found in the documents. Check the weight against the tender documents.
Description
Quality evaluated on the basis of the sub-subcriteria: Average Delivery time (Working Days) from the date of purchase order to delivery, cf. Appendix 4 (100%).The percentage rates indicate the weighting of the sub-criterion and the sub-sub criteria in the tender evaluation. With regard to the qualitative sub-criterion “Quality”, each tender will be awarded points in accord-ance with a qualitative evaluation. The qualitative evaluation will be performed for each sub-sub-criterion under the qualitative sub-criterion ‘Delivery time’. The qualitative evaluation will be performed in accordance with the evaluation basis of the sub-sub-criterion in question, see above and Appendix 1 – Requirement description. ‘Delivery time’ is categorized into tiers with corresponding point ranges based on the total average delivery time (number of Working Days) offered in Appendix 4 – Prices based on the offered delivery time in Appendix 4. The contracting entity will award the number of points that corresponds to the evaluation on the descriptive scale as outlined belove and in Appendix 4 Prices. The evaluation is based on the following descriptive scale: Average delivery time for evaluation of sub criterion ‘Delivery time’ Average delivery time ≤25 Working Days = 5 points Average delivery time ≤35 Working Days = 4 points Average delivery time ≤45 Working Days = 3 points Average delivery time ≤60 Working Days = 2 points. Average delivery time ≤70 Working Days = 1 points. Average delivery time >80 Working Days = 0 points. Description of scale: Points Description 5 Excellent fulfillment of the criterion. 4 Very Good fulfillment of the criterion. 3 Good Satisfactory fulfillment of the criterion. 2 Fair fulfillment of the criterion. 1 Poor fulfillment of the criterion. 0 Unacceptable (but conditional)
Source
No source found in the documents. Check the weight against the tender documents.
Previous winners
Who are you up against?
The suppliers who have won similar contracts at Evida Service A/S
From the notice
The Contracting Authority wishes to procure spare parts related to preventive maintenance work and repair work of the Customer’s 99 Fornovogas West - Fornovo Gas gas biomethane injection compressors, 5 Neumann Esser gas biomethane injection compressors, and 5 Kwangshin gas biomethane injection compressors, cf. Appendix 6 Compressor and service overview and Appendix 4 Prices.The compressors are used for controlling the pressure when channelling biomethane gas between the low-pressure network of 4 or 7 bar(g) to the high-pressure gas network of 19 to 80 bar(g).The compressors are placed at different biogas plant sites around Jutland, Fyn and Zealand and islands connected to mainland by bridge. At most sites, two or more compressors are installed to make failover possible and to mitigate the immediate impact in case of unplanned stops and/or breakdowns.The tender is divided into six subcontracts - 2 for each compressor type.Main features of the procedureOpen
Contact
Camilla Riiscamri@evida.dk- ResultType
- 42124340Main codeParts of gas compressors
- 42124300Parts of air or vacuum pumps, of air or gas compressors