Search

  • Search


    Storage Lift System HTC

    FAIR - Facility for Antiproton and Ion Research in Europe GmbH

    Storage Lift System HTC

    1. Competition notice published

      18. mars kl. 10:4418. mars 2026 kl. 10:44
    2. Contract signed

      2. juni kl. 00:002. juni 2026 kl. 00:00
    3. Result notice published

      2. juni kl. 05:522. juni 2026 kl. 05:52

    Brief

    Germany: Tenders/FAIR - Facility for Antiproton and Ion Research in Europe GmbH/Storage Lift System HTC

    Awarded

    The competition has ended and a winner has been selected.

    Brief

    FAIR - Facility for Antiproton and Ion Research in Europe GmbH hat mit Modula GmbH eine Vereinbarung über die Lieferung eines Lagerliftsystems getroffen. Das System soll im Keller des Gebäudes K308A, der High Energy Cave (HEC) der FAIR-Anlage, in Darmstadt, Kreisfreie Stadt, installiert werden, um Bau- und Ersatzteile, Werkzeuge und andere Arbeitsmaterialien zu lagern. Der Vertrag hat eine Laufzeit von 5 Monaten und einen Wert von 89.345 €. Es wurde erwartet, dass die Einhaltung der Spezifikation und der technischen Parameter dokumentiert wird, insbesondere in Bezug auf Brandschutzkonzepte (Brandmelde- und Löschanlage) sowie den Versand- und Installationsplan.

    Result

    Winner
    Modula GmbH
    Number of bids
    3
    Contract value
    €89,345

    About the bid

      In the basement of building K308A, the High Energy Cave (HEC), part of the FAIR facility, a storage lift system is required for storing construction and spare parts, tools, and other work materials. This lift is to be delivered, assembled, and commissioned by the contractor.

      Contact phone
      +49 6159712034
      Contact email
      sg227@gsi.de
      Address
      Planckstr. 1, 64291 Darmstadt

    Custom Assessment Criteria

    Start a free trial to ask your own questions about the tender and get AI-generated answers.

    Award Criteria

    • Description

      Price

    • Description

      Compliance with the specification and the technical parameters specified therein must be documented (data sheets, technical descriptions, etc.) and submitted to-gether with the bid as a separate document (explanatory notes to the bid). In addition to completeness and level of detail, it is expected that the described concepts allow conclusions on the fulfillment of the specification.

    • Description

      Especially the fire alarm and extinguishing system must be described in detail. In addition to completeness and level of detail, it is expected that the described concepts allow conclusions on the fulfillment of the specification.

    • Description

      A short description of the production and commissioning plan is expected with regards to the given receiving and installation dates.

    Qualification requirements

    • Description

      BGB company with joint and several liability with listing of all members and their authorised representatives incl. naming of an authorised representative who shall represent the consortium in a legally binding manner vis-à-vis the Contracting authority. The tender must be accompanied by a legally binding declaration signed by all joint members that the lead firm, as authorised representative, represents the joint members listed before the Contracting authority and is jointly and severally liable, having an effect on each member, for performing the service in accordance with the contract.

      Documentation Requirement

      Mit dem Angebot; Mittels Dritterklärung

    Previous Contract Winners

    Start a free trial to see who has won similar tenders for this buyer.

    See the full notice

    Contracting authority
    FAIR - Facility for Antiproton and Ion Research in Europe GmbH
    Title
    Storage Lift System HTC
    Type
    ResultPrequalification
    Main code
    42965110Depot system
    Supplemental codes
    42000000Industrial machinery
    Location
    Darmstadt, Kreisfreie Stadt
    Duration
    5 months

    Active similar competitions

    • FAIR - Facility for Antiproton and Ion Research in Europe GmbH

      Design, Manufacture, Supply and Installation of the Liquid Nitrogen (LN2) Transfer Line System for the Super-FRS Experiment Area

      FAIR - Facility for Antiproton and Ion Research in Europe GmbH needs the design, manufacture, supply, installation, and testing of a vacuum-insulated liquid nitrogen transfer system for the Super-FRS experiment area in Darmstadt, Germany, over a duration of 12 months. The base scope includes approximately 200 m of transfer line connecting the tank area to HI/DESPEC and FHF1, with an option for an additional 120 m and one valve box for FHF2. The system must deliver 25 l/min of LN2 at 77 K, with specific pressure requirements. The contractor's scope includes thermal and hydraulic calculations, supports, thermal contraction compensation, AD 2000 and PED compliance, factory and site acceptance testing, and technical documentation. Award criteria are Price (30%), Delivery schedule concept (28%), Technical design (21%), and Installation and execution concept (21%). Qualification requirements include a Bidder Consortium Declaration, a Business and Professional Liability Declaration with a sum insured covering at least the order value, a Declaration of Availability for subcontractors, and descriptions of three comparable reference projects demonstrating experience in manufacturing vacuum insulated cryogenic transfer lines longer than 25m and experience on major construction sites, ideally at research facilities and accelerator installations. Additionally, a certificate demonstrating components designed and tested in accordance with AD 2000 and the Pressure Equipment Directive 2014/68/EU, a Self-Declaration Data Protection Requirements, and a Self-Declaration of Compliance with ISO 9001 (or equivalent) are required.

      Competition28. sep. 2026
      29. okt. 2026(20 days)
    • GSI Helmholtzzentrum für Schwerionenforschung GmbH

      Cold Terminals für SIS100 QDM

      Die GSI Helmholtzzentrum für Schwerionenforschung GmbH benötigt die Lieferung von bis zu 532 Stromadaptern (Cold Terminals) aus supraleitendem Material für den Betrieb im SIS100-Teilchenbeschleuniger in Darmstadt, mit einer Vertragslaufzeit von 24 Monaten. Diese Stromadapter sind für einen Betriebsstrom von 250 A bei ca. 4.5 K ausgelegt und verbinden die Stromzuführung aus Hochtemperatursupraleiter mit der Magnetspule. Die Fertigung erfolgt nach vom Auftraggeber bereitgestellten Zeichnungen, und jeder Adapter muss eine Werksabnahme mit Hochspannungsprüfungen und Tests in Flüssigstickstoff unter Betriebsstrom bestehen. Die Zuschlagskriterien sind Preis (40 %), technisches Konzept Fertigung (21 %), technisches Konzept Testing (21 %), Konzept zum Aufgreifen von technischen Änderungswünschen (6 %) und Lieferzeit/Verpackung (12 %). Qualifikationsanforderungen umfassen eine Betriebshaftpflichtversicherung, eine Eigenerklärung zur Einhaltung der ISO 9001 (oder gleichwertig) und die Beschreibung von drei vergleichbaren Referenzprojekten, die nachweisbare Erfahrungen mit der prozesssicheren Verarbeitung von Epoxy-Klebstoffen und der reproduzierbaren Lötung von Hochtemperatur-Supraleitern, den Umgang mit flüssigem Stickstoff und das Testen supraleitender Materialien bei tiefen Temperaturen sowie Isolationsmessungen bei Gleichspannungen bis 1500 V belegen.

      Framework agreement9. sep. 2026
      12. okt. 2026(3 days)
    • FAIR - Facility for Antiproton and Ion Research in Europe GmbH

      Elektrisk infrastruktur og veibelysning

      CPS and UPS systems for SFRS and NUSTAR

      FAIR - Facility for Antiproton and Ion Research in Europe GmbH needs CPS and UPS systems, including external battery modules, for installation in 19-inch racks along the beamline of the Super-FRS at the FAIR accelerator facility in Darmstadt, Germany. These systems are crucial for providing interference-free power and maintaining power supply during outages, as connected components are sensitive to fluctuations. The contract duration is 4 months. Suppliers must provide three comparable reference projects.

      Competition with qualification28. sep. 2026
      29. okt. 2026(20 days)
    • Städtisches Klinikum Solingen gemeinnützige GmbH

      Heisinstallasjon og vedlikehold

      Neubau Bettenhaus - Fördertechnik

      Die Städtisches Klinikum Solingen gemeinnützige GmbH benötigt Bauleistungen für die Fördertechnik/Aufzugsanlagen im Rahmen des Neubaus eines Bettenhauses mit Küche in Solingen. Der Vertrag hat eine Laufzeit von 660 Tagen. Der Zuschlag erfolgt ausschließlich auf Basis des niedrigsten Angebotspreises (100 %). Als Qualifikationsanforderungen sind 3 vergleichbare Referenzprojekte in den letzten fünf Jahren sowie Angaben zum Jahresumsatz der letzten drei Geschäftsjahre und zur durchschnittlichen jährlichen Personalstärke in den letzten drei Kalenderjahren nachzuweisen.

      Competition5. okt. 2026
      5. nov. 2026(27 days)
    • Universitätsklinikum Düsseldorf

      Heisinstallasjon og vedlikehold

      Aufzugsanlagen AWT - Sanierung Zentralküche

      Das Universitätsklinikum Düsseldorf benötigt Bauleistungen für die Sanierung von Aufzugsanlagen in der Zentralküche in Düsseldorf. Die Vergabe erfolgt auf Basis des Brutto-Angebotspreises in Euro. Als Qualifikationsanforderungen sind Referenzen über vergleichbare Lieferungen aus den letzten 3 Geschäftsjahren, Angaben zum Umsatz der letzten drei Geschäftsjahre bezogen auf vergleichbare Leistungen sowie der Nachweis einer Berufs-/Betriebshaftpflichtversicherung erforderlich.

      Competition11. sep. 2026
      13. okt. 2026(4 days)